11006 W CASHMERE ST 90049
Certificate Information: 11006 W CASHMERE ST 90049
- Application / Permit
- 20014-30000-04946
- Plan Check / Job No.
- B20WL04852
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND 2-STORY ADDITION TO (E) SINGLE STORY SFD W./ ATT. 2-CAR GARAGE.
- Permit Issued
- Issued on 1/13/2021
- Issuing Office
- Current Status
- CofO Issued on 7/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2020 | REZA HAGHIGHAT |
| Corrections Issued | 11/16/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 11/25/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 1/13/2021 | REZA HAGHIGHAT |
| Issued | 1/13/2021 | APPLICANT |
| Building Plans Picked Up | 1/13/2021 | APPLICANT |
| CofO in Progress | 7/17/2023 | MICHAEL PELHAM |
| Permit Finaled | 7/17/2023 | DANIEL ORRANTE |
| CofO Issued | 7/17/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/17/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Watercourse | Cleared | 11/19/2020 | MAHELET GEBEYHU |
| Specific Plan | Cleared | 12/2/2020 | FREDDY GARCIA |
| Address approval | Cleared | 12/3/2020 | DINAH GARIN |
| Permit | Cleared | 12/3/2020 | DINAH GARIN |
| ZA Case | Cleared | 12/3/2020 | DENZEL HENDERSON |
| Low Impact Development | Cleared | 12/10/2020 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 12/11/2020 | DINAH GARIN |
| Sewer availability | Cleared | 12/11/2020 | DINAH GARIN |
| Trees in Parkway | Cleared | 12/28/2020 | JOHN KIM |
| GPI Written Notices | Cleared | 1/13/2021 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 1/13/2021 | REZA HAGHIGHAT |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Bookie Development Inc; Lic. No.: 977585-B | 10509 CLARKSON ROAD LOS ANGELES, CA 90064 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/21/2021 | Approved | CARLOS MATAMOROS |
| Pre-Inspection | 3/23/2021 | Approved | CARLOS MATAMOROS |
| FLOOD-Elevation Certificate | 6/11/2021 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 6/11/2021 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 6/17/2021 | Partial Approval | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 7/6/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| FLOOD-Proofing Certificate | 7/6/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 7/6/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 7/6/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Wood Frame | 7/6/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 7/8/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 7/8/2021 | Partial Approval | CARLOS MATAMOROS |
| Wood Frame | 7/8/2021 | Partial Approval | CARLOS MATAMOROS |
| PLUMBING-Rough | 7/9/2021 | No Access for Inspection | CARLOS MATAMOROS |
| Wood Frame | 7/9/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2021 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2021 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2021 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2021 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 10/14/2021 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2021 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 11/15/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/15/2021 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 12/3/2021 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2021 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/7/2022 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 1/7/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 1/11/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 1/28/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 2/16/2022 | Corrections Issued | CARLOS MATAMOROS |
| FLOOD-Proofing Certificate | 2/16/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 2/16/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 2/18/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 3/10/2022 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 3/22/2022 | Approved | CARLOS MATAMOROS |
| Shower Pan | 4/12/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 5/3/2022 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 5/3/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/17/2022 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 4/14/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 4/14/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Gas Test | 4/18/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 5/1/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 5/1/2023 | Corrections Issued | CARLOS MATAMOROS |
| HVAC-Final | 5/10/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 5/11/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 5/17/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 7/5/2023 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 7/5/2023 | Approved | CARLOS MATAMOROS |
| Green Building Final | 7/5/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 7/5/2023 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 7/5/2023 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 7/5/2023 | Approved | CARLOS MATAMOROS |