1048 E PALMS BLVD 90291
Certificate Information: 1048 E PALMS BLVD 90291
- Application / Permit
- 20014-30000-03999
- Plan Check / Job No.
- B20WL04020
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel of (E) SFD to rearrange all rooms, add (N) bedrooms and bathrooms. Addition to (E) SFD connecting the SFD to an (E) detached garage and coverting the garage to a living room.
- Permit Issued
- Issued on 2/18/2022
- Issuing Office
- Current Status
- CofO Issued on 7/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 1/25/2021 | JAHANSHAH POURHASSAN |
| Quality Review Completed | 2/4/2021 | TARIK SAOUD |
| Building Plans Picked Up | 2/5/2021 | APPLICANT |
| Applicant returned to address corrections | 7/9/2021 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 7/22/2021 | JAHANSHAH POURHASSAN |
| Issued | 2/18/2022 | APPLICANT |
| CofO in Progress | 7/15/2023 | RICHARD STEINBACH |
| Permit Finaled | 7/17/2023 | DANIEL ORRANTE |
| CofO Issued | 7/17/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/17/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 3/11/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/14/2021 | DENNIS BRAGIN |
| Low Impact Development | Cleared | 6/3/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/21/2021 | DENNIS BRAGIN |
Contact Information
| Architect | Gonzalez,, Jose Antonio; Lic. No.: C33472 | 6210 WILSHIRE BLVD SUITE 209 LOS ANGELES, CA 90048 |
| Contractor | Sun Developers Inc; Lic. No.: 865631-B | 23371 MULHOLLAND DRIVE #295 WOODLAND HILLS, CA 91364 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/30/2022 | Partial Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 7/5/2022 | Corrections Issued | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 7/8/2022 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 7/8/2022 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 8/24/2022 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2022 | Partial Approval | DAVID FEILER |
| Green Building Rough | 8/24/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 8/30/2022 | Partial Approval | DAVID FEILER |
| Special/Order Compliance | 8/30/2022 | Partial Inspection | CLAYTON GRAHAM |
| HVAC-Rough | 9/6/2022 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 9/22/2022 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 10/6/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 10/11/2022 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 10/27/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Deputy Drilled-In Anchors | 11/1/2022 | Conditional Approval | DAVID FEILER |
| ELECTRICAL-Rough | 11/2/2022 | Corrections Issued | DAVID FEILER |
| Underground Mechanical | 11/2/2022 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 11/4/2022 | Approved | DAVID FEILER |
| HVAC-Rough | 11/4/2022 | Corrections Issued | DAVID FEILER |
| Underground Mechanical | 11/4/2022 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 11/18/2022 | Partial Approval | DAVID FEILER |
| Green Building Rough | 11/18/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 11/18/2022 | Approved | DAVID FEILER |
| Insulation | 11/18/2022 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 11/18/2022 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 11/23/2022 | Partial Approval | DAVID FEILER |
| Green Building Rough | 11/23/2022 | Not Ready for Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 12/8/2022 | Not Ready for Inspection | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 12/9/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 12/9/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Shower Pan | 12/12/2022 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 12/13/2022 | Approved | EVAN COOPER |
| Green Building Rough | 12/13/2022 | Approved | EVAN COOPER |
| Insulation | 12/21/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 12/21/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 1/5/2023 | Approved | EVAN COOPER |
| HVAC-Final | 5/23/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 6/6/2023 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 6/6/2023 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Final | 6/13/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 6/15/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 6/15/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 6/15/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Gas Test | 6/20/2023 | Approved | EVAN COOPER |
| Final | 6/26/2023 | Corrections Issued | EVAN COOPER |
| Green Building Final | 6/26/2023 | Approved | EVAN COOPER |
| Smoke Detectors | 6/26/2023 | Approved | EVAN COOPER |
| Final | 7/12/2023 | Conditional Approval | EVAN COOPER |
| Service/Power Release | 7/12/2023 | Approved | EVAN COOPER |