519 N LATIMER ROAD 90402
Certificate Information: 519 N LATIMER ROAD 90402
- Application / Permit
- 20014-30000-04299
- Plan Check / Job No.
- B20WL04279
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel & 1 story addition to (E) 1 story SFD.
- Permit Issued
- Issued on 7/2/2021
- Issuing Office
- Current Status
- CofO in Progress on 10/17/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 10/20/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 10/29/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 6/22/2021 | VLADIMIR ARUTYUNYAN |
| Plan Check Approved | 6/28/2021 | VLADIMIR ARUTYUNYAN |
| Issued | 7/2/2021 | APPLICANT |
| Building Plans Picked Up | 7/2/2021 | APPLICANT |
| CofO in Progress | 12/1/2023 | ARAM AVEDISIAN |
| CofO in Progress | 10/17/2024 | KENNETH NAGLE |
| No Progress | 10/17/2024 | KENNETH NAGLE |
| CofO in Progress | 10/17/2024 | KENNETH NAGLE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/8/2020 | KATHLEEN LEE |
| BHO/Hillside ordinance | Cleared | 12/8/2020 | KATHLEEN LEE |
| BHO/Hillside ordinance | Cleared | 12/8/2020 | KATHLEEN LEE |
| BHO/Hillside ordinance | Cleared | 12/8/2020 | KATHLEEN LEE |
| BHO/Hillside ordinance | Cleared | 12/8/2020 | KATHLEEN LEE |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2020 | KATHLEEN LEE |
| Roof/Waste drainage to street | Cleared | 12/8/2020 | KATHLEEN LEE |
| ZA Case | Cleared | 12/8/2020 | ANACANY HURTADO |
| Coastal Zone | Cleared | 3/5/2021 | ANNA VIDAL |
| Low Impact Development | Cleared | 5/14/2021 | SUNG JOON WON |
| GPI Written Notices | Cleared | 6/28/2021 | VLADIMIR ARUTYUNYAN |
| Grading Pre-Inspection | Cleared | 6/28/2021 | VLADIMIR ARUTYUNYAN |
Contact Information
| Contractor | Garrett Oliver Construction Inc; Lic. No.: 671397-B | 881 WARREN AVENUE VENICE, CA 90291 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Polon,, Gordon Leonard; Lic. No.: C28564 | 709 19TH STREET SANTA MONICA, CA 90402 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/13/2021 | Partial Approval | JOHN KIDWELL |
| Deputy Grading | 7/14/2021 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 7/23/2021 | Conditional Approval | JOHN KIDWELL |
| Piling/Pier/Caisson | 7/23/2021 | Corrections Issued | JOHN KIDWELL |
| Deputy Reinf. Concrete | 7/27/2021 | Conditional Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 8/4/2021 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/4/2021 | Approved | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 8/20/2021 | Partial Approval | JUAN VALENZUELA |
| Underground Mechanical | 9/1/2021 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 9/8/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 9/9/2021 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 10/6/2021 | Approved | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 11/5/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Reinf. Concrete | 11/8/2021 | Corrections Issued | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 11/29/2021 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 12/22/2021 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 12/22/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2022 | Approved | JOHN KIDWELL |
| Rough-Elec/Plmb/HVAC | 1/11/2022 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 1/19/2022 | Corrections Issued | KENNETH NAGLE |
| Rough-Elec/Plmb/HVAC | 2/9/2022 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 3/29/2022 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 4/11/2022 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 4/29/2022 | Approved | JOHN KIDWELL |
| HVAC-Rough | 4/29/2022 | Corrections Issued | JOHN KIDWELL |
| PLUMBING-Rough | 4/29/2022 | Approved | JOHN KIDWELL |
| Drywall Nailing | 5/20/2022 | Approved | JOHN KIDWELL |
| Gas Test | 6/7/2022 | Approved | MICHAEL PELHAM |
| Shower Pan | 6/15/2022 | Partial Approval | JUAN VALENZUELA |
| Interior/Exterior Lathing | 6/21/2022 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 7/11/2022 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Final | 3/29/2023 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 4/3/2023 | Approved | JESUS PINEDA |
| PLUMBING-Final | 4/13/2023 | Approved | OGANES TARAKHCHYAN |
| Pre-Inspection | 5/16/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Pre-Inspection | 5/17/2023 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 6/8/2023 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/29/2023 | Approved | ARAM AVEDISIAN |
| Final | 11/29/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 11/29/2023 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 11/29/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 11/29/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 11/29/2023 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 12/1/2023 | Approved | ARAM AVEDISIAN |
| Final | 12/1/2023 | OK to Issue CofO | ARAM AVEDISIAN |
| HVAC-Final | 12/1/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 12/1/2023 | Approved | ARAM AVEDISIAN |
| Special/Order Compliance | 10/17/2024 | Corrections Issued | KENNETH NAGLE |