6550 N DE CELIS PL 91406

Certificate Information: 6550 N DE CELIS PL 91406

Application / Permit
20014-30000-05038
Plan Check / Job No.
B20WL04958
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Master bedroom/bath addition to rear of (E) sfd. Interior remodel.
Permit Issued
Issued on 3/16/2021
Issuing Office
Current Status
CofO Issued on 3/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 RICHARD GARCIA
Corrections Issued 11/27/2020 RICHARD GARCIA
Plan Check Approved 1/27/2021 JAHANSHAH POURHASSAN
Building Plans Picked Up 2/2/2021 APPLICANT
Issued 3/16/2021 APPLICANT
CofO in Progress 3/10/2023 RAUL OLAGI
CofO Issued 3/29/2023 MICHAEL SMITH
Permit Finaled 3/29/2023 MICHAEL SMITH

Permit Application Clearance Information

ZI Cleared 12/3/2020 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 12/10/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 12/10/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 12/10/2020 JOHN TRIANTAFYLLOS
ZI Cleared 1/5/2021 MIGUEL GAMBOA

Contact Information

Contractor Ramz Co Const; Lic. No.: 458540-B 4907 LA MADERA AVE      EL MONTE, CA 91733
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/12/2021 Approved ARTHUR SARGSYAN
Wood Frame 5/25/2021 Partial Approval ARTHUR SARGSYAN
Underground Mechanical 6/1/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 6/18/2021 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 6/18/2021 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 6/23/2021 Corrections Issued JACK KARGODORIAN
Green Building Rough 6/23/2021 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Approved JACK KARGODORIAN
Deputy Drilled-In Anchors 7/12/2021 Conditional Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 7/13/2021 Approved JACK KARGODORIAN
ELECTRICAL-Rough 7/13/2021 Approved JACK KARGODORIAN
Green Building Rough 7/13/2021 Approved JACK KARGODORIAN
HVAC-Rough 7/13/2021 Approved JACK KARGODORIAN
PLUMBING-Rough 7/13/2021 Approved JACK KARGODORIAN
Insulation 7/19/2021 Approved JAVIER RAMOS JR
Drywall Nailing 7/22/2021 Approved ALAN MORELOS
Interior/Exterior Lathing 8/6/2021 No Access for Inspection AMY COLIN
Interior/Exterior Lathing 8/10/2021 Corrections Issued DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 9/21/2021 Approved JACK KARGODORIAN
Final 11/12/2021 Corrections Issued RAUL OLAGI
Green Building Final 11/12/2021 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 11/12/2021 SGSOV Approved RAUL OLAGI
Smoke Detectors 11/12/2021 Approved RAUL OLAGI
Final 12/3/2021 Corrections Issued RAUL OLAGI
Green Building Final 12/3/2021 Corrections Issued RAUL OLAGI
Final 3/10/2023 OK to Issue CofO RAUL OLAGI
Green Building Final 3/10/2023 Approved RAUL OLAGI