1541 N RISING GLEN ROAD 90069

Certificate Information: 1541 N RISING GLEN ROAD 90069

Application / Permit
20014-30000-04949
Plan Check / Job No.
B20WL04854
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel of (E) 1-story SFD with addition to the side, re-roof the area adjacent to the proposed addition in the front of the dwelling and (N) uncovered raised wood deck at the rear.
Permit Issued
Issued on 7/26/2021
Issuing Office
Current Status
CofO Issued on 4/19/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 KAVIAN REFAHI
Corrections Issued 11/14/2020 KAVIAN REFAHI
Building Plans Picked Up 11/17/2020 APPLICANT
Applicant returned to address corrections 5/20/2021 DAVID CASTILLO
Applicant returned to address corrections 6/15/2021 JAHANSHAH POURHASSAN
Applicant returned to address corrections 6/24/2021 JAHANSHAH POURHASSAN
Plan Check Approved 7/23/2021 JAHANSHAH POURHASSAN
Issued 7/26/2021 APPLICANT
CofO in Progress 4/19/2024 RAUL BARAJAS
Permit Finaled 4/19/2024 RONALD MYRICK
CofO Issued 4/19/2024 RONALD MYRICK
Permit Finaled 4/19/2024 RONALD MYRICK

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/1/2020 VASIL MIHALEV
Low Impact Development Cleared 5/7/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/13/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 5/17/2021 WALLIE JONG

Contact Information

Architect Verdugo,, Emilio Amado; Lic. No.: C33263 4324 GRANDVIEW BLVD      LOS ANGELES, CA 90066
Contractor So Cal Kitchen Bath Inc; Lic. No.: 1026689-B 14007 PALAWAN WAY UNIT 36      MARINA DEL REY, CA 90292
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/20/2021 Approved RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 9/15/2021 Partial Approval RICHARD STEINBACH
Wood Frame 9/15/2021 Corrections Issued RICHARD STEINBACH
Shower Pan 9/22/2021 Approved RICHARD STEINBACH
ELECTRICAL-Rough 9/24/2021 Approved RICHARD STEINBACH
PLUMBING-Rough 9/24/2021 Not Ready for Inspection RICHARD STEINBACH
HVAC-Rough 10/4/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 10/4/2021 Approved RAUL BARAJAS
Gas Test 10/8/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 11/1/2021 Not Ready for Inspection RAUL BARAJAS
Insulation 11/9/2021 Corrections Issued RAUL BARAJAS
Insulation 11/22/2021 Partial Approval RAUL BARAJAS
Drywall Nailing 12/15/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 12/20/2021 Approved RAUL BARAJAS
Service/Power Release 4/22/2022 Not Ready for Inspection RAUL BARAJAS
BUILDING-Rough-Frame 7/21/2022 Approved RAUL BARAJAS
Final 7/21/2022 Not Ready for Inspection RAUL BARAJAS
Green Building Final 7/21/2022 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 7/21/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 7/21/2022 SGSOV Approved RAUL BARAJAS
Service/Power Release 7/21/2022 Not Ready for Inspection RAUL BARAJAS
Smoke Detectors 7/21/2022 Approved RAUL BARAJAS
Final 8/8/2022 Corrections Issued RAUL BARAJAS
Green Building Final 8/8/2022 Approved RAUL BARAJAS
Final 9/28/2022 Conditional Approval RAUL BARAJAS
Service/Power Release 9/28/2022 No Access for Inspection RAUL BARAJAS
Service/Power Release 9/29/2022 Approved RAUL BARAJAS
Final 4/18/2024 OK to Issue CofO RAUL BARAJAS