10752 W WESTMINSTER AVE 90034

Certificate Information: 10752 W WESTMINSTER AVE 90034

Application / Permit
20014-30000-04033
Plan Check / Job No.
B20WL04069
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
major remodel & 1st & 2nd story addition w/ attached garage to (e) 1-story s.f.d.
Permit Issued
Issued on 12/2/2021
Issuing Office
Current Status
CofO Issued on 7/24/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2020 APPLICANT
Assigned to Plan Check Engineer 10/14/2020 TARIK SAOUD
Corrections Issued 10/22/2020 TARIK SAOUD
Quality Review Completed 10/29/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 3/11/2021 TARIK SAOUD
Applicant returned to address corrections 6/11/2021 TARIK SAOUD
Applicant returned to address corrections 10/21/2021 TARIK SAOUD
Plan Check Approved 11/17/2021 TARIK SAOUD
Building Plans Picked Up 11/18/2021 APPLICANT
Issued 12/2/2021 APPLICANT
CofO in Progress 7/17/2023 JESUS PINEDA
Permit Finaled 7/24/2023 DANIEL ORRANTE
CofO Issued 7/24/2023 DANIEL ORRANTE
Permit Finaled 7/24/2023 DANIEL ORRANTE

Permit Application Clearance Information

Frnt yard landscape/Water mgmt Cleared 2/16/2021 KENTON TRINH
Specific Plan Cleared 2/18/2021 KEVIN ARUCAN
Eng Process Fee Ord 176,300 Cleared 2/23/2021 TRACY TATE
Permit Cleared 2/23/2021 TRACY TATE
Sewer availability Cleared 2/23/2021 TRACY TATE
Trees in Parkway Cleared 3/9/2021 JOHN KIM
Hydrant and Access approval Cleared 4/15/2021 JOHN CONNEALLY
Low Impact Development Cleared 9/30/2021 TA ANH
Roof/Waste drainage to street Cleared 10/6/2021 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Simonian,, Ara; Lic. No.: C37208 314 E BROADWAY STE A      GLENDALE, CA 91205

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/15/2022 Corrections Issued JOHNNY MIRANDA
Underground Mechanical 2/15/2022 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 4/7/2022 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 12/21/2022 Corrections Issued STEPHANIE SWANSON
BUILDING-Rough-Frame 2/7/2023 Approved JOHNNY MIRANDA
Drywall Nailing 2/7/2023 Approved JOHNNY MIRANDA
Green Building Rough 2/7/2023 Approved JOHNNY MIRANDA
Insulation 2/7/2023 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 2/7/2023 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Final 5/17/2023 Approved JOHNNY MIRANDA
Final 6/16/2023 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 6/16/2023 Approved JOHNNY MIRANDA
Green Building Final 6/16/2023 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 6/16/2023 SGSOV Approved JOHNNY MIRANDA
Service/Power Release 6/16/2023 Approved JOHNNY MIRANDA
Smoke Detectors 6/16/2023 Approved JOHNNY MIRANDA
Final 7/11/2023 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 7/11/2023 SGSOV Not Ready JESUS PINEDA
Final 7/14/2023 OK to Issue CofO JESUS PINEDA
HVAC-Final 7/14/2023 Approved JESUS PINEDA
PLUMBING-Final 7/14/2023 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 7/14/2023 SGSOV Approved JESUS PINEDA