1438 N SAN YSIDRO DR 90210
Certificate Information: 1438 N SAN YSIDRO DR 90210
- Application / Permit
- 20014-30000-04880
- Plan Check / Job No.
- B20WL04798
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition of 1 bedroom to second floor of existing single family residence.
- Permit Issued
- Issued on 5/4/2021
- Issuing Office
- Current Status
- CofO Issued on 6/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | RICHARD GARCIA |
| Corrections Issued | 11/15/2020 | RICHARD GARCIA |
| Building Plans Picked Up | 11/16/2020 | APPLICANT |
| Applicant returned to address corrections | 2/18/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 3/30/2021 | MARJAN SHENASI |
| Plan Check Approved | 4/20/2021 | RICHARD GARCIA |
| Issued | 5/4/2021 | APPLICANT |
| CofO in Progress | 6/1/2023 | STEPHANIE SWANSON |
| Permit Finaled | 6/5/2023 | DANIEL ORRANTE |
| CofO Issued | 6/5/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/5/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZI | Cleared | 3/1/2021 | DENZEL HENDERSON |
| ZI | Cleared | 3/1/2021 | DENZEL HENDERSON |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2021 | TRACY TATE |
| Roof/Waste drainage to street | Cleared | 3/9/2021 | TRACY TATE |
| Sewer availability | Cleared | 3/9/2021 | TRACY TATE |
| Grading Pre-Inspection | Cleared | 3/30/2021 | RICHARD GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khanlou,, Amir; Lic. No.: C87550 | 10671 HOLMAN AVE APT 207 LOS ANGELES, CA 90024 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/8/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Deputy Drilled-In Anchors | 11/4/2022 | Approved | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 11/4/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 11/4/2022 | Partial Approval | MICHAEL PELHAM |
| Pre-Inspection | 11/28/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 12/15/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Drilled-In Anchors | 12/16/2022 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 2/1/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 2/1/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 2/1/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 2/1/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 2/1/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 2/7/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 2/7/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 2/7/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 3/22/2023 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 3/22/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 3/22/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 3/24/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 3/28/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 3/30/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 5/16/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 5/16/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 5/16/2023 | Corrections Issued | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 5/16/2023 | Approved | CARLOS MATAMOROS |
| Green Building Final | 5/16/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 5/16/2023 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 5/16/2023 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 5/16/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 5/16/2023 | SGSOV Not Ready | CARLOS MATAMOROS |
| Smoke Detectors | 5/16/2023 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 6/1/2023 | Approved | STEPHANIE SWANSON |
| Final | 6/1/2023 | OK to Issue CofO | STEPHANIE SWANSON |
| Green Building Final | 6/1/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 6/1/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 6/1/2023 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 6/1/2023 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 6/1/2023 | Approved | STEPHANIE SWANSON |