833 E 82ND ST 90001

Certificate Information: 833 E 82ND ST 90001

Application / Permit
20014-30000-04189
Plan Check / Job No.
B20WL04166
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
new detached 1-story ADU (rear) (existing garage will be part of ADU) per ordinance.
Permit Issued
Issued on 1/12/2021
Issuing Office
Current Status
CofO Issued on 7/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 KAVIAN REFAHI
Corrections Issued 9/26/2020 KAVIAN REFAHI
Applicant returned to address corrections 12/27/2020 KAVIAN REFAHI
Plan Check Approved 12/31/2020 KAVIAN REFAHI
Building Plans Picked Up 1/4/2021 APPLICANT
Issued 1/12/2021 APPLICANT
CofO in Progress 7/6/2021 DAVID FEILER
Permit Finaled 7/8/2021 DEROLD HAUFF
CofO Issued 7/8/2021 DEROLD HAUFF
Permit Finaled 7/8/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/21/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 10/27/2020 THOMAS LANG
Sewer availability Cleared 10/29/2020 THOMAS LANG
Hydrant and Access approval Cleared 10/30/2020 MATTHEW CRAIG
Construction near power lines Cleared 12/13/2020 RIDWAN HARDY
Low Impact Development Cleared 12/15/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 12/16/2020 THOMAS LANG

Contact Information

Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701
Engineer Inman,, Donald J; Lic. No.: C11888 5131 FOX HILLS AVENUE      BUENA PARK, CA 90621

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/12/2021 Conditional Approval EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 2/18/2021 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/4/2021 Partial Approval DAVID FEILER
ELECTRICAL-Rough 3/11/2021 Approved EUGENE CASSIDY
HVAC-Rough 3/11/2021 Conditional Approval EUGENE CASSIDY
Interior/Exterior Lathing 3/11/2021 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 3/11/2021 Approved EUGENE CASSIDY
Insulation 3/18/2021 Approved EUGENE CASSIDY
Drywall Nailing 3/22/2021 Approved DAVID FEILER
Interior/Exterior Lathing 3/30/2021 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 4/5/2021 Approved EUGENE CASSIDY
ELECTRICAL-Rough 4/16/2021 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 4/16/2021 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 4/22/2021 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 4/26/2021 Corrections Issued FREDDIE RIVERA
Underground Mechanical 5/5/2021 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/18/2021 Approved EUGENE CASSIDY
Footing/Foundation/Slab 5/18/2021 Approved EUGENE CASSIDY
Green Building Final 5/18/2021 Corrections Issued EUGENE CASSIDY
Green Building Rough 5/18/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 5/18/2021 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 5/18/2021 Not Ready for Inspection EUGENE CASSIDY
Final 5/21/2021 Corrections Issued EUGENE CASSIDY
Final 6/7/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 6/7/2021 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/7/2021 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 6/7/2021 Approved EUGENE CASSIDY
Final 6/22/2021 Partial Inspection DAVID FEILER
Green Building Final 6/22/2021 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 6/22/2021 SGSOV Approved DAVID FEILER
Final 7/6/2021 OK to Issue CofO DAVID FEILER
Service/Power Release 7/6/2021 Approved DAVID FEILER