15004 W GREENLEAF ST 91403
Certificate Information: 15004 W GREENLEAF ST 91403
- Application / Permit
- 20014-30000-04882
- Plan Check / Job No.
- B20WL04802
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel and 2-story addition to (e) single story SFD w./ att. 2-car garage with roof trusses
- Permit Issued
- Issued on 2/5/2021
- Issuing Office
- Current Status
- CofO Issued on 8/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2020 | REZA HAGHIGHAT |
| Corrections Issued | 11/25/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 12/4/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 2/2/2021 | REZA HAGHIGHAT |
| Issued | 2/5/2021 | APPLICANT |
| Building Plans Picked Up | 2/8/2021 | APPLICANT |
| CofO in Progress | 12/16/2021 | JACK KARGODORIAN |
| Permit Finaled | 8/16/2022 | DEROLD HAUFF |
| CofO Issued | 8/16/2022 | DEROLD HAUFF |
| Permit Finaled | 8/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 12/17/2020 | LOUIS ORTEGA |
| Trees in Parkway | Cleared | 12/22/2020 | JOHN KIM |
| Low Impact Development | Cleared | 1/8/2021 | SARAH YOUSSEF |
| Permit | Cleared | 1/12/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 1/12/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 1/13/2021 | GABRIEL ROBLES |
| GPI Written Notices | Cleared | 2/2/2021 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 2/2/2021 | REZA HAGHIGHAT |
Contact Information
| Architect | Niemerski,, Kenneth Chester; Lic. No.: C23971 | 52 DAWNWOOD LADERA RANCH, CA 92694 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
| Engineer | Toedter,, Randy W; Lic. No.: S2991 | 7474 EISENHOWER ST VENTURA, CA 93003 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/18/2021 | Partial Approval | CHARLES POWELL |
| PLUMBING-Rough | 3/26/2021 | Corrections Issued | MARK JOHNSON |
| Underground Mechanical | 3/26/2021 | Partial Approval | MARK JOHNSON |
| PLUMBING-Rough | 3/31/2021 | Partial Approval | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 4/5/2021 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 4/5/2021 | Partial Approval | CHARLES POWELL |
| Special/Order Compliance | 4/20/2021 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2021 | Partial Approval | CHARLES POWELL |
| ELECTRICAL-Rough | 6/2/2021 | Not Ready for Inspection | MARK JOHNSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2021 | Not Ready for Inspection | MARK JOHNSON |
| HVAC-Rough | 6/2/2021 | Not Ready for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 6/2/2021 | Not Ready for Inspection | MARK JOHNSON |
| BUILDING-Rough-Frame | 6/7/2021 | Not Ready for Inspection | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/7/2021 | Not Ready for Inspection | CHARLES POWELL |
| ELECTRICAL-Rough | 6/8/2021 | Partial Approval | CHARLES POWELL |
| HVAC-Rough | 6/8/2021 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 6/8/2021 | Approved | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| Green Building Rough | 6/15/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| Rough-Elec/Plmb/HVAC | 6/15/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 6/21/2021 | Approved | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 6/22/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Rough | 6/22/2021 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 6/23/2021 | Conditional Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2021 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 6/25/2021 | Conditional Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2021 | Approved | CHARLES POWELL |
| Green Building Rough | 7/22/2021 | Not Ready for Inspection | CHARLES POWELL |
| Wood Frame | 7/22/2021 | Not Ready for Inspection | CHARLES POWELL |
| Interior/Exterior Lathing | 7/28/2021 | Partial Approval | ALAN MORELOS |
| Green Building Rough | 8/10/2021 | Approved | CHARLES POWELL |
| Shower Pan | 8/10/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 8/20/2021 | Partial Approval | DANIEL DREW |
| BUILDING-Rough-Frame | 8/24/2021 | Approved | CHARLES POWELL |
| Insulation | 8/24/2021 | Approved | CHARLES POWELL |
| Drywall Nailing | 8/31/2021 | Approved | CHARLES POWELL |
| Insulation | 8/31/2021 | Approved | CHARLES POWELL |
| Pre-Inspection | 8/31/2021 | Partial Approval | AMY COLIN |
| Pre-Inspection | 8/31/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| Special/Order Compliance | 8/31/2021 | Partial Inspection | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 9/20/2021 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 11/30/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Final | 11/30/2021 | Approved | JACK KARGODORIAN |
| HVAC-Final | 11/30/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| PLUMBING-Final | 11/30/2021 | Corrections Issued | JACK KARGODORIAN |
| Pre-Inspection | 12/3/2021 | Partial Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Final | 12/8/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 12/8/2021 | Corrections Issued | JACK KARGODORIAN |
| Footing/Foundation/Slab | 12/8/2021 | Approved | JACK KARGODORIAN |
| HVAC-Final | 12/8/2021 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 12/8/2021 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 12/8/2021 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 12/8/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Smoke Detectors | 12/8/2021 | Approved | JACK KARGODORIAN |
| Service/Power Release | 12/9/2021 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Final | 12/13/2021 | Approved | JACK KARGODORIAN |
| Service/Power Release | 12/13/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Final | 12/16/2021 | OK to Issue CofO | JACK KARGODORIAN |
| Service/Power Release | 12/16/2021 | Approved | JACK KARGODORIAN |