8019 S CHASE AVE 90045
Certificate Information: 8019 S CHASE AVE 90045
- Application / Permit
- 20014-30000-04932
- Plan Check / Job No.
- B20WL04839
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERSION OF AN (E) GARAGE INTO AN ADU.
- Permit Issued
- Issued on 5/17/2021
- Issuing Office
- Current Status
- CofO Issued on 3/7/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | RICHARD GARCIA |
| Corrections Issued | 11/15/2020 | RICHARD GARCIA |
| Building Plans Picked Up | 3/2/2021 | APPLICANT |
| Applicant returned to address corrections | 3/5/2021 | RICHARD GARCIA |
| Plan Check Approved | 4/28/2021 | RICHARD GARCIA |
| Issued | 5/17/2021 | APPLICANT |
| CofO in Progress | 2/7/2022 | BOBBY KEY |
| Permit Finaled | 3/7/2022 | DANIEL ORRANTE |
| CofO Issued | 3/7/2022 | DANIEL ORRANTE |
| Permit Finaled | 3/7/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/1/2020 | DINAH GARIN |
| ZI | Cleared | 12/1/2020 | DENZEL HENDERSON |
| ZI | Cleared | 12/1/2020 | DENZEL HENDERSON |
| ZI | Cleared | 12/1/2020 | DENZEL HENDERSON |
| Roof/Waste drainage to street | Cleared | 12/2/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2020 | DINAH GARIN |
| Sewer availability | Cleared | 12/4/2020 | DINAH GARIN |
| Specific Plan | Cleared | 12/10/2020 | VALERIA CEJA |
| Green Code | Cleared | 3/8/2021 | RICHARD GARCIA |
| Construction near power lines | Cleared | 3/10/2021 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 4/24/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/13/2021 | Partial Approval | BRENDAN LOONEY |
| Sewer | 7/21/2021 | Approved | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 7/29/2021 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 7/29/2021 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 8/4/2021 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 8/13/2021 | Approved | BRENDAN LOONEY |
| Underground Mechanical | 8/13/2021 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2021 | Conditional Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/23/2021 | Partial Approval | BRENDAN LOONEY |
| Rough-Elec/Plmb/HVAC | 9/29/2021 | Conditional Approval | BRENDAN LOONEY |
| Insulation | 10/6/2021 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 10/13/2021 | Partial Approval | JOHNNY MIRANDA |
| Drywall Nailing | 10/15/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 1/24/2022 | Approved | BOBBY KEY |
| Final | 1/24/2022 | Corrections Issued | BOBBY KEY |
| Gas Test | 1/24/2022 | Approved | BOBBY KEY |
| Green Building Final | 1/24/2022 | Not Ready for Inspection | BOBBY KEY |
| Green Building Rough | 1/24/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 1/24/2022 | Approved | BOBBY KEY |
| MERV13>=Rough | 1/24/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 1/24/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 1/24/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 2/3/2022 | Approved | BOBBY KEY |
| Green Building Final | 2/3/2022 | Approved | BOBBY KEY |
| HVAC-Final | 2/3/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 2/3/2022 | Approved | BOBBY KEY |
| Final | 2/7/2022 | OK to Issue CofO | BOBBY KEY |