3020 S KELTON AVE 90034
Certificate Information: 3020 S KELTON AVE 90034
- Application / Permit
- 20014-30000-04889
- Plan Check / Job No.
- B20WL04810
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- addition/remdodel to (e) 1-story s.f.d.
- Permit Issued
- Issued on 6/25/2021
- Issuing Office
- Current Status
- CofO Issued on 7/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 11/16/2020 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 11/16/2020 | CHIHARU SUZUKI |
| Building Plans Picked Up | 11/19/2020 | APPLICANT |
| Applicant returned to address corrections | 4/27/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 5/4/2021 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 5/29/2021 | KAMRAN GHOTBI RAVANDI |
| Issued | 6/25/2021 | APPLICANT |
| CofO in Progress | 7/21/2022 | KENNETH NAGLE |
| Permit Finaled | 7/23/2022 | DANIEL ORRANTE |
| CofO Issued | 7/23/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/23/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 1/12/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2021 | DINAH GARIN |
| Low Impact Development | Cleared | 3/26/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 4/1/2021 | ANTHONY MAINEZ |
Contact Information
| Contractor | Stregan Group Ltd; Lic. No.: 962579-B | 5739 KANAN RD #255 AGOURA HILLS, CA 91301 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/1/2021 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/14/2021 | Partial Approval | EVAN COOPER |
| Wood Frame | 7/14/2021 | Corrections Issued | EVAN COOPER |
| Deputy Drilled-In Anchors | 9/14/2021 | Conditional Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2021 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 11/23/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Rough | 11/23/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 11/23/2021 | Approved | JOHNNY MIRANDA |
| MERV13>=Rough | 11/23/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 11/23/2021 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 11/29/2021 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 11/30/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 11/30/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 11/30/2021 | Approved | JOHNNY MIRANDA |
| HVAC-Rough | 11/30/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 11/30/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 11/30/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Insulation | 12/3/2021 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 12/9/2021 | Approved | EVAN COOPER |
| Insulation | 12/9/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 12/9/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 12/13/2021 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 2/9/2022 | Approved | JOHNNY MIRANDA |
| Final | 5/11/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Green Building Final | 5/11/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| MERV13>=Final | 5/11/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 5/11/2022 | SGSOV Not Ready | JOHNNY MIRANDA |
| Smoke Detectors | 5/11/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| ELECTRICAL-Final | 6/3/2022 | Approved | JOHNNY MIRANDA |
| HVAC-Final | 6/3/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 6/3/2022 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Final | 7/11/2022 | Approved | EVAN COOPER |
| Final | 7/11/2022 | Conditional Approval | EVAN COOPER |
| Green Building Final | 7/11/2022 | Approved | EVAN COOPER |
| HVAC-Final | 7/11/2022 | Approved | EVAN COOPER |
| MERV13>=Final | 7/11/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 7/11/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 7/11/2022 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 7/11/2022 | Approved | EVAN COOPER |