5704-5706 N CALVIN AVE 91356
Certificate Information: 5704-5706 N CALVIN AVE 91356
- Application / Permit
- 20014-30000-04667
- Plan Check / Job No.
- B20WL04644
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel, Addition and (N) Attached ADU per LAMC 12.22 A.33 (c) and (e) to an (E) 1-Story S.F.D
- Permit Issued
- Issued on 5/31/2022
- Issuing Office
- Current Status
- Issued on 5/31/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2020 | DAVID CASTILLO |
| Corrections Issued | 11/9/2020 | DAVID CASTILLO |
| Quality Review Completed | 11/17/2020 | TARIK SAOUD |
| Applicant returned to address corrections | 10/19/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 12/8/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 1/13/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 3/9/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 3/11/2022 | APPLICANT |
| Plan Check Approved | 3/30/2022 | DAVID CASTILLO |
| Issued | 5/31/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/23/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/23/2021 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 10/7/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/28/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abkarian,, Raffi; Lic. No.: C36027 | 18763 VINTAGE STREET NORTHRIDGE, CA 91324 |
| Engineer | Price,, Mark Erin; Lic. No.: L7764 | 18700 WELLHAVEN STREET CANYON COUNTRY, CA 91351 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/7/2022 | Conditional Approval | JUSTIN HAWLEY |
| Footing/Foundation/Slab | 11/18/2022 | Corrections Issued | SEAN HAUPT |
| Special/Order Compliance | 11/18/2022 | Partial Inspection | KRISTEN CAUSEY |
| Pre-Inspection | 4/14/2023 | Corrections Issued | JON MCHUGH |
| Wood Frame | 4/14/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 4/24/2023 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Rough | 4/24/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 4/24/2023 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 5/1/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 5/4/2023 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2023 | Corrections Issued | JON MCHUGH |
| Insulation | 5/10/2023 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Partial Approval | JON MCHUGH |
| Deputy Drilled-In Anchors | 10/11/2023 | Conditional Approval | JON MCHUGH |
| Deputy Wood Construction | 10/11/2023 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 11/30/2023 | Partial Approval | JEFFREY PARD |
| Deputy Wood Construction | 12/12/2023 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 12/14/2023 | Corrections Issued | JON MCHUGH |
| Drywall Nailing | 12/14/2023 | Not Ready for Inspection | JON MCHUGH |
| Final | 12/14/2023 | Not Ready for Inspection | JON MCHUGH |
| Footing/Foundation/Slab | 12/14/2023 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 12/14/2023 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 12/14/2023 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Final | 12/14/2023 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Rough | 12/14/2023 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 12/14/2023 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 12/14/2023 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 12/28/2023 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 12/28/2023 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Rough | 12/28/2023 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 2/1/2024 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 2/1/2024 | Not Ready for Inspection | JON MCHUGH |
| MERV13>=Rough | 2/1/2024 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2024 | Partial Approval | JON MCHUGH |
| Sewer | 5/10/2024 | Corrections Issued | JON MCHUGH |
| Sewer | 5/14/2024 | Corrections Issued | JON MCHUGH |
| Sewer | 5/17/2024 | Corrections Issued | JON MCHUGH |
| Sewer | 5/20/2024 | Approved | MORRIS JACKSON |
| Sewer | 6/3/2024 | Approved | MORRIS JACKSON |
| Underground Mechanical | 6/27/2024 | Not Ready for Inspection | JON MCHUGH |
| Underground Mechanical | 7/2/2024 | Partial Approval | JON MCHUGH |
| PLUMBING-Rough | 7/24/2024 | Partial Approval | ALEXANDER HANDY |
| Underground Mechanical | 7/24/2024 | Partial Approval | ALEXANDER HANDY |
| Interior/Exterior Lathing | 11/7/2024 | Corrections Issued | MORRIS JACKSON |
| Interior/Exterior Lathing | 11/18/2024 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 11/25/2024 | Partial Approval | JON MCHUGH |