11728 W TENNESSEE AVE 90064

Certificate Information: 11728 W TENNESSEE AVE 90064

Application / Permit
20014-30000-04672
Plan Check / Job No.
B20WL04650
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New car garage addition 10'x20' attached to (E) SFD. Per engineering design.
Permit Issued
Issued on 12/17/2020
Issuing Office
Current Status
Issued on 12/17/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/22/2020 APPLICANT
Assigned to Plan Check Engineer 11/2/2020 RICHARD GARCIA
Corrections Issued 11/2/2020 RICHARD GARCIA
Applicant returned to address corrections 12/3/2020 ALFREDO JARA
Plan Check Approved 12/4/2020 ALFREDO JARA
Issued 12/17/2020 APPLICANT
Building Plans Picked Up 12/22/2020 APPLICANT

Permit Application Clearance Information

Specific Plan Cleared 11/16/2020 DYLAN SITTIG
ZI Cleared 11/16/2020 DYLAN SITTIG
ZI Cleared 11/16/2020 DYLAN SITTIG
ZI Cleared 11/17/2020 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 11/24/2020 KATHLEEN LEE
Roof/Waste drainage to street Cleared 11/24/2020 KATHLEEN LEE

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/21/2021 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 1/25/2021 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/9/2021 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 2/17/2021 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 2/17/2021 Approved OGANES TARAKHCHYAN
Green Building Rough 2/17/2021 Approved OGANES TARAKHCHYAN
Insulation 2/17/2021 Approved OGANES TARAKHCHYAN
Drywall Nailing 2/23/2021 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 2/23/2021 Approved OGANES TARAKHCHYAN
Final 3/22/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 3/22/2021 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 3/22/2021 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 3/22/2021 Approved OGANES TARAKHCHYAN