1407 N AVENIDA DE CORTEZ 90272
Certificate Information: 1407 N AVENIDA DE CORTEZ 90272
- Application / Permit
- 20014-30000-04400
- Plan Check / Job No.
- B20WL04397
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- second story addition to an existing 2-storySFD with attached garage
- Permit Issued
- Issued on 10/12/2021
- Issuing Office
- Current Status
- CofO Issued on 2/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2020 | TARIK SAOUD |
| Corrections Issued | 10/17/2020 | TARIK SAOUD |
| Quality Review Completed | 10/29/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 11/2/2020 | APPLICANT |
| Applicant returned to address corrections | 2/9/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 2/10/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 7/21/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 8/25/2021 | DAVID CASTILLO |
| Plan Check Approved | 9/23/2021 | TARIK SAOUD |
| Issued | 10/12/2021 | APPLICANT |
| CofO in Progress | 11/10/2022 | BRENDAN LOONEY |
| Permit Finaled | 2/11/2023 | DANIEL ORRANTE |
| CofO Issued | 2/11/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/11/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/25/2021 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 2/25/2021 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 2/25/2021 | TRACY TATE |
| BHO/Hillside ordinance | Cleared | 2/25/2021 | TRACY TATE |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2021 | TRACY TATE |
| Coastal Zone | Cleared | 4/26/2021 | RICHARD REASER |
| Address approval | Cleared | 6/29/2021 | ANTHONY MAINEZ |
| BHO/Hillside ordinance | Cleared | 6/29/2021 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 6/29/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 7/6/2021 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 7/21/2021 | TARIK SAOUD |
Contact Information
| Architect | Tekletsion,, Goitom; Lic. No.: C31925 | 2100 N SEPULVEDA BLVD # 44 MANHATTAN BEACH, CA 90266 |
| Contractor | M D R N Remodeling Company; Lic. No.: 1065843-B | 18432 OXNARD ST #218 TARZANA, CA 91316 |
| Engineer | Khoury,, Nader Bulos; Lic. No.: C61402 | 1278 GLENNEYRE ST 201 LAGUNA BEACH, CA 92651 |
Inspector Information
| MICHAEL ALLEN, (310) 914-3886 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/19/2021 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 10/21/2021 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2021 | Partial Approval | ANDREW NAVE |
| BUILDING-Rough-Frame | 12/28/2021 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Rough | 12/28/2021 | Approved | ANDREW NAVE |
| Green Building Rough | 12/28/2021 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 12/28/2021 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 1/7/2022 | Conditional Approval | ANDREW NAVE |
| HVAC-Rough | 1/7/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 1/7/2022 | Corrections Issued | ANDREW NAVE |
| Insulation | 1/11/2022 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 1/11/2022 | Approved | JOHN KIDWELL |
| Drywall Nailing | 2/3/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Shower Pan | 2/3/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 2/15/2022 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 2/15/2022 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 6/29/2022 | Approved | ANDREW NAVE |
| Final | 6/29/2022 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 6/29/2022 | Approved | ANDREW NAVE |
| Green Building Final | 6/29/2022 | Corrections Issued | ANDREW NAVE |
| Green Building Rough | 6/29/2022 | Approved | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 6/29/2022 | SGSOV Approved | ANDREW NAVE |
| Smoke Detectors | 6/29/2022 | Corrections Issued | ANDREW NAVE |
| Wood Frame | 7/20/2022 | Corrections Issued | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2022 | Approved | ANDREW NAVE |
| Drywall Nailing | 8/4/2022 | No Access for Inspection | BRENDAN LOONEY |
| Drywall Nailing | 8/10/2022 | Approved | BRENDAN LOONEY |
| Final | 11/1/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Final | 11/1/2022 | Approved | BRENDAN LOONEY |
| Smoke Detectors | 11/1/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 11/9/2022 | OK to Issue CofO | BRENDAN LOONEY |
| Smoke Detectors | 11/9/2022 | Approved | BRENDAN LOONEY |