2700 S COLBY AVE 90064

Certificate Information: 2700 S COLBY AVE 90064

Application / Permit
20014-30000-04883
Plan Check / Job No.
B20WL04803
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New covered porch addition, ground floor addition, and interior remodel to (E) SFD with attached garage
Permit Issued
Issued on 3/1/2021
Issuing Office
Current Status
CofO Issued on 3/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/10/2020 APPLICANT
Assigned to Plan Check Engineer 11/17/2020 JASON JANGADA
Corrections Issued 11/17/2020 JASON JANGADA
Building Plans Picked Up 11/19/2020 APPLICANT
Plan Check Approved 12/16/2020 KAVIAN REFAHI
Issued 3/1/2021 APPLICANT
CofO in Progress 3/3/2022 JOHNNY MIRANDA
CofO in Progress 3/4/2022 JOHNNY MIRANDA
Permit Finaled 3/17/2022 DANIEL ORRANTE
CofO Issued 3/17/2022 DANIEL ORRANTE
Permit Finaled 3/17/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 11/30/2020 PEDRO AYALA
Roof/Waste drainage to street Cleared 12/3/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 12/8/2020 DINAH GARIN

Contact Information

Contractor Mary Construction; Lic. No.: 852310-B 4814 TOPEKA DRIVE      TARZANA, CA 91356
Engineer Mezey,, Steven William; Lic. No.: S2665 14017 HARTSOOK ST      SHERMAN OAKS, CA 91423

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/28/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 7/2/2021 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 7/28/2021 Partial Approval OGANES TARAKHCHYAN
HVAC-Rough 7/28/2021 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 7/28/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Wood Frame 7/28/2021 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/5/2021 Approved OGANES TARAKHCHYAN
Green Building Rough 8/5/2021 Approved OGANES TARAKHCHYAN
HVAC-Rough 8/5/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 8/5/2021 Partial Approval OGANES TARAKHCHYAN
PLUMBING-Rough 8/5/2021 Approved OGANES TARAKHCHYAN
Insulation 8/11/2021 Approved ANTHONY MCDOWALL
Drywall Nailing 9/15/2021 Approved JESUS RODRIGUEZ
Shower Pan 9/28/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/30/2021 Approved EVAN COOPER
ELECTRICAL-Final 2/7/2022 Corrections Issued JOHNNY MIRANDA
Final 2/7/2022 Corrections Issued JOHNNY MIRANDA
Green Building Final 2/7/2022 Corrections Issued JOHNNY MIRANDA
HVAC-Final 2/7/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 2/7/2022 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 2/7/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 2/7/2022 Approved JOHNNY MIRANDA
Final 3/1/2022 OK to Issue CofO JOHNNY MIRANDA
Green Building Final 3/1/2022 Approved JOHNNY MIRANDA