3760 N GLENRIDGE DR 91423
Certificate Information: 3760 N GLENRIDGE DR 91423
- Application / Permit
- 20014-30000-04759
- Plan Check / Job No.
- B20WL04711
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add new rec-room (pool house) (396 sf) and a bathroom w./ access from outside to rear side of (e) 1-story SFD w./ att. 2-car garage
- Permit Issued
- Issued on 5/2/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2020 | FELIPE HERNANDEZ |
| Corrections Issued | 11/30/2020 | FELIPE HERNANDEZ |
| Quality Review Completed | 12/10/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 11/16/2021 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 3/16/2022 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 3/25/2022 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 5/26/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 5/31/2022 | APPLICANT |
| Applicant returned to address corrections | 8/19/2022 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 12/14/2022 | REZA HAGHIGHAT |
| Plan Check Approved | 5/2/2023 | REZA HAGHIGHAT |
| Issued | 5/2/2023 | APPLICANT |
| CofO in Progress | 6/6/2025 | MISAEL ESPARZA |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| CofO Issued | 7/8/2025 | RUBEN SALAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/13/2021 | ROSE MARIE SMITH |
| Sewer availability | Cleared | 1/13/2021 | ROSE MARIE SMITH |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2021 | ROSE MARIE SMITH |
| Specific Plan | Cleared | 10/11/2022 | CLAUDIA RODRIGUEZ |
| ZI | Cleared | 11/21/2022 | CLAUDIA RODRIGUEZ |
| Grading Pre-Inspection | Cleared | 12/13/2022 | FELIPE HERNANDEZ |
| Hydrant and Access approval | Cleared | 12/13/2022 | GILBERT URREA |
| BHO/Hillside ordinance | Cleared | 12/19/2022 | JOSE DUARTE-DIAZ |
| BHO/Hillside ordinance | Cleared | 4/17/2023 | MARY MARCUS |
| BHO/Hillside ordinance | Cleared | 4/17/2023 | MARY MARCUS |
| BHO/Hillside ordinance | Cleared | 4/17/2023 | MARY MARCUS |
| BHO/Hillside ordinance | Cleared | 4/18/2023 | MARY MARCUS |
Contact Information
| Architect | Khoudikian,, Kaaren G; Lic. No.: C13183 | 6906 FOOTHILL BLVD. TUJUNGA, CA 91042 |
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/30/2023 | Approved | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 8/2/2024 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 8/6/2024 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 8/9/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 8/12/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 8/13/2024 | Partial Approval | MISAEL ESPARZA |
| Masonry Wall/Backfill | 8/15/2024 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 8/21/2024 | Corrections Issued | MISAEL ESPARZA |
| Deputy Reinf. Concrete | 8/22/2024 | Conditional Approval | JUAN VALENZUELA |
| Pre-Inspection | 10/8/2024 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 10/17/2024 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/30/2024 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2024 | Partial Approval | JACK KARGODORIAN |
| Verify Sprinkler Sign Off | 10/30/2024 | Approved | JACK KARGODORIAN |
| Pre-Inspection | 10/31/2024 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Partial Approval | JACK KARGODORIAN |
| Interior/Exterior Lathing | 11/5/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/7/2024 | Partial Inspection | MISAEL ESPARZA |
| Sewer | 11/19/2024 | Partial Approval | MISAEL ESPARZA |
| Sewer | 11/20/2024 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 12/4/2024 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 12/9/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 12/9/2024 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/12/2024 | Approved | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 12/12/2024 | Approved | MISAEL ESPARZA |
| Insulation | 12/13/2024 | Corrections Issued | MISAEL ESPARZA |
| Drywall Nailing | 12/18/2024 | Approved | MICHAEL CORTEZ |
| Green Building Rough | 12/18/2024 | Approved | MICHAEL CORTEZ |
| Pre-Inspection | 1/28/2025 | Approved | MISAEL ESPARZA |
| Shower Pan | 2/12/2025 | Approved | MISAEL ESPARZA |
| Pre-Inspection | 4/7/2025 | Approved | MISAEL ESPARZA |
| Final | 4/22/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/22/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Final | 4/22/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 4/22/2025 | SGSOV Not Ready | JUAN VALENZUELA |
| Smoke Detectors | 4/22/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 4/30/2025 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/30/2025 | Approved | MISAEL ESPARZA |
| Green Building Final | 4/30/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 4/30/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 4/30/2025 | Approved | MISAEL ESPARZA |
| Special/Order Compliance | 5/13/2025 | Partial Inspection | MISAEL ESPARZA |
| Final | 5/15/2025 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/15/2025 | SGSOV Approved | MISAEL ESPARZA |
| Final | 6/5/2025 | OK to Issue CofO | MISAEL ESPARZA |