3525 S MAY ST 90066

Certificate Information: 3525 S MAY ST 90066

Application / Permit
20014-30000-04020
Plan Check / Job No.
B20WL04055
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TO EXISTING SINGLE FAMILY DWELLING WITH NEW ATTACHED 2-CAR GARAGE, EQUIPPED THROUGHOUT WITH NFPA 13D FIRE SPRINKLERS. COMPLY WITH DEPARTMENT ORDER effective date 12/17/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE. CEIS Case Number is 901970.
Permit Issued
Issued on 6/30/2021
Issuing Office
Current Status
CofO Issued on 4/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2020 APPLICANT
Assigned to Plan Check Engineer 10/14/2020 SERGIO SILVA
Corrections Issued 10/28/2020 SERGIO SILVA
Quality Review Completed 11/4/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 11/5/2020 APPLICANT
Applicant returned to address corrections 5/5/2021 SERGIO SILVA
Applicant returned to address corrections 5/6/2021 SERGIO SILVA
Applicant returned to address corrections 6/3/2021 SERGIO SILVA
Plan Check Approved 6/17/2021 SERGIO SILVA
Issued 6/30/2021 APPLICANT
CofO in Progress 4/12/2022 JOHN MATTILLO
Permit Finaled 4/20/2022 BRUCE TODD
CofO Issued 4/20/2022 BRUCE TODD
Permit Finaled 4/20/2022 BRUCE TODD

Permit Application Clearance Information

Specific Plan Cleared 12/10/2020 FREDDY GARCIA
Hydrant and Access approval Cleared 12/17/2020 MATTHEW CRAIG
Low Impact Development Cleared 3/17/2021 ANDRES COVARRUBIAS
Address approval Cleared 3/19/2021 DINAH GARIN
Permit Cleared 3/19/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 3/19/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 3/22/2021 DINAH GARIN
Sewer availability Cleared 3/22/2021 DINAH GARIN
Disturb/Remove Protected Trees Cleared 4/13/2021 SERGIO SILVA
GPI Written Notices Cleared 5/6/2021 SERGIO SILVA
Grading Pre-Inspection Cleared 5/6/2021 SERGIO SILVA
Green Code Cleared 6/17/2021 SERGIO SILVA

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Azarmy,, Cyrus; Lic. No.: L9404 4402 CHARLEMONT AVE      WOODLAND HILLS, CA 91364
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 7/2/2021 Not Ready for Inspection MARIAN PODPORA
Excavation/Setback/Form/Re-Bar 7/20/2021 Approved RYAN BARNES
Underground Mechanical 7/28/2021 Partial Approval RYAN BARNES
Underground Mechanical 7/29/2021 Partial Approval RYAN BARNES
Footing/Foundation/Slab 8/2/2021 Approved RYAN BARNES
Underground Mechanical 8/2/2021 Approved RYAN BARNES
BUILDING-Rough-Frame 8/25/2021 Partial Approval RYAN BARNES
Green Building Rough 8/25/2021 Approved RYAN BARNES
Wood Frame 8/25/2021 Partial Approval RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 Not Ready for Inspection RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 9/23/2021 Approved RYAN BARNES
HVAC-Rough 10/25/2021 Corrections Issued RYAN BARNES
PLUMBING-Rough 10/25/2021 Approved RYAN BARNES
Shower Pan 10/25/2021 Approved RYAN BARNES
ELECTRICAL-Rough 11/2/2021 Corrections Issued RYAN BARNES
BUILDING-Rough-Frame 11/8/2021 Not Ready for Inspection RYAN BARNES
ELECTRICAL-Rough 11/8/2021 Approved RYAN BARNES
HVAC-Rough 11/8/2021 Approved RYAN BARNES
BUILDING-Rough-Frame 11/10/2021 Approved RYAN BARNES
Shower Pan 11/15/2021 Approved RYAN BARNES
Wood Frame 11/15/2021 Approved RYAN BARNES
Insulation 11/23/2021 Approved RYAN BARNES
Interior/Exterior Lathing 11/23/2021 Corrections Issued RYAN BARNES
Interior/Exterior Lathing 11/24/2021 Approved RYAN BARNES
Drywall Nailing 11/30/2021 Approved RYAN BARNES
Interior/Exterior Lathing 11/30/2021 Approved RYAN BARNES
PLUMBING-Final 3/15/2022 Partial Approval RYAN BARNES
ELECTRICAL-Final 3/17/2022 Not Ready for Inspection RYAN BARNES
HVAC-Final 3/17/2022 Not Ready for Inspection RYAN BARNES
HVAC-Final 3/18/2022 Not Ready for Inspection RYAN BARNES
ELECTRICAL-Final 3/21/2022 Approved RYAN BARNES
HVAC-Final 3/21/2022 Approved RYAN BARNES
PLUMBING-Final 3/21/2022 Conditional Approval RYAN BARNES
Service/Power Release 3/21/2022 Approved RYAN BARNES
Final 3/22/2022 Not Ready for Inspection RYAN BARNES
Green Building Final 3/22/2022 Approved RYAN BARNES
SGSOV-Seismic Gas S/O Valve 3/22/2022 SGSOV Not Ready RYAN BARNES
Smoke Detectors 3/22/2022 Approved RYAN BARNES
Final 4/5/2022 Conditional Approval RYAN BARNES
SGSOV-Seismic Gas S/O Valve 4/5/2022 SGSOV Approved RYAN BARNES