3334 W MADERA AVE 90039
Certificate Information: 3334 W MADERA AVE 90039
- Application / Permit
- 20014-30000-03911
- Plan Check / Job No.
- B20WL03923
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- remodel and addition to existing SFD.
- Permit Issued
- Issued on 3/25/2021
- Issuing Office
- Current Status
- CofO Issued on 11/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | TARIK SAOUD |
| Corrections Issued | 9/20/2020 | TARIK SAOUD |
| Quality Review Completed | 9/28/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 1/21/2021 | TARIK SAOUD |
| Building Plans Picked Up | 1/22/2021 | APPLICANT |
| Applicant returned to address corrections | 2/22/2021 | TARIK SAOUD |
| Plan Check Approved | 3/11/2021 | TARIK SAOUD |
| Issued | 3/25/2021 | APPLICANT |
| CofO in Progress | 10/21/2021 | HAMIK HARTOUNIAN |
| Permit Finaled | 11/5/2021 | DEROLD HAUFF |
| CofO Issued | 11/5/2021 | DEROLD HAUFF |
| Permit Finaled | 11/5/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 11/24/2020 | TARIK SAOUD |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2020 | CECILIO NAVARRO |
| Frnt yard landscape/Water mgmt | Cleared | 12/1/2020 | RICHARD REASER |
| Sewer availability | Cleared | 12/4/2020 | CECILIO NAVARRO |
| ZI | Cleared | 12/7/2020 | RICHARD REASER |
| Roof/Waste drainage to street | Cleared | 12/21/2020 | ARMEN MEHRABIAN |
| Excavation more than 5-ft deep | Cleared | 1/21/2021 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Boules,, George Helmy; Lic. No.: C64144 | 29082 MADRID PL CASTAIC, CA 91384 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/12/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 4/22/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 4/27/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 5/10/2021 | Approved | PAUL BECKER |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Pre-Inspection | 6/1/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2021 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 6/11/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/11/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Grounding or Bonding | 6/17/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 7/2/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/2/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 7/2/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 7/8/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Green Building Rough | 7/8/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 7/8/2021 | Approved | HAMIK HARTOUNIAN |
| Insulation | 7/8/2021 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 7/13/2021 | Approved | RICHARD STEINBACH |
| Gas Test | 7/13/2021 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 7/13/2021 | Partial Approval | RICHARD STEINBACH |
| Shower Pan | 7/15/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 7/21/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Shower Pan | 7/21/2021 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 8/11/2021 | Partial Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 8/31/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Final | 8/31/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Service/Power Release | 8/31/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Service/Power Release | 9/10/2021 | Not Required | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/8/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 10/8/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 10/8/2021 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 10/8/2021 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 10/8/2021 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 10/8/2021 | SGSOV Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 10/8/2021 | Not Required | HAMIK HARTOUNIAN |
| Smoke Detectors | 10/8/2021 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/21/2021 | Approved | HAMIK HARTOUNIAN |
| Final | 10/21/2021 | OK to Issue CofO | HAMIK HARTOUNIAN |