3718-3720 S TILDEN AVE 90034
Certificate Information: 3718-3720 S TILDEN AVE 90034
- Application / Permit
- 20014-30000-05039
- Plan Check / Job No.
- B20WL04959
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel & addition to (E) 1 story SFD. Convert (E) attached garage to JADU.
- Permit Issued
- Issued on 11/10/2021
- Issuing Office
- Current Status
- CofO Issued on 5/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 12/17/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 12/22/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/1/2021 | VLADIMIR ARUTYUNYAN |
| Applicant returned to address corrections | 9/22/2021 | VLADIMIR ARUTYUNYAN |
| Plan Check Approved | 11/3/2021 | VLADIMIR ARUTYUNYAN |
| Building Plans Picked Up | 11/8/2021 | APPLICANT |
| Issued | 11/10/2021 | APPLICANT |
| CofO in Progress | 4/20/2022 | EVAN COOPER |
| CofO Issued | 5/25/2022 | DANIEL ORRANTE |
| Permit Finaled | 5/25/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/6/2021 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 5/6/2021 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 6/19/2021 | ROBERT DUFF |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 7/19/2021 | ANTHONY MAINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/29/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 12/13/2021 | Partial Approval | JOHNNY MIRANDA |
| Special/Order Compliance | 12/15/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Wood Frame | 12/15/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2022 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 1/20/2022 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 1/20/2022 | Corrections Issued | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 1/20/2022 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 1/20/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 1/25/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 1/25/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 1/25/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 1/25/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 1/27/2022 | Approved | RYAN SALAZAR |
| Shower Pan | 1/28/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/2/2022 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 2/3/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 3/30/2022 | Corrections Issued | JOHNNY MIRANDA |
| Final | 3/30/2022 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 3/30/2022 | Approved | JOHNNY MIRANDA |
| Green Building Final | 3/30/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 3/30/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 3/30/2022 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 3/30/2022 | SGSOV Approved | JOHNNY MIRANDA |
| Smoke Detectors | 3/30/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 4/5/2022 | Approved | JOHNNY MIRANDA |
| Final | 4/5/2022 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 4/5/2022 | Approved | JOHNNY MIRANDA |
| Service/Power Release | 4/5/2022 | Approved | JOHNNY MIRANDA |
| Final | 4/19/2022 | OK to Issue CofO | EVAN COOPER |