8849 S KITTYHAWK AVE 90045

Certificate Information: 8849 S KITTYHAWK AVE 90045

Application / Permit
20014-30000-03943
Plan Check / Job No.
B20WL03940
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One story addition at rear of sfd. All work per WFPP.
Permit Issued
Issued on 11/20/2020
Issuing Office
Current Status
CofO Issued on 11/22/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2020 APPLICANT
Assigned to Plan Check Engineer 9/15/2020 MANUEL GARCIA
Corrections Issued 9/17/2020 MANUEL GARCIA
Plan Check Approved 10/23/2020 RICHARD GARCIA
Building Plans Picked Up 11/17/2020 APPLICANT
Issued 11/20/2020 APPLICANT
CofO in Progress 11/6/2021 DAVID FEILER
Permit Finaled 11/22/2021 DANIEL ORRANTE
CofO Issued 11/22/2021 DANIEL ORRANTE
Permit Finaled 11/22/2021 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/30/2020 DENNIS BRAGIN
Sewer availability Cleared 9/30/2020 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 10/7/2020 DENNIS BRAGIN
ZA Case Cleared 10/7/2020 KEVIN FULTON

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/9/2021 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 4/22/2021 Approved BRENDAN LOONEY
Footing/Foundation/Slab 4/22/2021 Approved BRENDAN LOONEY
PLUMBING-Rough 4/22/2021 Approved BRENDAN LOONEY
ELECTRICAL-Rough 6/7/2021 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 6/7/2021 Corrections Issued BRENDAN LOONEY
Wood Frame 6/7/2021 Partial Approval BRENDAN LOONEY
ELECTRICAL-Rough 6/14/2021 Approved JUAN VALENZUELA
PLUMBING-Rough 6/14/2021 Corrections Issued JUAN VALENZUELA
Interior/Exterior Lathing 6/18/2021 Approved DONALD GALLAGHER
PLUMBING-Rough 6/18/2021 Approved DONALD GALLAGHER
Insulation 6/21/2021 Conditional Approval BRENDAN LOONEY
Drywall Nailing 6/29/2021 Approved BRENDAN LOONEY
Green Building Rough 6/29/2021 Approved BRENDAN LOONEY
HVAC-Rough 6/29/2021 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 8/17/2021 Approved BRENDAN LOONEY
Final 8/17/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 8/17/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 8/17/2021 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 8/17/2021 Not Ready for Inspection BRENDAN LOONEY
Final 8/31/2021 Not Ready for Inspection BRENDAN LOONEY
Green Building Final 8/31/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 8/31/2021 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 8/31/2021 Not Ready for Inspection BRENDAN LOONEY
Final 9/27/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 9/27/2021 Not Ready for Inspection BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 9/27/2021 SGSOV Approved BRENDAN LOONEY
Smoke Detectors 9/27/2021 Not Ready for Inspection BRENDAN LOONEY
Final 10/5/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 10/5/2021 Approved BRENDAN LOONEY
Service/Power Release 10/5/2021 Approved BRENDAN LOONEY
Smoke Detectors 10/5/2021 Approved BRENDAN LOONEY
Final 11/1/2021 OK to Issue CofO DAVID FEILER