Pre-Inspection
|
8/12/2021
|
Approved
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
9/20/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
9/21/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
9/21/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Footing/Foundation/Slab
|
9/21/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
9/22/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Excavation/Setback/Form/Re-Bar
|
9/22/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Pre-Inspection
|
9/28/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
9/29/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Footing/Foundation/Slab
|
9/30/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
10/4/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Excavation/Setback/Form/Re-Bar
|
10/4/2021
|
Not Ready for Inspection
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
10/5/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Reinforced Concrete Frame
|
10/5/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
10/6/2021
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
10/13/2021
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Drilled-In Anchors
|
10/13/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Excavation/Setback/Form/Re-Bar
|
10/13/2021
|
Not Ready for Inspection
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
10/13/2021
|
Not Ready for Inspection
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
10/14/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Excavation/Setback/Form/Re-Bar
|
10/14/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Green Building Rough
|
10/14/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Piling/Pier/Caisson
|
10/14/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
10/15/2021
|
Not Ready for Inspection
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
10/18/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
10/19/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Footing/Foundation/Slab
|
10/19/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
10/25/2021
|
Not Ready for Inspection
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
10/26/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
10/27/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
10/28/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
10/28/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
10/29/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Excavation/Setback/Form/Re-Bar
|
10/29/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
11/1/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
11/1/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
11/2/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
11/3/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
11/4/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
11/5/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
11/10/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
11/12/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
11/15/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Shotcrete
|
11/15/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
11/16/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
11/17/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
11/18/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
11/18/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Green Building Rough
|
11/18/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Wood Frame
|
11/18/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
11/19/2021
|
Conditional Approval
|
TIMOTHY BUXTON
|
|
Deputy Drilled-In Anchors
|
11/23/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Shotcrete
|
11/23/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Reinforced Concrete Frame
|
11/23/2021
|
Partial Inspection
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
11/24/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
11/24/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Excavation/Setback/Form/Re-Bar
|
11/24/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
11/24/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
12/8/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
12/9/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Green Building Rough
|
12/15/2021
|
Partial Inspection
|
TED RIES
|
|
Reinforced Concrete Frame
|
12/15/2021
|
Partial Inspection
|
TED RIES
|
|
Structural Steel Frame
|
12/15/2021
|
Partial Inspection
|
TED RIES
|
|
Deputy Drilled-In Anchors
|
12/16/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
12/17/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
12/20/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Footing/Foundation/Slab
|
12/20/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Green Building Rough
|
12/21/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Structural Steel Frame
|
12/21/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Wood Frame
|
12/21/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
1/12/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
1/12/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Green Building Rough
|
1/12/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Reinforced Masonry Frame
|
1/12/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Structural Steel Frame
|
1/12/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
1/13/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
1/13/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
1/14/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
1/14/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Green Building Rough
|
1/14/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Reinforced Concrete Frame
|
1/14/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Reinforced Masonry Frame
|
1/14/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Structural Steel Frame
|
1/14/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
1/19/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
1/19/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Green Building Rough
|
1/19/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Reinforced Concrete Frame
|
1/19/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Structural Steel Frame
|
1/19/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
1/20/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
1/20/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
1/21/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
1/21/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
1/24/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
1/24/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
1/24/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Reinforced Concrete Frame
|
1/24/2022
|
Partial Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
1/25/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
1/25/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
1/25/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Footing/Foundation/Slab
|
1/25/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Green Building Rough
|
1/25/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Reinforced Masonry Frame
|
1/25/2022
|
Partial Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
1/26/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
1/26/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
1/26/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Masonry Wall/Backfill
|
1/26/2022
|
Partial Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
1/27/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
1/27/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
1/27/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
1/28/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
1/28/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
1/28/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
