8831 S GRAMERCY PL 90047
Certificate Information: 8831 S GRAMERCY PL 90047
- Application / Permit
- 20014-30000-04697
- Plan Check / Job No.
- B20WL04666
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Master bathroom addition to existing 1-story single family dwelling
- Permit Issued
- Issued on 2/11/2021
- Issuing Office
- Current Status
- CofO Issued on 2/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2020 | MARJAN SHENASI |
| Corrections Issued | 11/5/2020 | MARJAN SHENASI |
| Applicant returned to address corrections | 11/24/2020 | RICHARD GARCIA |
| Plan Check Approved | 1/5/2021 | RICHARD GARCIA |
| Issued | 2/11/2021 | APPLICANT |
| Building Plans Picked Up | 2/26/2021 | APPLICANT |
| CofO in Progress | 7/14/2021 | FREDDIE RIVERA |
| Permit Finaled | 2/25/2023 | DANIEL ORRANTE |
| CofO Issued | 2/25/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/25/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2020 | ROSA SILVA |
| Roof/Waste drainage to street | Cleared | 12/17/2020 | ROSA SILVA |
Contact Information
| Contractor | Harbor Coast Construction; Lic. No.: 1068080-B | 1611 W 108TH ST LOS ANGELES, CA 90047 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/3/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/19/2021 | Partial Approval | FREDDIE RIVERA |
| Insulation | 3/19/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/15/2021 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/15/2021 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2021 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 4/15/2021 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 4/15/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 4/15/2021 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2021 | Approved | FREDDIE RIVERA |
| Insulation | 4/30/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 4/30/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Shower Pan | 4/30/2021 | Corrections Issued | FREDDIE RIVERA |
| Drywall Nailing | 5/11/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 5/11/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 5/11/2021 | Approved | FREDDIE RIVERA |
| Shower Pan | 5/11/2021 | Approved | FREDDIE RIVERA |
| Final | 6/9/2021 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 6/9/2021 | Approved | EUGENE CASSIDY |
| Green Building Final | 6/9/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Barrier | 6/9/2021 | Approved | EUGENE CASSIDY |
| METHANE-Subgrade | 6/9/2021 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 6/9/2021 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 6/9/2021 | Not Ready for Inspection | EUGENE CASSIDY |
| Pre-Inspection | 6/30/2021 | No Access for Inspection | FREDDIE RIVERA |
| Final | 7/9/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Final | 7/9/2021 | Corrections Issued | FREDDIE RIVERA |
| Smoke Detectors | 7/9/2021 | Approved | FREDDIE RIVERA |
| Final | 7/13/2021 | OK to Issue CofO | FREDDIE RIVERA |
| Green Building Final | 7/13/2021 | Approved | FREDDIE RIVERA |