3334 W MADERA AVE 90039

Certificate Information: 3334 W MADERA AVE 90039

Application / Permit
20014-30000-03911
Plan Check / Job No.
B20WL03923
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
remodel and addition to existing SFD.
Permit Issued
Issued on 3/25/2021
Issuing Office
Current Status
CofO Issued on 11/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 TARIK SAOUD
Corrections Issued 9/20/2020 TARIK SAOUD
Quality Review Completed 9/28/2020 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 1/21/2021 TARIK SAOUD
Building Plans Picked Up 1/22/2021 APPLICANT
Applicant returned to address corrections 2/22/2021 TARIK SAOUD
Plan Check Approved 3/11/2021 TARIK SAOUD
Issued 3/25/2021 APPLICANT
CofO in Progress 10/21/2021 HAMIK HARTOUNIAN
Permit Finaled 11/5/2021 DEROLD HAUFF
CofO Issued 11/5/2021 DEROLD HAUFF
Permit Finaled 11/5/2021 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 11/24/2020 TARIK SAOUD
Eng Process Fee Ord 176,300 Cleared 11/25/2020 CECILIO NAVARRO
Frnt yard landscape/Water mgmt Cleared 12/1/2020 RICHARD REASER
Sewer availability Cleared 12/4/2020 CECILIO NAVARRO
ZI Cleared 12/7/2020 RICHARD REASER
Roof/Waste drainage to street Cleared 12/21/2020 ARMEN MEHRABIAN
Excavation more than 5-ft deep Cleared 1/21/2021 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Boules,, George Helmy; Lic. No.: C64144 29082 MADRID PL      CASTAIC, CA 91384

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/12/2021 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 4/22/2021 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 4/27/2021 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 5/10/2021 Approved PAUL BECKER
Floor/Roof Diaphrgm/Shear Wall 5/24/2021 Corrections Issued HAMIK HARTOUNIAN
Pre-Inspection 6/1/2021 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/2/2021 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 6/11/2021 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 6/11/2021 Conditional Approval HAMIK HARTOUNIAN
Grounding or Bonding 6/17/2021 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 7/2/2021 Approved HAMIK HARTOUNIAN
HVAC-Rough 7/2/2021 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 7/2/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 7/8/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 7/8/2021 Approved HAMIK HARTOUNIAN
HVAC-Rough 7/8/2021 Approved HAMIK HARTOUNIAN
Insulation 7/8/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 7/13/2021 Approved RICHARD STEINBACH
Gas Test 7/13/2021 Approved RICHARD STEINBACH
Interior/Exterior Lathing 7/13/2021 Partial Approval RICHARD STEINBACH
Shower Pan 7/15/2021 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 7/21/2021 Partial Approval HAMIK HARTOUNIAN
Shower Pan 7/21/2021 Approved HAMIK HARTOUNIAN
Pre-Inspection 8/11/2021 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Final 8/31/2021 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Final 8/31/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Service/Power Release 8/31/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Service/Power Release 9/10/2021 Not Required HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/8/2021 Corrections Issued HAMIK HARTOUNIAN
Final 10/8/2021 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/8/2021 Approved HAMIK HARTOUNIAN
Green Building Final 10/8/2021 Approved HAMIK HARTOUNIAN
Green Building Rough 10/8/2021 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 10/8/2021 SGSOV Approved HAMIK HARTOUNIAN
Service/Power Release 10/8/2021 Not Required HAMIK HARTOUNIAN
Smoke Detectors 10/8/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/21/2021 Approved HAMIK HARTOUNIAN
Final 10/21/2021 OK to Issue CofO HAMIK HARTOUNIAN