18615 W LANARK ST 91335
Certificate Information: 18615 W LANARK ST 91335
- Application / Permit
- 20014-30000-04971
- Plan Check / Job No.
- B20WL04887
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Bedroom addition to existing SFD.
- Permit Issued
- Issued on 4/19/2021
- Issuing Office
- Current Status
- CofO Issued on 9/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2020 | MANUEL GARCIA |
| Corrections Issued | 12/3/2020 | MANUEL GARCIA |
| Plan Check Approved | 1/25/2021 | RICHARD GARCIA |
| Building Plans Picked Up | 1/26/2021 | APPLICANT |
| Issued | 4/19/2021 | APPLICANT |
| CofO in Progress | 8/16/2022 | JEFFREY BULL |
| CofO Issued | 9/30/2022 | JOHN JANSON |
| Permit Finaled | 9/30/2022 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/4/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/4/2021 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/4/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Jencor Construction Inc; Lic. No.: 968170-B | 19528 VENTURA BLVD 273 TARZANA, CA 91356 |
| Engineer | Herrera,, Edgar E; Lic. No.: C67603 | 1929 GREENLEAF DR WEST COVINA, CA 91792 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/6/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 12/23/2021 | Approved | VINCENT HANLEY |
| Pre-Inspection | 12/23/2021 | Approved | VINCENT HANLEY |
| Sewer | 12/23/2021 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 1/21/2022 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 1/21/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/19/2022 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/19/2022 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/31/2022 | Approved | MORRIS JACKSON |
| HVAC-Rough | 5/31/2022 | Approved | MORRIS JACKSON |
| Shower Pan | 5/31/2022 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 6/10/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 6/10/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 6/10/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 6/10/2022 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 6/17/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/17/2022 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 8/15/2022 | Approved | JEFFREY BULL |
| Final | 8/15/2022 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 8/15/2022 | Approved | JEFFREY BULL |
| HVAC-Final | 8/15/2022 | Approved | JEFFREY BULL |
| PLUMBING-Final | 8/15/2022 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 8/15/2022 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 8/15/2022 | Approved | JEFFREY BULL |