1835 S ORANGE DR 90019
Certificate Information: 1835 S ORANGE DR 90019
- Application / Permit
- 20014-30000-03888
- Plan Check / Job No.
- B20WL03908
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO AND CONVERSION OF (E) DETACHED GARAGE TO ADU AT REAR OF THE LOT PER LAMC 12.22A33(c) & (d).
- Permit Issued
- Issued on 4/12/2021
- Issuing Office
- Current Status
- CofO Issued on 3/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | JAHANSHAH POURHASSAN |
| Corrections Issued | 9/25/2020 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 11/10/2020 | MARJAN SHENASI |
| Applicant returned to address corrections | 2/24/2021 | ALFREDO JARA |
| Plan Check Approved | 3/8/2021 | ALFREDO JARA |
| Issued | 4/12/2021 | APPLICANT |
| Building Plans Picked Up | 4/20/2021 | APPLICANT |
| CofO in Progress | 3/3/2022 | JOSE AVILA |
| CofO Issued | 3/24/2022 | DEROLD HAUFF |
| Permit Finaled | 3/24/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/15/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2020 | ELAINE LEI |
| Sewer availability | Cleared | 11/24/2020 | ELAINE LEI |
| Construction near power lines | Cleared | 12/23/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 12/23/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/22/2021 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 2/9/2021 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 2/26/2021 | ELAINE LEI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baich,, Brendon Chad; Lic. No.: C83347 | 1898 WILDROSE AVE POMONA, CA 91767 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 5/21/2021 | Conditional Approval | RYAN BARNES |
| Footing/Foundation/Slab | 5/21/2021 | Not Ready for Inspection | RYAN BARNES |
| FLOOD-Elevation Certificate | 6/2/2021 | Approved | RUBEN SALAS |
| Underground Mechanical | 6/2/2021 | Partial Approval | RUBEN SALAS |
| PLUMBING-Rough | 6/14/2021 | Partial Approval | STUART CHAPMAN |
| Sewer | 6/14/2021 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 6/21/2021 | Approved | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 6/23/2021 | Approved | RONALD KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/30/2021 | Partial Approval | HORACE FULTZ |
| BUILDING-Rough-Frame | 9/8/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/8/2021 | Approved | FREDDIE RIVERA |
| FLOOD-Proofing Certificate | 9/8/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2021 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 9/8/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| HVAC-Rough | 9/8/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 9/8/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 9/8/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/14/2021 | Corrections Issued | THOMAS LOGRASSO |
| FLOOD-Proofing Certificate | 9/14/2021 | Partial Inspection | THOMAS LOGRASSO |
| Green Building Rough | 9/14/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 9/14/2021 | Corrections Issued | THOMAS LOGRASSO |
| Underground Mechanical | 9/14/2021 | Partial Approval | THOMAS LOGRASSO |
| Deputy Wood Construction | 9/15/2021 | Conditional Approval | CALEB MEISTER |
| BUILDING-Rough-Frame | 9/16/2021 | Approved | STUART CHAPMAN |
| FLOOD-Proofing Certificate | 9/16/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 9/16/2021 | Partial Approval | STUART CHAPMAN |
| Insulation | 9/20/2021 | Corrections Issued | CALEB MEISTER |
| Drywall Nailing | 10/7/2021 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/19/2021 | Approved | JOSE AVILA |
| Special/Order Compliance | 11/4/2021 | Approved | ALIZAH MAYAGOITIA |
| Final | 11/24/2021 | Corrections Issued | JOSE AVILA |
| Green Building Final | 11/24/2021 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 11/24/2021 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 11/24/2021 | Approved | JOSE AVILA |
| Final | 12/7/2021 | Corrections Issued | JOSE AVILA |
| Green Building Final | 12/7/2021 | Approved | JOSE AVILA |
| Final | 2/16/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 2/23/2022 | Not Ready for Inspection | JOSE AVILA |
| Final | 3/2/2022 | OK to Issue CofO | JOSE AVILA |