4006 S 2ND AVE 90008

Certificate Information: 4006 S 2ND AVE 90008

Application / Permit
20014-30000-04933
Plan Check / Job No.
B20WL04840
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW LAUNDRY ROOM & PORCH ADDITION TO THE SIDE OF AN (E) ADU PER WFPP AT REAR OF THE LOT.
Permit Issued
Issued on 10/18/2021
Issuing Office
Current Status
CofO Issued on 7/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2020 APPLICANT
Assigned to Plan Check Engineer 11/13/2020 JASON JANGADA
Corrections Issued 11/13/2020 JASON JANGADA
Applicant returned to address corrections 12/22/2020 JAHANSHAH POURHASSAN
Building Plans Picked Up 12/23/2020 APPLICANT
Applicant returned to address corrections 2/18/2021 ALFREDO JARA
Plan Check Approved 10/15/2021 MANUEL GARCIA
Issued 10/18/2021 APPLICANT
CofO in Progress 7/17/2024 CRAIG DAVIS
CofO Issued 7/24/2024 DEROLD HAUFF
Permit Finaled 7/24/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/24/2020 KATHLEEN LEE
Roof/Waste drainage to street Cleared 11/24/2020 KATHLEEN LEE
Construction near power lines Cleared 7/19/2021 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/29/2023 Approved ANTHONY EGSON
BUILDING-Rough-Frame 7/16/2024 Approved CRAIG DAVIS
ELECTRICAL-Final 7/16/2024 Approved CRAIG DAVIS
Final 7/16/2024 OK to Issue CofO CRAIG DAVIS
Footing/Foundation/Slab 7/16/2024 Approved CRAIG DAVIS
Green Building Final 7/16/2024 Approved CRAIG DAVIS
Green Building Rough 7/16/2024 Approved CRAIG DAVIS
HVAC-Final 7/16/2024 Approved CRAIG DAVIS
PLUMBING-Final 7/16/2024 Approved CRAIG DAVIS
Smoke Detectors 7/16/2024 Approved CRAIG DAVIS