249 S MUIRFIELD ROAD 90004

Certificate Information: 249 S MUIRFIELD ROAD 90004

Application / Permit
20014-30000-04242
Plan Check / Job No.
B20WL04241
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Ground floor addition to (E) SFD. Remove (E) covered patio.
Permit Issued
Issued on 3/5/2021
Issuing Office
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2020 APPLICANT
Assigned to Plan Check Engineer 11/2/2020 JASON JANGADA
Corrections Issued 11/4/2020 JASON JANGADA
Applicant returned to address corrections 12/28/2020 RICHARD GARCIA
Applicant returned to address corrections 1/26/2021 RICHARD GARCIA
Applicant returned to address corrections 2/8/2021 RICHARD GARCIA
Applicant returned to address corrections 2/23/2021 RICHARD GARCIA
Plan Check Approved 3/2/2021 RICHARD GARCIA
Issued 3/5/2021 APPLICANT
Building Plans Picked Up 3/8/2021 APPLICANT
CofO in Progress 5/4/2022 SCOTT FINNILA
Permit Finaled 12/17/2022 DEROLD HAUFF
CofO Issued 12/17/2022 DEROLD HAUFF
Permit Finaled 12/17/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/18/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 11/18/2020 RENZ SORIANO
Sewer availability Cleared 11/18/2020 RENZ SORIANO
CPC Cleared 12/3/2020 SUKI GERSHENHORN
HPOZ Cleared 12/3/2020 SUKI GERSHENHORN
ZI Cleared 12/3/2020 SUKI GERSHENHORN

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Grant General Contracting Inc; Lic. No.: 1016710-B 5776-D LINDERO CANYON RD   #412    WESTLAKE VILLAGE, CA 91362

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/12/2021 Conditional Approval JOSEPH MCGARRY
METHANE-Barrier 3/12/2021 Approved JOSEPH MCGARRY
METHANE-Subgrade 3/12/2021 Approved JOSEPH MCGARRY
Deputy Drilled-In Anchors 3/15/2021 Conditional Approval THOMAS LOGRASSO
Deputy Drilled-In Anchors 4/5/2021 No Access for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 4/8/2021 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 5/5/2021 Approved DAVID FEILER
ELECTRICAL-Rough 5/5/2021 Approved DAVID FEILER
Green Building Rough 5/5/2021 Approved DAVID FEILER
HVAC-Rough 5/5/2021 Approved DAVID FEILER
METHANE-Rough 5/5/2021 Approved DAVID FEILER
Drywall Nailing 5/12/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 6/9/2021 Approved WILLIAM WREN
Final 11/16/2021 Corrections Issued ARTHUR SARGSYAN
Footing/Foundation/Slab 11/16/2021 Approved ARTHUR SARGSYAN
Green Building Final 11/16/2021 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 11/16/2021 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 11/16/2021 Approved ARTHUR SARGSYAN
Final 12/13/2021 Not Ready for Inspection ARTHUR SARGSYAN
Final 1/7/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Final 3/9/2022 Corrections Issued ARTHUR SARGSYAN
Verify Rec and Parks Fee Memo 3/9/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 5/4/2022 Approved SCOTT FINNILA
Final 5/4/2022 OK to Issue CofO SCOTT FINNILA
HVAC-Final 5/4/2022 Approved SCOTT FINNILA
PLUMBING-Final 5/4/2022 Approved SCOTT FINNILA