8315 S CAMPION DR 90045

Certificate Information: 8315 S CAMPION DR 90045

Application / Permit
20014-30000-04367
Plan Check / Job No.
B20WL04363
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
interior remodel & addition of 725 sf
Permit Issued
Issued on 5/20/2021
Issuing Office
Current Status
CofO Issued on 7/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2020 APPLICANT
Assigned to Plan Check Engineer 10/9/2020 RICHARD GARCIA
Corrections Issued 10/14/2020 RICHARD GARCIA
Building Plans Picked Up 10/14/2020 APPLICANT
Applicant returned to address corrections 4/6/2021 RICHARD GARCIA
Applicant returned to address corrections 4/15/2021 JASON JANGADA
Plan Check Approved 5/13/2021 RICHARD GARCIA
Issued 5/20/2021 APPLICANT
CofO in Progress 7/6/2022 RYAN BARNES
Permit Finaled 7/12/2022 BRUCE TODD
CofO Issued 7/12/2022 BRUCE TODD
Permit Finaled 7/12/2022 BRUCE TODD

Permit Application Clearance Information

Specific Plan Cleared 12/7/2020 LOUIS ORTEGA
ZI Cleared 12/7/2020 LOUIS ORTEGA
ZI Cleared 12/7/2020 LOUIS ORTEGA
ZI Cleared 12/7/2020 LOUIS ORTEGA
ZI Cleared 12/7/2020 LOUIS ORTEGA
Eng Process Fee Ord 176,300 Cleared 12/15/2020 CATHERINE ADROVER
Sewer availability Cleared 12/15/2020 CATHERINE ADROVER
Low Impact Development Cleared 3/19/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 3/19/2021 NIKTA MOUSAVI

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Williamson Vincent Construction Inc; Lic. No.: 1050555-B 8723 BLERIOT AVE      LOS ANGELES, CA 90045

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/25/2021 Corrections Issued MARIAN PODPORA
METHANE-Barrier 5/25/2021 Approved MARIAN PODPORA
METHANE-Subgrade 5/25/2021 Corrections Issued MARIAN PODPORA
Piling/Pier/Caisson 6/3/2021 Not Ready for Inspection MARIAN PODPORA
Footing/Foundation/Slab 6/4/2021 Approved MARIAN PODPORA
METHANE-Subgrade 6/4/2021 Approved MARIAN PODPORA
BUILDING-Rough-Frame 6/17/2021 Partial Approval MARIAN PODPORA
PLUMBING-Rough 6/17/2021 Partial Approval MARIAN PODPORA
Floor/Roof Diaphrgm/Shear Wall 6/18/2021 Partial Approval MARIAN PODPORA
BUILDING-Rough-Frame 7/20/2021 Not Ready for Inspection MARIAN PODPORA
Floor/Roof Diaphrgm/Shear Wall 7/20/2021 Corrections Issued MARIAN PODPORA
Green Building Rough 7/20/2021 Not Ready for Inspection MARIAN PODPORA
METHANE-Rough 7/20/2021 Approved MARIAN PODPORA
Rough-Elec/Plmb/HVAC 7/28/2021 Corrections Issued MARIAN PODPORA
BUILDING-Rough-Frame 9/9/2021 Not Ready for Inspection RYAN BARNES
Green Building Rough 9/9/2021 Not Ready for Inspection RYAN BARNES
Interior/Exterior Lathing 9/9/2021 Not Ready for Inspection RYAN BARNES
Rough-Elec/Plmb/HVAC 9/9/2021 Partial Approval RYAN BARNES
BUILDING-Rough-Frame 9/20/2021 Not Ready for Inspection RYAN BARNES
HVAC-Rough 9/20/2021 Not Ready for Inspection RYAN BARNES
ELECTRICAL-Rough 9/24/2021 Partial Approval MARIAN PODPORA
BUILDING-Rough-Frame 9/28/2021 Partial Approval MARIAN PODPORA
Green Building Rough 9/28/2021 Approved MARIAN PODPORA
PLUMBING-Rough 9/28/2021 Partial Approval MARIAN PODPORA
Insulation 10/6/2021 Not Ready for Inspection MARIAN PODPORA
Drywall Nailing 10/13/2021 Conditional Approval MARIAN PODPORA
Interior/Exterior Lathing 10/13/2021 Conditional Approval MARIAN PODPORA
BUILDING-Rough-Frame 2/1/2022 Not Ready for Inspection MARIAN PODPORA
Final 2/1/2022 Not Ready for Inspection MARIAN PODPORA
Green Building Final 2/1/2022 Not Ready for Inspection MARIAN PODPORA
SGSOV-Seismic Gas S/O Valve 2/1/2022 SGSOV Not Ready MARIAN PODPORA
Smoke Detectors 2/1/2022 Not Ready for Inspection MARIAN PODPORA
SGSOV-Seismic Gas S/O Valve 2/3/2022 SGSOV Not Ready MARIAN PODPORA
Gas Test 2/7/2022 Approved MARIAN PODPORA
Pre-Inspection 2/7/2022 Not Ready for Inspection MARIAN PODPORA
Service/Power Release 2/7/2022 Approved MARIAN PODPORA
ELECTRICAL-Final 2/23/2022 Corrections Issued MARIAN PODPORA
HVAC-Final 2/23/2022 Corrections Issued MARIAN PODPORA
PLUMBING-Final 2/23/2022 Corrections Issued MARIAN PODPORA
ELECTRICAL-Final 3/9/2022 Not Ready for Inspection MARIAN PODPORA
HVAC-Final 3/9/2022 Not Ready for Inspection MARIAN PODPORA
ELECTRICAL-Final 3/15/2022 Corrections Issued MARIAN PODPORA
HVAC-Final 3/15/2022 Corrections Issued MARIAN PODPORA
BUILDING-Rough-Frame 4/26/2022 Approved MARIAN PODPORA
Final 4/26/2022 Corrections Issued MARIAN PODPORA
Green Building Final 4/26/2022 Approved MARIAN PODPORA
HVAC-Final 4/26/2022 Approved MARIAN PODPORA
SGSOV-Seismic Gas S/O Valve 4/26/2022 SGSOV Approved MARIAN PODPORA
Smoke Detectors 4/26/2022 Approved MARIAN PODPORA
Final 5/12/2022 Corrections Issued MARIAN PODPORA
Final 7/5/2022 Conditional Approval RYAN BARNES