1/31/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
1/31/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
2/1/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
2/1/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
2/1/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Reinforced Concrete Frame
|
2/1/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
2/2/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
2/2/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Green Building Rough
|
2/2/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Piling/Pier/Caisson
|
2/2/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Reinforced Concrete Frame
|
2/2/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Wood Frame
|
2/2/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
2/3/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
2/3/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Excavation/Setback/Form/Re-Bar
|
2/3/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Structural Steel Frame
|
2/3/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
2/4/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
2/4/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
2/11/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Green Building Rough
|
2/15/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Structural Steel Frame
|
2/15/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Wood Frame
|
2/15/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
2/16/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
2/16/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
2/16/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
2/17/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
2/17/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
2/17/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
2/18/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
2/18/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
2/18/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
2/22/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
2/22/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
2/23/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
2/23/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
2/24/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
2/24/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
2/25/2022
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
2/25/2022
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
3/2/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Green Building Rough
|
3/2/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Masonry Wall/Backfill
|
3/2/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Reinforced Masonry Frame
|
3/2/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
3/3/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
3/4/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
3/11/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Green Building Rough
|
3/11/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Reinforced Masonry Frame
|
3/11/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
3/14/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
3/15/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
3/16/2022
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
3/17/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Masonry Wall/Backfill
|
3/17/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
3/18/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
3/21/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
3/22/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
3/22/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Green Building Rough
|
3/22/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Reinforced Masonry Frame
|
3/22/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
3/23/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
3/24/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Reinforced Concrete Frame
|
3/24/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
3/25/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Masonry
|
4/7/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Masonry
|
4/8/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
4/8/2022
|
Corrections Issued
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
4/11/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
4/12/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
4/13/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
4/14/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Wood Construction
|
4/14/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
4/15/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/15/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/22/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/3/2022
|
Not Ready for Inspection
|
EDWIN GREGORYONA
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/11/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Wall Anchors
|
5/11/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Excavation/Setback/Form/Re-Bar
|
5/18/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
T-Bar Ceiling
|
5/18/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Drywall Nailing
|
5/24/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Green Building Rough
|
5/24/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Drywall Nailing
|
5/26/2022
|
Partial Inspection
|
JONATHAN QUACH
|
|
Green Building Final
|
6/10/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Green Building Rough
|
6/10/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
SGSOV-Seismic Gas S/O Valve
|
6/10/2022
|
SGSOV Not Ready
|
JONATHAN QUACH
|
|
Smoke Detectors
|
6/10/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Drywall Nailing
|
6/23/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Final
|
6/23/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Footing/Foundation/Slab
|
6/23/2022
|
Partial Approval
|
JONATHAN QUACH
|
|
Green Building Final
|
6/23/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Green Building Rough
|
6/23/2022
|
Approved
|
JONATHAN QUACH
|
|
Reinforced Masonry Frame
|
6/23/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
SGSOV-Seismic Gas S/O Valve
|
6/23/2022
|
SGSOV Not Ready
|
JONATHAN QUACH
|
|
Smoke Detectors
|
6/23/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Structural Steel Frame
|
6/23/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
Wood Frame
|
6/23/2022
|
Not Ready for Inspection
|
JONATHAN QUACH
|
|
SGSOV-Seismic Gas S/O Valve
|
9/20/2022
|
SGSOV Approved
|
JONATHAN QUACH
|
|
Smoke Detectors
|
9/20/2022
|
Approved
|
JONATHAN QUACH
|
|
Drywall Nailing
|
5/23/2023
|
Partial Inspection
|
JULIAN CAPUCETTI
|
|
Final
|
5/23/2023
|
Not Ready for Inspection
|
JULIAN CAPUCETTI
|
|
Footing/Foundation/Slab
|
5/23/2023
|
Approved
|
JULIAN CAPUCETTI
|
|
Green Building Final
|
5/23/2023
|
Not Ready for Inspection
|
JULIAN CAPUCETTI
|
|
Reinforced Masonry Frame
|
5/23/2023
|
Partial Inspection
|
JULIAN CAPUCETTI
|
|
Structural Steel Frame
|
5/23/2023
|
Partial Inspection
|
JULIAN CAPUCETTI
|
|
Wood Frame
|
5/23/2023
|
Partial Inspection
|
JULIAN CAPUCETTI
|
|
Drywall Nailing
|
7/13/2023
|
Approved
|
RONALD JIMENEZ
|
|
Final
|
7/13/2023
|
Conditional Approval
|
RONALD JIMENEZ
|
|
Green Building Final
|
7/13/2023
|
Approved
|
RONALD JIMENEZ
|
|
Reinforced Masonry Frame
|
7/13/2023
|
Approved
|
RONALD JIMENEZ
|
|
Structural Steel Frame
|
7/13/2023
|
Approved
|
RONALD JIMENEZ
|
|
Wood Frame
|
7/13/2023
|
Approved
|
RONALD JIMENEZ
|
|
Final
|
2/28/2024
|
Not Ready for Inspection
|
JEFFREY FULTON
|
|
Special/Order Compliance
|
5/31/2024
|
Approved
|
RAFAEL CORTES
|
|
Special/Order Compliance
|
6/24/2024
|
Corrections Issued
|
RONALD JIMENEZ
|
|
Special/Order Compliance
|
11/26/2024
|
Partial Approval
|
LUIS CCAMACHO
|
|
Special/Order Compliance
|
5/20/2025
|
Partial Approval
|
LUIS CCAMACHO
|