12022 W MARINE ST 90066
Certificate Information: 12022 W MARINE ST 90066
- Application / Permit
- 20014-30000-03906
- Plan Check / Job No.
- B20WL03917
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition w/ roof trusses to (E) 1 story SFD.
- Permit Issued
- Issued on 1/22/2021
- Issuing Office
- Current Status
- CofO Issued on 11/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 11/6/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 11/12/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 1/21/2021 | VLADIMIR ARUTYUNYAN |
| Issued | 1/22/2021 | APPLICANT |
| Building Plans Picked Up | 1/25/2021 | APPLICANT |
| CofO in Progress | 11/8/2021 | KENNETH NAGLE |
| Permit Finaled | 11/8/2021 | KENNETH NAGLE |
| CofO Issued | 11/8/2021 | KENNETH NAGLE |
| Permit Finaled | 11/8/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Permit | Cleared | 11/19/2020 | DINAH GARIN |
| Sewer availability | Cleared | 11/20/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 12/30/2020 | ORVAL HERNANDEZ-MARCI |
| Trees in Parkway | Cleared | 1/7/2021 | JOHN KIM |
| Roof/Waste drainage to street | Cleared | 1/8/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 1/21/2021 | VLADIMIR ARUTYUNYAN |
| Grading Pre-Inspection | Cleared | 1/21/2021 | VLADIMIR ARUTYUNYAN |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/24/2021 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 3/31/2021 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 5/19/2021 | Conditional Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 5/19/2021 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2021 | Corrections Issued | EVAN COOPER |
| HVAC-Rough | 5/19/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 5/19/2021 | Approved | EVAN COOPER |
| Shower Pan | 5/25/2021 | Approved | ADAM ESCOTO |
| ELECTRICAL-Rough | 5/28/2021 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 6/8/2021 | Conditional Approval | EVAN COOPER |
| Green Building Rough | 6/8/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/8/2021 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 6/16/2021 | Conditional Approval | EVAN COOPER |
| Insulation | 6/16/2021 | Conditional Approval | EVAN COOPER |
| Drywall Nailing | 6/28/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/28/2021 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 9/8/2021 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 9/29/2021 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 10/28/2021 | Approved | JOHNNY MIRANDA |
| Final | 10/28/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Final | 10/28/2021 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Final | 10/28/2021 | Corrections Issued | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 10/28/2021 | SGSOV Not Ready | JOHNNY MIRANDA |
| Service/Power Release | 10/28/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Smoke Detectors | 10/28/2021 | Approved | JOHNNY MIRANDA |
| Final | 11/2/2021 | Conditional Approval | JOHNNY MIRANDA |
| Green Building Final | 11/2/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Final | 11/2/2021 | Approved | JOHNNY MIRANDA |
| SGSOV-Seismic Gas S/O Valve | 11/2/2021 | SGSOV Approved | JOHNNY MIRANDA |
| Service/Power Release | 11/2/2021 | Approved | JOHNNY MIRANDA |