10346 W ILONA AVE 90064
Certificate Information: 10346 W ILONA AVE 90064
- Application / Permit
- 20014-30000-04041
- Plan Check / Job No.
- B20WL04071
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-story addition to existing 1-story s.f.d.
- Permit Issued
- Issued on 1/6/2021
- Issuing Office
- Current Status
- CofO Issued on 10/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2020 | TARIK SAOUD |
| Corrections Issued | 10/22/2020 | TARIK SAOUD |
| Quality Review Completed | 10/29/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/24/2020 | TARIK SAOUD |
| Plan Check Approved | 12/28/2020 | TARIK SAOUD |
| Issued | 1/6/2021 | APPLICANT |
| Building Plans Picked Up | 1/7/2021 | APPLICANT |
| CofO in Progress | 10/18/2022 | STEPHANIE SWANSON |
| Permit Finaled | 10/28/2022 | DANIEL ORRANTE |
| CofO Issued | 10/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/5/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 11/6/2020 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 11/6/2020 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 11/24/2020 | TARIK SAOUD |
| Specific Plan | Cleared | 12/7/2020 | FREDDY GARCIA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Griffin John Construction; Lic. No.: 292252-B | 10310 ILONA AVENUE LOS ANGELES, CA 90064 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/19/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Barrier | 2/19/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Subgrade | 2/19/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 4/5/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Rough | 4/5/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 4/5/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Deputy Wood Construction | 5/7/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/21/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 6/3/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 8/12/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 8/12/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 8/12/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 8/31/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 8/31/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 8/31/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Insulation | 9/22/2021 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 10/4/2021 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Shower Pan | 11/30/2021 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 12/23/2021 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 8/31/2022 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 8/31/2022 | SGSOV Not Ready | STEPHANIE SWANSON |
| Final | 10/6/2022 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 10/6/2022 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 10/6/2022 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 10/6/2022 | Approved | STEPHANIE SWANSON |
| Special/Order Compliance | 10/6/2022 | Partial Inspection | CLAYTON GRAHAM |
| Final | 10/18/2022 | OK to Issue CofO | STEPHANIE SWANSON |