1358 N AVENIDA DE CORTEZ 90272

Certificate Information: 1358 N AVENIDA DE CORTEZ 90272

Application / Permit
20014-30000-04784
Plan Check / Job No.
B20WL04728
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2nd floor addition (466 sf) above garage to (e) 2-story SFD (2,228 sf) w./ att. 2-car garage (440 sf)
Permit Issued
Issued on 7/8/2022
Issuing Office
Current Status
CofO Issued on 3/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 REZA HAGHIGHAT
Corrections Issued 12/14/2020 REZA HAGHIGHAT
Quality Review Completed 12/24/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 3/8/2022 REZA HAGHIGHAT
Plan Check Approved 7/8/2022 REZA HAGHIGHAT
Issued 7/8/2022 APPLICANT
Building Plans Picked Up 8/25/2022 APPLICANT
CofO in Progress 3/20/2023 BRENDAN LOONEY
Permit Finaled 3/20/2023 DANIEL ORRANTE
CofO Issued 3/20/2023 DANIEL ORRANTE
Permit Finaled 3/20/2023 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 5/18/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 5/18/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 5/18/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 5/18/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 5/18/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/20/2021 DINAH GARIN
Sewer availability Cleared 5/20/2021 DINAH GARIN
Coastal Zone Cleared 10/1/2021 JASON CHAN
ZA Case Cleared 10/1/2021 JASON CHAN
Low Impact Development Cleared 11/10/2021 TA ANH
Roof/Waste drainage to street Cleared 12/22/2021 DINAH GARIN
GPI Written Notices Cleared 7/8/2022 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 7/8/2022 REZA HAGHIGHAT

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

MICHAEL ALLEN, (310) 914-3886 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/21/2022 Corrections Issued ANDREW NAVE
Deputy Drilled-In Anchors 9/29/2022 Conditional Approval BRENDAN LOONEY
Footing/Foundation/Slab 9/30/2022 Partial Approval BRENDAN LOONEY
Deputy Drilled-In Anchors 10/25/2022 Conditional Approval BRENDAN LOONEY
Footing/Foundation/Slab 10/27/2022 Approved ANDREW NAVE
BUILDING-Rough-Frame 11/17/2022 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 11/17/2022 Partial Approval BRENDAN LOONEY
Green Building Rough 11/17/2022 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 12/12/2022 Approved BRENDAN LOONEY
PLUMBING-Rough 12/28/2022 Partial Approval BRENDAN LOONEY
ELECTRICAL-Rough 1/9/2023 Conditional Approval BRENDAN LOONEY
HVAC-Rough 1/9/2023 Approved BRENDAN LOONEY
PLUMBING-Rough 1/10/2023 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 1/17/2023 Corrections Issued BRENDAN LOONEY
Green Building Rough 1/17/2023 Not Ready for Inspection BRENDAN LOONEY
Deputy Wood Construction 1/18/2023 Conditional Approval MICHAEL PELHAM
Insulation 1/27/2023 Approved BRENDAN LOONEY
Interior/Exterior Lathing 1/27/2023 Partial Approval BRENDAN LOONEY
Shower Pan 2/2/2023 Approved BRENDAN LOONEY
Drywall Nailing 2/6/2023 Not Ready for Inspection BRENDAN LOONEY
Green Building Rough 2/6/2023 Approved BRENDAN LOONEY
Interior/Exterior Lathing 2/6/2023 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 3/17/2023 Approved BRENDAN LOONEY
Drywall Nailing 3/17/2023 Approved BRENDAN LOONEY
ELECTRICAL-Final 3/17/2023 Approved BRENDAN LOONEY
Final 3/17/2023 OK to Issue CofO BRENDAN LOONEY
Green Building Final 3/17/2023 Approved BRENDAN LOONEY
HVAC-Final 3/17/2023 Approved BRENDAN LOONEY
PLUMBING-Final 3/17/2023 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 3/17/2023 SGSOV Approved BRENDAN LOONEY
Smoke Detectors 3/17/2023 Approved BRENDAN LOONEY