13610 W BAYLISS ROAD 90049

Certificate Information: 13610 W BAYLISS ROAD 90049

Application / Permit
20014-30000-03971
Plan Check / Job No.
B20WL03986
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Interior remodel and 2-story addition to an existing two-story, wood framed single family dwelling with attached garage.
Permit Issued
Issued on 5/11/2021
Issuing Office
Current Status
CofO Issued on 4/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2020 APPLICANT
Assigned to Plan Check Engineer 10/7/2020 KAMRAN GHOTBI RAVANDI
Corrections Issued 10/13/2020 KAMRAN GHOTBI RAVANDI
Quality Review Completed 10/13/2020 CHIHARU SUZUKI
Building Plans Picked Up 10/20/2020 APPLICANT
Applicant returned to address corrections 4/7/2021 KAMRAN GHOTBI RAVANDI
Plan Check Approved 4/26/2021 KAMRAN GHOTBI RAVANDI
Issued 5/11/2021 APPLICANT
CofO in Progress 4/28/2022 JUAN VALENZUELA
Permit Finaled 4/28/2022 DANIEL ORRANTE
CofO Issued 4/28/2022 DANIEL ORRANTE
Permit Finaled 4/28/2022 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/1/2021 TRACY TATE
BHO/Hillside ordinance Cleared 4/1/2021 TRACY TATE
BHO/Hillside ordinance Cleared 4/1/2021 TRACY TATE
BHO/Hillside ordinance Cleared 4/1/2021 TRACY TATE
Eng Process Fee Ord 176,300 Cleared 4/1/2021 TRACY TATE
Low Impact Development Cleared 4/1/2021 JORGE MEJIA LEMUS
BHO/Hillside ordinance Cleared 4/5/2021 TRACY TATE
Roof/Waste drainage to street Cleared 4/5/2021 TRACY TATE
Sewer availability Cleared 4/20/2021 HISASHI KOBAYAKAWA

Contact Information

Architect Sandoval,, Gabriel Louis; Lic. No.: C31457 2045 WALGROVE AVENUE      LOS ANGELES, CA 90066
Contractor Pacific Southwest Builders Inc; Lic. No.: 553992-B 703 PIER AVE SUITE B #706      HERMOSA BEACH, CA 90254
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

KEVIN SARGSYAN, (310) 914-3889 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/13/2021 No Access for Inspection KENNETH NAGLE
Deputy Drilled-In Anchors 5/21/2021 No Access for Inspection KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 5/28/2021 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 5/28/2021 Partial Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 6/4/2021 Conditional Approval ROBERT SHELLY
Deputy Reinf. Concrete 6/4/2021 Conditional Approval ROBERT SHELLY
Footing/Foundation/Slab 6/9/2021 Approved BRENDAN LOONEY
Deputy Drilled-In Anchors 6/22/2021 Conditional Approval BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 7/15/2021 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Partial Approval JUAN VALENZUELA
Wood Frame 10/4/2021 Partial Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/23/2021 Partial Approval KRISTEN CAUSEY
Service/Power Release 11/23/2021 Not Ready for Inspection KRISTEN CAUSEY
HVAC-Rough 11/24/2021 Corrections Issued DEANDRE HOFFMAN
PLUMBING-Rough 12/10/2021 Approved JUAN VALENZUELA
Pre-Inspection 12/15/2021 Approved JUAN VALENZUELA
Insulation 12/28/2021 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 1/7/2022 Corrections Issued JUAN VALENZUELA
HVAC-Rough 1/7/2022 Approved JUAN VALENZUELA
Rough-Elec/Plmb/HVAC 1/7/2022 Partial Inspection JUAN VALENZUELA
Shower Pan 1/7/2022 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 1/11/2022 Approved JUAN VALENZUELA
ELECTRICAL-Rough 1/11/2022 Approved JUAN VALENZUELA
Green Building Rough 1/11/2022 Not Ready for Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 1/11/2022 Approved JUAN VALENZUELA
Green Building Rough 1/18/2022 Approved JUAN VALENZUELA
Insulation 1/18/2022 Approved JUAN VALENZUELA
Drywall Nailing 2/1/2022 Approved JUAN VALENZUELA
Interior/Exterior Lathing 2/14/2022 Approved JUAN VALENZUELA
HVAC-Final 4/6/2022 Partial Approval JUAN VALENZUELA
Pre-Inspection 4/6/2022 Partial Inspection JUAN VALENZUELA
ELECTRICAL-Final 4/22/2022 Approved JUAN VALENZUELA
Final 4/22/2022 Corrections Issued JUAN VALENZUELA
Green Building Final 4/22/2022 Approved JUAN VALENZUELA
HVAC-Final 4/22/2022 Approved JUAN VALENZUELA
PLUMBING-Final 4/22/2022 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 4/22/2022 SGSOV Not Ready JUAN VALENZUELA
Smoke Detectors 4/22/2022 Approved JUAN VALENZUELA
Gas Test 4/26/2022 Approved JUAN VALENZUELA
PLUMBING-Final 4/26/2022 Approved JUAN VALENZUELA
Final 4/27/2022 OK to Issue CofO JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 4/27/2022 SGSOV Approved JUAN VALENZUELA
Service/Power Release 4/27/2022 Approved JUAN VALENZUELA