1922 S CRESCENT HEIGHTS BLVD 90034

Certificate Information: 1922 S CRESCENT HEIGHTS BLVD 90034

Application / Permit
20014-30000-04859
Plan Check / Job No.
B20WL04790
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION, NEW PORCH, REMODELING INTERIOR WALLS
Permit Issued
Issued on 4/22/2021
Issuing Office
Current Status
CofO Issued on 2/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2020 APPLICANT
Assigned to Plan Check Engineer 12/2/2020 TARIK SAOUD
Corrections Issued 12/16/2020 TARIK SAOUD
Quality Review Completed 12/23/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 12/28/2020 APPLICANT
Plan Check Approved 4/15/2021 TARIK SAOUD
Issued 4/22/2021 APPLICANT
CofO in Progress 1/21/2022 JOSE AVILA
CofO Issued 2/1/2022 DEROLD HAUFF
Permit Finaled 2/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 3/8/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 3/10/2021 JEANIE LAM
Low Impact Development Cleared 4/7/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 4/7/2021 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/26/2021 Partial Approval SCOTT FINNILA
Underground Mechanical 5/3/2021 Partial Approval SCOTT FINNILA
Wood Frame 5/3/2021 Partial Approval SCOTT FINNILA
PLUMBING-Rough 5/11/2021 Not Ready for Inspection STUART CHAPMAN
Wood Frame 5/11/2021 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/17/2021 Partial Inspection SCOTT FINNILA
PLUMBING-Rough 5/17/2021 Partial Inspection SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/24/2021 Partial Approval CHRIS CHRISTENSEN
Deputy Wood Construction 5/25/2021 No Access for Inspection ELMER BLAND
ELECTRICAL-Rough 5/25/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 5/25/2021 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/28/2021 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 6/4/2021 Corrections Issued SCOTT FINNILA
HVAC-Rough 6/4/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 6/4/2021 Partial Inspection SCOTT FINNILA
BUILDING-Rough-Frame 6/8/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 6/8/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 6/8/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 6/8/2021 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 6/8/2021 Corrections Issued STUART CHAPMAN
HVAC-Rough 6/10/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 6/15/2021 Partial Approval STUART CHAPMAN
Shower Pan 6/22/2021 Approved CHRIS CHRISTENSEN
Insulation 6/23/2021 Not Ready for Inspection BENEVA JACKSON
Insulation 6/24/2021 Not Ready for Inspection CALEB MEISTER
Insulation 6/29/2021 Corrections Issued BENEVA JACKSON
Insulation 7/20/2021 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 8/9/2021 Approved STUART CHAPMAN
Green Building Rough 8/9/2021 Approved STUART CHAPMAN
PLUMBING-Rough 8/9/2021 Approved STUART CHAPMAN
Insulation 8/11/2021 Conditional Approval ADAM ESCOTO
Drywall Nailing 8/16/2021 Approved CALEB MEISTER
Drywall Nailing 8/17/2021 Approved CALEB MEISTER
Interior/Exterior Lathing 8/17/2021 Approved CALEB MEISTER
Special/Order Compliance 10/22/2021 No Access for Inspection HECTOR ALIKHAN
Special/Order Compliance 11/4/2021 Approved ALIZAH MAYAGOITIA
Special/Order Compliance 11/5/2021 Approved LILIANA PORTILLO
Deputy Drilled-In Anchors 11/17/2021 Conditional Approval JOSE AVILA
ELECTRICAL-Final 11/23/2021 Approved JOSE AVILA
HVAC-Final 11/23/2021 Approved JOSE AVILA
PLUMBING-Final 11/23/2021 Approved JOSE AVILA
Final 1/3/2022 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 1/3/2022 Approved JOSE AVILA
Green Building Final 1/3/2022 Partial Approval JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/3/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 1/3/2022 Approved JOSE AVILA
Final 1/13/2022 Corrections Issued JOSE AVILA
Green Building Final 1/13/2022 Approved JOSE AVILA
Final 1/20/2022 OK to Issue CofO JOSE AVILA