249 S MUIRFIELD ROAD 90004
Certificate Information: 249 S MUIRFIELD ROAD 90004
- Application / Permit
- 20014-30000-04242
- Plan Check / Job No.
- B20WL04241
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Ground floor addition to (E) SFD. Remove (E) covered patio.
- Permit Issued
- Issued on 3/5/2021
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2020 | JASON JANGADA |
| Corrections Issued | 11/4/2020 | JASON JANGADA |
| Applicant returned to address corrections | 12/28/2020 | RICHARD GARCIA |
| Applicant returned to address corrections | 1/26/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 2/8/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 2/23/2021 | RICHARD GARCIA |
| Plan Check Approved | 3/2/2021 | RICHARD GARCIA |
| Issued | 3/5/2021 | APPLICANT |
| Building Plans Picked Up | 3/8/2021 | APPLICANT |
| CofO in Progress | 5/4/2022 | SCOTT FINNILA |
| Permit Finaled | 12/17/2022 | DEROLD HAUFF |
| CofO Issued | 12/17/2022 | DEROLD HAUFF |
| Permit Finaled | 12/17/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 11/18/2020 | RENZ SORIANO |
| Sewer availability | Cleared | 11/18/2020 | RENZ SORIANO |
| CPC | Cleared | 12/3/2020 | SUKI GERSHENHORN |
| HPOZ | Cleared | 12/3/2020 | SUKI GERSHENHORN |
| ZI | Cleared | 12/3/2020 | SUKI GERSHENHORN |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Grant General Contracting Inc; Lic. No.: 1016710-B | 5776-D LINDERO CANYON RD #412 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/12/2021 | Conditional Approval | JOSEPH MCGARRY |
| METHANE-Barrier | 3/12/2021 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 3/12/2021 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 3/15/2021 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Drilled-In Anchors | 4/5/2021 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2021 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 5/5/2021 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 5/5/2021 | Approved | DAVID FEILER |
| Green Building Rough | 5/5/2021 | Approved | DAVID FEILER |
| HVAC-Rough | 5/5/2021 | Approved | DAVID FEILER |
| METHANE-Rough | 5/5/2021 | Approved | DAVID FEILER |
| Drywall Nailing | 5/12/2021 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 6/9/2021 | Approved | WILLIAM WREN |
| Final | 11/16/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 11/16/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Final | 11/16/2021 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 11/16/2021 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 11/16/2021 | Approved | ARTHUR SARGSYAN |
| Final | 12/13/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Final | 1/7/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 3/9/2022 | Corrections Issued | ARTHUR SARGSYAN |
| Verify Rec and Parks Fee Memo | 3/9/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 5/4/2022 | Approved | SCOTT FINNILA |
| Final | 5/4/2022 | OK to Issue CofO | SCOTT FINNILA |
| HVAC-Final | 5/4/2022 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 5/4/2022 | Approved | SCOTT FINNILA |