1050 W PALMS BLVD 90291

Certificate Information: 1050 W PALMS BLVD 90291

Application / Permit
20014-30000-04000
Plan Check / Job No.
B20WL04020
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) detached garage with ADU above per LAMC 12.22A.33(c) & (d) at rear of the lot.
Permit Issued
Issued on 2/18/2022
Issuing Office
Current Status
CofO Issued on 7/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2021 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 JAHANSHAH POURHASSAN
Corrections Issued 1/25/2021 JAHANSHAH POURHASSAN
Quality Review Completed 2/4/2021 TARIK SAOUD
Building Plans Picked Up 2/5/2021 APPLICANT
Applicant returned to address corrections 7/9/2021 JAHANSHAH POURHASSAN
Plan Check Approved 7/20/2021 JAHANSHAH POURHASSAN
Issued 2/18/2022 APPLICANT
CofO in Progress 7/13/2023 EVAN COOPER
Permit Finaled 7/17/2023 DANIEL ORRANTE
CofO Issued 7/17/2023 DANIEL ORRANTE
Permit Finaled 7/17/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/11/2021 DENNIS BRAGIN
Sewer availability Cleared 3/11/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 3/14/2021 DENNIS BRAGIN
Hydrant and Access approval Cleared 5/13/2021 KURT CORRAL
Low Impact Development Cleared 6/3/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 6/14/2021 DENNIS BRAGIN

Contact Information

Architect Gonzalez,, Jose Antonio; Lic. No.: C33472 6210 WILSHIRE BLVD SUITE 209      LOS ANGELES, CA 90048
Contractor Sun Developers Inc; Lic. No.: 865631-B 23371 MULHOLLAND DRIVE #295      WOODLAND HILLS, CA 91364
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/5/2022 Corrections Issued DAVID FEILER
Underground Mechanical 7/5/2022 Not Ready for Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 7/8/2022 Approved DAVID FEILER
Footing/Foundation/Slab 7/8/2022 Approved DAVID FEILER
Deputy Wood Construction 7/20/2022 No Access for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 7/22/2022 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 8/9/2022 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 8/24/2022 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 8/24/2022 Partial Approval DAVID FEILER
Green Building Rough 8/24/2022 Not Ready for Inspection DAVID FEILER
Verify Sprinkler Sign Off 8/24/2022 Not Ready for Inspection DAVID FEILER
HVAC-Rough 9/6/2022 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 9/19/2022 Corrections Issued DAVID FEILER
HVAC-Rough 9/22/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 9/22/2022 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 9/26/2022 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 9/26/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 9/28/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 10/3/2022 Corrections Issued CLAYTON GRAHAM
ELECTRICAL-Rough 10/5/2022 Approved DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/5/2022 Partial Approval DAVID FEILER
Sewer 10/5/2022 Approved DAVID FEILER
Underground Mechanical 10/5/2022 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 10/18/2022 Partial Approval DAVID FEILER
Green Building Rough 10/18/2022 Not Ready for Inspection DAVID FEILER
Verify Sprinkler Sign Off 10/18/2022 Not Ready for Inspection DAVID FEILER
HVAC-Rough 10/27/2022 Approved JESUS RODRIGUEZ
Underground Mechanical 11/2/2022 Not Ready for Inspection DAVID FEILER
Interior/Exterior Lathing 12/8/2022 Not Ready for Inspection CLAYTON GRAHAM
Interior/Exterior Lathing 12/9/2022 Approved JESUS RODRIGUEZ
Shower Pan 12/9/2022 Corrections Issued JESUS RODRIGUEZ
Shower Pan 12/12/2022 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 12/14/2022 Approved EVAN COOPER
Green Building Rough 12/14/2022 Approved EVAN COOPER
Verify Sprinkler Sign Off 12/14/2022 Approved EVAN COOPER
Final 12/21/2022 Corrections Issued JESUS RODRIGUEZ
Insulation 12/21/2022 Approved JESUS RODRIGUEZ
Shower Pan 12/21/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 1/5/2023 Approved EVAN COOPER
HVAC-Final 5/23/2023 Approved EVAN COOPER
ELECTRICAL-Final 6/6/2023 Corrections Issued EVAN COOPER
PLUMBING-Final 6/6/2023 Corrections Issued EVAN COOPER
ELECTRICAL-Final 6/9/2023 Approved EVAN COOPER
PLUMBING-Final 6/9/2023 Approved EVAN COOPER
Final 6/26/2023 Corrections Issued EVAN COOPER
Green Building Final 6/26/2023 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 6/26/2023 SGSOV Approved EVAN COOPER
Service/Power Release 6/26/2023 Not Ready for Inspection EVAN COOPER
Smoke Detectors 6/26/2023 Approved EVAN COOPER
Final 7/12/2023 OK to Issue CofO EVAN COOPER
Service/Power Release 7/12/2023 Approved EVAN COOPER