3519 S BARRY AVE 90066
Certificate Information: 3519 S BARRY AVE 90066
- Application / Permit
 - 20014-30000-04665
 - Plan Check / Job No.
 - B20WL04641
 - Group
 - Building
 - Type
 - Bldg-Addition
 - Sub-Type
 - 1 or 2 Family Dwelling
 - Primary Use
 - (1) Dwelling - Single Family
 - Work Description
 - 2-STORY MAJOR ADDITION KEEPING ONLY 2-FT OF WALL AND FOUNDATION WITH ATTACHED 2-CAR GARAGE
 - Permit Issued
 - Issued on 1/26/2021
 - Issuing Office
 - Current Status
 - CofO Issued on 4/15/2022
 - Certificate of Occupancy
 - CofO Issued More Information
 
Permit Application Status History
| Submitted | 10/22/2020 | APPLICANT | 
| Assigned to Plan Check Engineer | 10/29/2020 | TARIK SAOUD | 
| Corrections Issued | 11/2/2020 | TARIK SAOUD | 
| Quality Review Completed | 11/4/2020 | KAMRAN GHOTBI RAVANDI | 
| Plan Check Approved | 1/4/2021 | TARIK SAOUD | 
| Issued | 1/26/2021 | APPLICANT | 
| Building Plans Picked Up | 1/27/2021 | APPLICANT | 
| CofO in Progress | 4/1/2022 | JOHNNY MIRANDA | 
| Permit Finaled | 4/15/2022 | DANIEL ORRANTE | 
| CofO Issued | 4/15/2022 | DANIEL ORRANTE | 
| Permit Finaled | 4/15/2022 | DANIEL ORRANTE | 
Permit Application Clearance Information
| Permit | Cleared | 11/17/2020 | DINAH GARIN | 
| Low Impact Development | Cleared | 11/18/2020 | ROBIN YAMADA | 
| Specific Plan | Cleared | 11/18/2020 | FREDDY GARCIA | 
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2020 | DINAH GARIN | 
| Roof/Waste drainage to street | Cleared | 11/25/2020 | DINAH GARIN | 
| Sewer availability | Cleared | 11/25/2020 | DINAH GARIN | 
| Trees in Parkway | Cleared | 12/28/2020 | JOHN KIM | 
| Grading Pre-Inspection | Cleared | 1/4/2021 | TARIK SAOUD | 
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 | 
| Contractor | Southland Building & Remodel Company; Lic. No.: 894311-B | 1324 WEST ROSECRANS AVENUE COMPTON, CA 90222 | 
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 | 
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI | 
Pending Inspections
| No Data Available. | 
Inspection Request History
| PLUMBING-Rough | 3/15/2021 | Partial Approval | EVAN COOPER | 
| Sewer | 3/15/2021 | Approved | EVAN COOPER | 
| Excavation/Setback/Form/Re-Bar | 3/24/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA | 
| Footing/Foundation/Slab | 3/24/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA | 
| Footing/Foundation/Slab | 3/25/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA | 
| Deputy Wood Construction | 4/13/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA | 
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2021 | Partial Approval | OGANES TARAKHCHYAN | 
| BUILDING-Rough-Frame | 7/12/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN | 
| ELECTRICAL-Rough | 7/12/2021 | Partial Approval | OGANES TARAKHCHYAN | 
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2021 | Partial Approval | OGANES TARAKHCHYAN | 
| Green Building Rough | 7/12/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN | 
| HVAC-Rough | 7/12/2021 | Approved | OGANES TARAKHCHYAN | 
| PLUMBING-Rough | 7/12/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN | 
| BUILDING-Rough-Frame | 7/15/2021 | Partial Approval | OGANES TARAKHCHYAN | 
| Green Building Rough | 7/15/2021 | Approved | OGANES TARAKHCHYAN | 
| PLUMBING-Rough | 7/15/2021 | Approved | OGANES TARAKHCHYAN | 
| Insulation | 8/23/2021 | Approved | JUAN VALENZUELA | 
| Interior/Exterior Lathing | 8/23/2021 | Partial Approval | JUAN VALENZUELA | 
| Drywall Nailing | 9/13/2021 | Approved | MORRIS JACKSON | 
| Shower Pan | 9/13/2021 | Approved | MORRIS JACKSON | 
| Interior/Exterior Lathing | 10/12/2021 | Approved | OGANES TARAKHCHYAN | 
| BUILDING-Rough-Frame | 2/25/2022 | Approved | JOHNNY MIRANDA | 
| ELECTRICAL-Final | 2/25/2022 | Corrections Issued | JOHNNY MIRANDA | 
| Final | 2/25/2022 | Corrections Issued | JOHNNY MIRANDA | 
| Footing/Foundation/Slab | 2/25/2022 | Approved | JOHNNY MIRANDA | 
| Green Building Final | 2/25/2022 | Approved | JOHNNY MIRANDA | 
| HVAC-Final | 2/25/2022 | Corrections Issued | JOHNNY MIRANDA | 
| PLUMBING-Final | 2/25/2022 | Corrections Issued | JOHNNY MIRANDA | 
| SGSOV-Seismic Gas S/O Valve | 2/25/2022 | SGSOV Not Ready | JOHNNY MIRANDA | 
| Smoke Detectors | 2/25/2022 | Approved | JOHNNY MIRANDA | 
| ELECTRICAL-Final | 2/28/2022 | Approved | JOHNNY MIRANDA | 
| Gas Test | 2/28/2022 | Approved | JOHNNY MIRANDA | 
| HVAC-Final | 2/28/2022 | Not Ready for Inspection | JOHNNY MIRANDA | 
| PLUMBING-Final | 2/28/2022 | Corrections Issued | JOHNNY MIRANDA | 
| Service/Power Release | 3/4/2022 | Approved | KENNETH NAGLE | 
| Final | 3/24/2022 | OK to Issue CofO | JOHNNY MIRANDA | 
| SGSOV-Seismic Gas S/O Valve | 3/24/2022 | SGSOV Approved | JOHNNY MIRANDA |