2309 1/2 S SCARFF ST 90007
Certificate Information: 2309 1/2 S SCARFF ST 90007
- Application / Permit
- 20014-30000-04669
- Plan Check / Job No.
- B20WL04645
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition to and conversion of an (e) garage into an ADU.
- Permit Issued
- Issued on 2/16/2022
- Issuing Office
- Current Status
- CofO Issued on 1/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | RICHARD GARCIA |
| Corrections Issued | 11/1/2020 | RICHARD GARCIA |
| Quality Review Completed | 11/10/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 2/4/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 2/26/2021 | RICHARD GARCIA |
| Plan Check Approved | 3/31/2021 | RICHARD GARCIA |
| No Progress | 11/23/2021 | RICHARD GARCIA |
| Plan Check Approved | 12/21/2021 | RICHARD GARCIA |
| Issued | 2/16/2022 | APPLICANT |
| Building Plans Picked Up | 2/23/2022 | APPLICANT |
| CofO in Progress | 1/9/2023 | BRENDAN MORELLI |
| CofO Issued | 1/13/2023 | DEROLD HAUFF |
| Permit Finaled | 1/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 11/16/2020 | KENTON TRINH |
| ZI | Cleared | 11/16/2020 | KENTON TRINH |
| HPOZ | Cleared | 11/17/2020 | LAMBERT GIESSINGER |
| Address approval | Cleared | 9/10/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2021 | WALLIE JONG |
| Sewer availability | Cleared | 9/13/2021 | WALLIE JONG |
| ZI | Cleared | 9/14/2021 | LAMBERT GIESSINGER |
| ZI | Cleared | 9/14/2021 | RICHARD REASER |
| ZI | Cleared | 9/14/2021 | RICHARD REASER |
| Hydrant and Access approval | Cleared | 9/20/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 10/7/2021 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | WALLIE JONG |
| Green Code | Cleared | 12/21/2021 | RICHARD GARCIA |
Contact Information
| Architect | Zbikowski,, Jeffrey; Lic. No.: C35389 | 1810 14TH STREET SUITE 204 SANTA MONICA, CA 90404 |
| Contractor | J M A General Construction Inc; Lic. No.: 940631-B | 5834 VINELAND AVE NORTH HOLLYWOOD, CA 91606 |
| Engineer | Lee,, Sang Youck; Lic. No.: S3821 | 3531 BROOKHILL ST GLENDALE, CA 91214 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/20/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Barrier | 4/20/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 4/20/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 4/20/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 4/22/2022 | Partial Approval | JOAQUIN GREENOUGH |
| METHANE-Rough | 4/22/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 4/22/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/4/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| METHANE-Barrier | 5/4/2022 | Approved | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 5/4/2022 | Approved | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/11/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 8/9/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 8/9/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| METHANE-Rough | 8/9/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/9/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Rough-Elec/Plmb/HVAC | 8/12/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 8/12/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 8/29/2022 | Approved | RYAN SALAZAR |
| Insulation | 8/31/2022 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 10/17/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Green Building Rough | 10/17/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| METHANE-Rough | 10/17/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 11/2/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/2/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| METHANE-Rough | 11/2/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Underground Mechanical | 11/2/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/8/2022 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 11/8/2022 | Approved | ENRIQUE MIRELES |
| METHANE-Rough | 11/8/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 12/13/2022 | Approved | BRENDAN MORELLI |
| Final | 12/13/2022 | Corrections Issued | BRENDAN MORELLI |
| Footing/Foundation/Slab | 12/13/2022 | Approved | BRENDAN MORELLI |
| Green Building Final | 12/13/2022 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 12/13/2022 | SGSOV Not Ready | BRENDAN MORELLI |
| Smoke Detectors | 12/13/2022 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 12/19/2022 | Approved | BRENDAN MORELLI |
| HVAC-Final | 12/19/2022 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 12/19/2022 | Approved | BRENDAN MORELLI |
| Final | 12/23/2022 | OK to Issue CofO | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 12/23/2022 | SGSOV Approved | BRENDAN MORELLI |