10119 W HILLGROVE DR 90210
Certificate Information: 10119 W HILLGROVE DR 90210
- Application / Permit
- 20014-30000-04438
- Plan Check / Job No.
- B20WL04430
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-story addition to extend living room and add bathrooms to an (e) single story SFD w./ att. garage, remove and replace portion of (e) roof
- Permit Issued
- Issued on 3/12/2021
- Issuing Office
- Current Status
- Issued on 3/12/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2020 | REZA HAGHIGHAT |
| Corrections Issued | 10/26/2020 | REZA HAGHIGHAT |
| Quality Review Completed | 11/5/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 11/9/2020 | APPLICANT |
| Plan Check Approved | 2/22/2021 | REZA HAGHIGHAT |
| Issued | 3/12/2021 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/23/2020 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 12/23/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/28/2020 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 2/22/2021 | REZA HAGHIGHAT |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tzeng,, Charles Chau-Jyi; Lic. No.: C34005 | PO BOX 5044 PASADENA, CA 91117 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/11/2021 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 4/8/2022 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 4/10/2022 | Corrections Issued | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 5/20/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Steel/Welding | 6/8/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 4/18/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 4/24/2023 | Corrections Issued | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 5/3/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 6/12/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Footing/Foundation/Slab | 7/11/2023 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 8/11/2023 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 8/17/2023 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 8/23/2023 | Corrections Issued | BRENDAN LOONEY |
| Deputy Drilled-In Anchors | 1/9/2024 | Conditional Approval | MICHAEL PELHAM |
| Pre-Inspection | 1/9/2024 | Partial Inspection | BRENDAN LOONEY |
| Footing/Foundation/Slab | 1/23/2024 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 1/25/2024 | Corrections Issued | BRENDAN LOONEY |
| Deputy Steel/Welding | 2/14/2024 | Conditional Approval | CHRISTOPHER WILSON |
| Pre-Inspection | 5/7/2024 | Corrections Issued | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Approved | SEAN HAUPT |
| Pre-Inspection | 5/28/2024 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 8/2/2024 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 8/30/2024 | Partial Approval | SEAN HAUPT |
| Sewer | 8/30/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 10/3/2024 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Rough | 10/3/2024 | Partial Approval | SEAN HAUPT |
| HVAC-Final | 10/25/2024 | Corrections Issued | SEAN HAUPT |
| HVAC-Rough | 10/25/2024 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 10/28/2024 | Approved | SEAN HAUPT |
| HVAC-Rough | 12/27/2024 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 12/30/2024 | Approved | SEAN HAUPT |
| Green Building Rough | 12/30/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 12/30/2024 | Approved | SEAN HAUPT |
| Special/Order Compliance | 12/30/2024 | Approved | SEAN HAUPT |
| Insulation | 1/8/2025 | Corrections Issued | BOBBY KEY |
| Insulation | 1/9/2025 | Approved | BOBBY KEY |
| Drywall Nailing | 1/24/2025 | Conditional Approval | CHRISTOPHER WILSON |
| Special/Order Compliance | 1/24/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 1/24/2025 | Approved | CHRISTOPHER WILSON |
| Shower Pan | 2/4/2025 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 2/14/2025 | Approved | SEAN HAUPT |
| Deputy Drilled-In Anchors | 4/9/2025 | Conditional Approval | MICHAEL PELHAM |
| Special/Order Compliance | 4/9/2025 | Not Ready for Inspection | MICHAEL PELHAM |
| Interior/Exterior Lathing | 4/16/2025 | Corrections Issued | SEAN HAUPT |
| Pre-Inspection | 7/11/2025 | Partial Approval | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2026 | Approved | CARLOS MATAMOROS |