6632 N BIRCHTON AVE 91307

Certificate Information: 6632 N BIRCHTON AVE 91307

Application / Permit
20014-30000-04316
Plan Check / Job No.
B20WL04315
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New dining room addition to the rear of an existing 1-story SFD.
Permit Issued
Issued on 2/19/2021
Issuing Office
Current Status
CofO Issued on 11/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 KAVIAN REFAHI
Corrections Issued 10/17/2020 KAVIAN REFAHI
Applicant returned to address corrections 2/1/2021 RICHARD GARCIA
Plan Check Approved 2/2/2021 RICHARD GARCIA
No Progress 2/2/2021 RICHARD GARCIA
Plan Check Approved 2/18/2021 ALFREDO JARA
Issued 2/19/2021 APPLICANT
Building Plans Picked Up 2/26/2021 APPLICANT
CofO in Progress 11/23/2021 TROY SANDERS
Permit Finaled 11/30/2021 JOHN JANSON
CofO Issued 11/30/2021 JOHN JANSON
Permit Finaled 11/30/2021 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/2/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/3/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/12/2021 Partial Approval TROY SANDERS
Footing/Foundation/Slab 5/18/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 7/26/2021 Corrections Issued DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 7/26/2021 Partial Approval DAVID STEPANYAN
Green Building Rough 7/26/2021 Not Ready for Inspection DAVID STEPANYAN
BUILDING-Rough-Frame 8/23/2021 Approved TROY SANDERS
Green Building Rough 8/23/2021 Not Ready for Inspection TROY SANDERS
HVAC-Rough 8/23/2021 Approved TROY SANDERS
Rough-Elec/Plmb/HVAC 8/23/2021 Approved TROY SANDERS
BUILDING-Rough-Frame 9/14/2021 Approved STEPHANIE SWANSON
Green Building Rough 9/14/2021 Approved STEPHANIE SWANSON
Insulation 9/14/2021 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 9/14/2021 Approved STEPHANIE SWANSON
Drywall Nailing 10/26/2021 Approved JESUS PINEDA
Final 11/23/2021 OK to Issue CofO TROY SANDERS
Green Building Final 11/23/2021 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 11/23/2021 SGSOV Approved TROY SANDERS
Smoke Detectors 11/23/2021 Approved TROY SANDERS