1565 N BUNDY DR 90049

Certificate Information: 1565 N BUNDY DR 90049

Application / Permit
20014-30000-04435
Plan Check / Job No.
B20WL04426
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
interior remodel, bedroom addition at the third floor, convert crawl space into gym and storage area as additin to the garage level and new proposed deck
Permit Issued
Issued on 8/16/2021
Issuing Office
Current Status
CofO Issued on 7/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2020 APPLICANT
Assigned to Plan Check Engineer 10/14/2020 TARIK SAOUD
Corrections Issued 10/18/2020 TARIK SAOUD
Quality Review Completed 10/29/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 2/18/2021 TARIK SAOUD
Applicant returned to address corrections 3/16/2021 TARIK SAOUD
Applicant returned to address corrections 4/8/2021 TARIK SAOUD
Plan Check Approved 4/8/2021 TARIK SAOUD
Issued 8/16/2021 APPLICANT
Building Plans Picked Up 8/18/2021 APPLICANT
CofO in Progress 7/11/2024 ARAM AVEDISIAN
Permit Finaled 7/20/2024 DANIEL ORRANTE
CofO Issued 7/20/2024 DANIEL ORRANTE
Permit Finaled 7/20/2024 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 3/16/2021 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 3/16/2021 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 3/16/2021 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 3/16/2021 ANTHONY MAINEZ
BHO/Hillside ordinance Cleared 3/16/2021 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 3/16/2021 TARIK SAOUD
Low Impact Development Cleared 3/17/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/17/2021 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 3/19/2021 NIKTA MOUSAVI
Sewer availability Cleared 3/19/2021 NIKTA MOUSAVI

Contact Information

Architect Desai,, Manish Mahesh; Lic. No.: C30479 169 1/2 SAN GABRIEL CT.      SIERRA MADRE, CA 91024
Contractor Chadwick & Doggett General Contracting Inc; Lic. No.: 756093-B 13428 MAXELLA AVENUE      MARINA DEL REY, CA 90292
Engineer Mccullum,, Eric William; Lic. No.: C68850 727 2ND ST STE 104      HERMOSA BEACH, CA 90254

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

FLOOD-Elevation Certificate 11/12/2021 Approved ANDREW NAVE
Footing/Foundation/Slab 11/12/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 12/1/2021 Partial Approval JUAN VALENZUELA
Deputy Reinf. Concrete 12/14/2021 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 2/25/2022 Corrections Issued JUAN VALENZUELA
Deputy Drilled-In Anchors 3/14/2022 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/18/2022 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 3/18/2022 Partial Approval JUAN VALENZUELA
Deputy Wood Construction 7/13/2022 Approved MICHAEL PELHAM
Deputy Wood Construction 8/9/2022 No Access for Inspection KENNETH NAGLE
ELECTRICAL-Rough 9/27/2022 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 9/27/2022 Partial Approval JUAN VALENZUELA
FLOOD-Proofing Certificate 10/5/2022 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/5/2022 Approved JUAN VALENZUELA
Green Building Rough 10/5/2022 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 10/5/2022 Conditional Approval JUAN VALENZUELA
Special/Order Compliance 10/5/2022 Partial Inspection CLAYTON GRAHAM
BUILDING-Rough-Frame 1/13/2023 Approved JUAN VALENZUELA
ELECTRICAL-Rough 1/13/2023 Approved JUAN VALENZUELA
Green Building Rough 1/13/2023 Approved JUAN VALENZUELA
Insulation 1/13/2023 Approved JUAN VALENZUELA
Interior/Exterior Lathing 1/13/2023 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 1/13/2023 Approved JUAN VALENZUELA
Shower Pan 1/13/2023 Approved JUAN VALENZUELA
Drywall Nailing 1/27/2023 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 1/27/2023 Approved KEVIN SARGSYAN
ELECTRICAL-Final 2/22/2024 Approved ARAM AVEDISIAN
PLUMBING-Final 2/23/2024 Corrections Issued KEVIN SARGSYAN
HVAC-Final 2/26/2024 Approved KEVIN SARGSYAN
PLUMBING-Final 2/26/2024 Approved KEVIN SARGSYAN
Final 7/11/2024 OK to Issue CofO ARAM AVEDISIAN
Footing/Foundation/Slab 7/11/2024 Approved ARAM AVEDISIAN
Green Building Final 7/11/2024 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 7/11/2024 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 7/11/2024 Approved ARAM AVEDISIAN