542 N SAN BENITO ST 90033

Certificate Information: 542 N SAN BENITO ST 90033

Application / Permit
20014-30000-04969
Plan Check / Job No.
B20WL04884
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition and conversion of (E) garage to accessory dwelling unit with new roof framing per GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
Permit Issued
Issued on 3/18/2021
Issuing Office
Current Status
CofO Issued on 11/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2020 APPLICANT
Assigned to Plan Check Engineer 11/17/2020 RICHARD GARCIA
Corrections Issued 11/21/2020 RICHARD GARCIA
Applicant returned to address corrections 1/15/2021 RICHARD GARCIA
Building Plans Picked Up 1/19/2021 APPLICANT
Plan Check Approved 2/19/2021 JASON JANGADA
Issued 3/18/2021 APPLICANT
CofO in Progress 10/29/2021 OSVALDO PARAMO
CofO in Progress 10/29/2021 OSVALDO PARAMO
Permit Finaled 11/5/2021 DEROLD HAUFF
Permit Finaled 11/5/2021 DEROLD HAUFF
CofO Issued 11/5/2021 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 12/2/2020 ISMAEL HERNANDEZ
Address approval Cleared 12/4/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 12/7/2020 JUAN ASHTON
Sewer availability Cleared 12/8/2020 JUAN ASHTON
ZI Cleared 12/10/2020 SARAHI ORTEGA
ZI Cleared 12/10/2020 SARAHI ORTEGA
ZI Cleared 12/10/2020 SARAHI ORTEGA
Grading Pre-Inspection Cleared 12/18/2020 BRIAN MILLER
Roof/Waste drainage to street Cleared 12/18/2020 JUAN ASHTON

Contact Information

Contractor Jkc Construction & Design; Lic. No.: 1007078-B 18880 WELLS DRIVE      TARZANA, CA 91356
Engineer Chavez,, Eduardo; Lic. No.: C76372 437 ARCADIA WAY      WALNUT, CA 91789

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/24/2021 Approved OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/15/2021 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/27/2021 Approved OSVALDO PARAMO
Footing/Foundation/Slab 4/27/2021 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 5/17/2021 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 5/19/2021 Approved OSVALDO PARAMO
Green Building Rough 5/19/2021 Approved OSVALDO PARAMO
MERV13>=Rough 5/19/2021 Approved OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 5/19/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 5/25/2021 Partial Approval THOMAS LOGRASSO
Interior/Exterior Lathing 6/10/2021 Partial Approval OSVALDO PARAMO
Insulation 6/18/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Drywall Nailing 6/24/2021 Approved WILLIAM WREN
Insulation 6/24/2021 Approved WILLIAM WREN
Interior/Exterior Lathing 7/15/2021 Approved JESUS PINEDA
Underground Mechanical 7/29/2021 Partial Approval SCOTT FINNILA
Final 9/9/2021 Corrections Issued OSVALDO PARAMO
Green Building Final 9/9/2021 Approved OSVALDO PARAMO
MERV13>=Final 9/9/2021 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/9/2021 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 9/9/2021 Not Ready for Inspection OSVALDO PARAMO
Final 9/14/2021 OK to Issue CofO OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/14/2021 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 9/14/2021 Approved OSVALDO PARAMO
Service/Power Release 9/20/2021 Approved OSVALDO PARAMO