1048 E PALMS BLVD 90291

Certificate Information: 1048 E PALMS BLVD 90291

Application / Permit
20014-30000-03999
Plan Check / Job No.
B20WL04020
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel of (E) SFD to rearrange all rooms, add (N) bedrooms and bathrooms. Addition to (E) SFD connecting the SFD to an (E) detached garage and coverting the garage to a living room.
Permit Issued
Issued on 2/18/2022
Issuing Office
Current Status
CofO Issued on 7/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2021 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 JAHANSHAH POURHASSAN
Corrections Issued 1/25/2021 JAHANSHAH POURHASSAN
Quality Review Completed 2/4/2021 TARIK SAOUD
Building Plans Picked Up 2/5/2021 APPLICANT
Applicant returned to address corrections 7/9/2021 JAHANSHAH POURHASSAN
Plan Check Approved 7/22/2021 JAHANSHAH POURHASSAN
Issued 2/18/2022 APPLICANT
CofO in Progress 7/15/2023 RICHARD STEINBACH
Permit Finaled 7/17/2023 DANIEL ORRANTE
CofO Issued 7/17/2023 DANIEL ORRANTE
Permit Finaled 7/17/2023 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 3/11/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 3/14/2021 DENNIS BRAGIN
Low Impact Development Cleared 6/3/2021 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 7/21/2021 DENNIS BRAGIN

Contact Information

Architect Gonzalez,, Jose Antonio; Lic. No.: C33472 6210 WILSHIRE BLVD SUITE 209      LOS ANGELES, CA 90048
Contractor Sun Developers Inc; Lic. No.: 865631-B 23371 MULHOLLAND DRIVE #295      WOODLAND HILLS, CA 91364
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/30/2022 Partial Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 7/5/2022 Corrections Issued DAVID FEILER
Excavation/Setback/Form/Re-Bar 7/8/2022 Approved DAVID FEILER
Footing/Foundation/Slab 7/8/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 8/24/2022 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 8/24/2022 Partial Approval DAVID FEILER
Green Building Rough 8/24/2022 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 8/30/2022 Partial Approval DAVID FEILER
Special/Order Compliance 8/30/2022 Partial Inspection CLAYTON GRAHAM
HVAC-Rough 9/6/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 9/22/2022 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Rough 10/6/2022 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 10/11/2022 Partial Approval DAVID FEILER
HVAC-Rough 10/27/2022 Not Ready for Inspection JESUS RODRIGUEZ
Deputy Drilled-In Anchors 11/1/2022 Conditional Approval DAVID FEILER
ELECTRICAL-Rough 11/2/2022 Corrections Issued DAVID FEILER
Underground Mechanical 11/2/2022 Not Ready for Inspection DAVID FEILER
ELECTRICAL-Rough 11/4/2022 Approved DAVID FEILER
HVAC-Rough 11/4/2022 Corrections Issued DAVID FEILER
Underground Mechanical 11/4/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 11/18/2022 Partial Approval DAVID FEILER
Green Building Rough 11/18/2022 Not Ready for Inspection DAVID FEILER
HVAC-Rough 11/18/2022 Approved DAVID FEILER
Insulation 11/18/2022 Partial Approval DAVID FEILER
PLUMBING-Rough 11/18/2022 Approved DAVID FEILER
BUILDING-Rough-Frame 11/23/2022 Partial Approval DAVID FEILER
Green Building Rough 11/23/2022 Not Ready for Inspection DAVID FEILER
Interior/Exterior Lathing 12/8/2022 Not Ready for Inspection CLAYTON GRAHAM
Interior/Exterior Lathing 12/9/2022 Approved JESUS RODRIGUEZ
Shower Pan 12/9/2022 Corrections Issued JESUS RODRIGUEZ
Shower Pan 12/12/2022 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 12/13/2022 Approved EVAN COOPER
Green Building Rough 12/13/2022 Approved EVAN COOPER
Insulation 12/21/2022 Approved JESUS RODRIGUEZ
Shower Pan 12/21/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 1/5/2023 Approved EVAN COOPER
HVAC-Final 5/23/2023 Approved EVAN COOPER
ELECTRICAL-Final 6/6/2023 Corrections Issued EVAN COOPER
PLUMBING-Rough 6/6/2023 Corrections Issued EVAN COOPER
ELECTRICAL-Final 6/13/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 6/15/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 6/15/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/15/2023 SGSOV Approved JESUS RODRIGUEZ
Gas Test 6/20/2023 Approved EVAN COOPER
Final 6/26/2023 Corrections Issued EVAN COOPER
Green Building Final 6/26/2023 Approved EVAN COOPER
Smoke Detectors 6/26/2023 Approved EVAN COOPER
Final 7/12/2023 Conditional Approval EVAN COOPER
Service/Power Release 7/12/2023 Approved EVAN COOPER