941 N HIGHLAND AVE 90038

Certificate Information: 941 N HIGHLAND AVE 90038

Application / Permit
20014-30000-04181
Plan Check / Job No.
B20WL04156
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(4) Art Gallery
Work Description
Mezzanine addition (B OCC. = 3,323 sf), tenant improvement and change of use from manufacturing (warehouse) to Fine Art & Interior Design Gallery (No Retail) per ZA-2019-7489-ZAI at portion of 1st floor (10,831 sf) of (e) 2-story commercial building.
Permit Issued
Issued on 10/6/2021
Issuing Office
Current Status
CofO Issued on 8/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2020 APPLICANT
Assigned to Plan Check Engineer 9/30/2020 REZA HAGHIGHAT
Green Plans Picked Up 10/9/2020 APPLICANT
Corrections Issued 10/19/2020 REZA HAGHIGHAT
Quality Review Completed 10/30/2020 KAMRAN GHOTBI RAVANDI
Disabled Access Plans Picked Up 10/30/2020 APPLICANT
Applicant returned to address corrections 11/16/2020 REZA HAGHIGHAT
Applicant returned to address corrections 2/8/2021 REZA HAGHIGHAT
Applicant returned to address corrections 3/23/2021 REZA HAGHIGHAT
Applicant returned to address corrections 5/12/2021 REZA HAGHIGHAT
Applicant returned to address corrections 7/29/2021 REZA HAGHIGHAT
Plan Check Approved 10/6/2021 REZA HAGHIGHAT
Issued 10/6/2021 APPLICANT
Building Plans Picked Up 10/7/2021 APPLICANT
CofO in Progress 7/19/2022 EDWIN GREGORYONA
CofO in Progress 7/19/2022 EDWIN GREGORYONA
Permit Finaled 8/1/2022 ERNESTO CORRAL
CofO Issued 8/1/2022 ERNESTO CORRAL
Permit Finaled 8/1/2022 ERNESTO CORRAL

Permit Application Clearance Information

ZI Cleared 11/10/2020 DENZEL HENDERSON
Eng Process Fee Ord 176,300 Cleared 11/13/2020 CECILIO NAVARRO
Sewer availability Cleared 12/9/2020 CECILIO NAVARRO
ZA Case Cleared 4/15/2021 DENZEL HENDERSON
ZI Cleared 4/20/2021 DENZEL HENDERSON
Green Code Cleared 9/20/2021 RICHARD GARCIA
DAS Clearance Cleared 9/27/2021 REZA HAGHIGHAT

Contact Information

Architect Johnston-Lee,, Sharon L; Lic. No.: C28130 1545 PONTIUS AVE      LOS ANGELES, CA 90025
Contractor Dickinson Cameron Construction Company Inc; Lic. No.: 690239-B 6184 INNOVATION WAY      CARLSBAD, CA 92009
Engineer Melnyk,, Matthew John; Lic. No.: S5853 527 WEST 7TH ST STE 701      LOS ANGELES, CA 90014

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/14/2021 Approved KATY RAMIREZ
Footing/Foundation/Slab 10/20/2021 Partial Approval KATY RAMIREZ
METHANE-Barrier 10/20/2021 Approved KATY RAMIREZ
METHANE-Subgrade 10/20/2021 Approved KATY RAMIREZ
Deputy Drilled-In Anchors 10/22/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Masonry 10/22/2021 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 11/1/2021 No Access for Inspection KATY RAMIREZ
Footing/Foundation/Slab 11/1/2021 No Access for Inspection KATY RAMIREZ
Deputy Drilled-In Anchors 11/2/2021 Conditional Approval TIMOTHY BUXTON
Excavation/Setback/Form/Re-Bar 11/2/2021 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 11/5/2021 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 11/8/2021 Not Ready for Inspection KATY RAMIREZ
Deputy Wood Construction 11/9/2021 Conditional Approval KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 11/10/2021 Approved KATY RAMIREZ
Green Building Rough 11/10/2021 Approved KATY RAMIREZ
METHANE-Rough 11/10/2021 Approved KATY RAMIREZ
Structural Steel Frame 11/10/2021 Partial Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 11/12/2021 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 12/20/2021 Partial Inspection JONATHAN QUACH
Structural Steel Frame 12/20/2021 Not Ready for Inspection JONATHAN QUACH
Wall Anchors 12/20/2021 Not Ready for Inspection JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 12/30/2021 Partial Approval JONATHAN QUACH
Deputy Drilled-In Anchors 1/4/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 1/4/2022 Conditional Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 1/5/2022 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 1/12/2022 Conditional Approval JONATHAN QUACH
Deputy Drilled-In Anchors 1/13/2022 Conditional Approval DARRYL ARNOLD
Light Gage Steel Frame 1/20/2022 Partial Approval EDWIN GREGORYONA
Masonry Wall/Backfill 1/20/2022 Partial Approval EDWIN GREGORYONA
Structural Steel Frame 1/20/2022 Partial Approval EDWIN GREGORYONA
Light Gage Steel Frame 2/8/2022 Partial Approval KATY RAMIREZ
Structural Steel Frame 2/8/2022 Partial Inspection KATY RAMIREZ
Deputy Steel/Welding 2/9/2022 Conditional Approval KATY RAMIREZ
Drywall Nailing 2/14/2022 Partial Approval KATY RAMIREZ
Structural Steel Frame 2/18/2022 Partial Inspection KATY RAMIREZ
Pre-Inspection 2/22/2022 Not Ready for Inspection KATY RAMIREZ
Deputy Steel/Welding 3/21/2022 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 4/12/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/12/2022 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 4/13/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/13/2022 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 4/14/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/14/2022 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 5/9/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/9/2022 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 5/10/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/10/2022 Conditional Approval KATY RAMIREZ
Structural Steel Frame 5/11/2022 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 5/18/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/18/2022 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 5/19/2022 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/19/2022 Conditional Approval KATY RAMIREZ
Pre-Inspection 5/27/2022 Approved DAVID BURKHEAD
Pre-Inspection 6/1/2022 Partial Inspection KATY RAMIREZ
Special/Order Compliance 6/15/2022 Approved KATY RAMIREZ
Deputy Drilled-In Anchors 6/16/2022 Conditional Approval ERNESTO CORRAL
Drywall Nailing 7/11/2022 Approved EDWIN GREGORYONA
Final 7/11/2022 OK to Issue CofO EDWIN GREGORYONA
Footing/Foundation/Slab 7/11/2022 Approved EDWIN GREGORYONA
Green Building Final 7/11/2022 Approved EDWIN GREGORYONA
Reinforced Masonry Frame 7/11/2022 Approved EDWIN GREGORYONA
SGSOV-Seismic Gas S/O Valve 7/11/2022 SGSOV Approved EDWIN GREGORYONA
Smoke Detectors 7/11/2022 Approved EDWIN GREGORYONA
Structural Steel Frame 7/11/2022 Approved EDWIN GREGORYONA