15256 W DE PAUW ST 90272

Certificate Information: 15256 W DE PAUW ST 90272

Application / Permit
20014-30000-04565
Plan Check / Job No.
B20WL04564
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story house addition with attached garage to (E) 1 story SFD.
Permit Issued
Issued on 1/25/2021
Issuing Office
Current Status
CofO Issued on 7/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2020 APPLICANT
Assigned to Plan Check Engineer 10/21/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 11/7/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 11/19/2020 TARIK SAOUD
Plan Check Approved 1/21/2021 VLADIMIR ARUTYUNYAN
Issued 1/25/2021 APPLICANT
Building Plans Picked Up 1/26/2021 APPLICANT
CofO in Progress 7/15/2022 ANDREW NAVE
Permit Finaled 7/21/2022 DANIEL ORRANTE
CofO Issued 7/21/2022 DANIEL ORRANTE
Permit Finaled 7/21/2022 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 11/19/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 11/20/2020 DINAH GARIN
Sewer availability Cleared 11/20/2020 DINAH GARIN
Low Impact Development Cleared 12/2/2020 ANDRES COVARRUBIAS
Coastal Zone Cleared 12/8/2020 DENZEL HENDERSON
Roof/Waste drainage to street Cleared 12/15/2020 DINAH GARIN
Trees in Parkway Cleared 1/6/2021 JOHN KIM
GPI Written Notices Cleared 1/21/2021 VLADIMIR ARUTYUNYAN
Grading Pre-Inspection Cleared 1/21/2021 VLADIMIR ARUTYUNYAN

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

STEPHANIE SWANSON, (213) 469-1255 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/25/2021 Approved ANDREW NAVE
Sewer 3/2/2021 Approved ANDREW NAVE
Underground Mechanical 3/2/2021 Partial Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 3/17/2021 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 6/24/2021 Partial Approval ANDREW NAVE
Deputy Drilled-In Anchors 7/29/2021 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 8/3/2021 Partial Approval ANDREW NAVE
Deputy Wood Construction 8/10/2021 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 8/11/2021 Approved ANDREW NAVE
PLUMBING-Rough 9/1/2021 Conditional Approval ANDREW NAVE
ELECTRICAL-Rough 9/30/2021 Approved ANDREW NAVE
Interior/Exterior Lathing 10/6/2021 Partial Approval STEPHANIE SWANSON
HVAC-Rough 10/8/2021 Corrections Issued ANDREW NAVE
BUILDING-Rough-Frame 11/9/2021 Partial Approval ANDREW NAVE
Green Building Rough 11/9/2021 Conditional Approval ANDREW NAVE
HVAC-Rough 11/9/2021 Approved ANDREW NAVE
Insulation 11/30/2021 Approved KRISTEN CAUSEY
Pre-Inspection 12/2/2021 Approved ANDREW NAVE
BUILDING-Rough-Frame 12/9/2021 Approved ANDREW NAVE
Green Building Rough 12/9/2021 Approved ANDREW NAVE
Pre-Inspection 12/9/2021 Approved ANDREW NAVE
Shower Pan 12/9/2021 Approved ANDREW NAVE
PLUMBING-Rough 12/17/2021 Conditional Approval ANDREW NAVE
Drywall Nailing 12/28/2021 Partial Approval ANDREW NAVE
Drywall Nailing 1/4/2022 Approved ANDREW NAVE
Interior/Exterior Lathing 1/11/2022 Approved ANDREW NAVE
PLUMBING-Rough 1/11/2022 Approved ANDREW NAVE
ELECTRICAL-Final 6/17/2022 Corrections Issued ANDREW NAVE
PLUMBING-Final 6/17/2022 Corrections Issued ANDREW NAVE
ELECTRICAL-Final 6/24/2022 Not Ready for Inspection ANDREW NAVE
HVAC-Final 6/24/2022 Not Ready for Inspection ANDREW NAVE
PLUMBING-Final 6/24/2022 Approved ANDREW NAVE
Service/Power Release 6/24/2022 Not Ready for Inspection ANDREW NAVE
ELECTRICAL-Final 7/5/2022 Approved ANDREW NAVE
Final 7/5/2022 Corrections Issued ANDREW NAVE
Service/Power Release 7/8/2022 Approved MICHAEL PELHAM
HVAC-Final 7/13/2022 Corrections Issued ANDREW NAVE
Final 7/15/2022 OK to Issue CofO ANDREW NAVE
Footing/Foundation/Slab 7/15/2022 Approved ANDREW NAVE
Green Building Final 7/15/2022 Approved ANDREW NAVE
HVAC-Final 7/15/2022 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 7/15/2022 SGSOV Approved ANDREW NAVE
Smoke Detectors 7/15/2022 Approved ANDREW NAVE