1338 S COMSTOCK AVE 90024

Certificate Information: 1338 S COMSTOCK AVE 90024

Application / Permit
20014-30000-03831
Plan Check / Job No.
B20WL03837
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1st & 2nd story addition & interior remodel of (E) 2 story SFD with attached garage.
Permit Issued
Issued on 3/3/2021
Issuing Office
Current Status
CofO Issued on 10/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/7/2020 APPLICANT
Assigned to Plan Check Engineer 9/30/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 11/6/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 11/12/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 2/3/2021 VLADIMIR ARUTYUNYAN
Issued 3/3/2021 APPLICANT
Building Plans Picked Up 3/4/2021 APPLICANT
CofO in Progress 9/26/2023 STEPHANIE SWANSON
Permit Finaled 10/7/2023 DANIEL ORRANTE
CofO Issued 10/7/2023 DANIEL ORRANTE
Permit Finaled 10/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Trees in Parkway Cleared 1/11/2021 JOHN KIM
Permit Cleared 1/13/2021 DINAH GARIN
Sewer availability Cleared 1/13/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 1/14/2021 DINAH GARIN
Low Impact Development Cleared 1/15/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/15/2021 DINAH GARIN
GPI Written Notices Cleared 2/3/2021 VLADIMIR ARUTYUNYAN
Grading Pre-Inspection Cleared 2/3/2021 VLADIMIR ARUTYUNYAN

Contact Information

Contractor Snow Construction; Lic. No.: 1016716-B 3268 HILLOCK DRIVE      LOS ANGELES, CA 90068
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/27/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 5/3/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 5/10/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 5/10/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 5/10/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Subgrade 5/10/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 5/11/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 5/11/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 5/11/2021 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Subgrade 5/11/2021 Approved GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 5/20/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Reinforced Concrete Frame 5/20/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 7/16/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Posting Pre-Inspection 7/20/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 7/26/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 7/27/2021 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 8/2/2021 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 8/11/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 8/11/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 9/3/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 10/8/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 10/19/2021 Partial Approval BRENDAN LOONEY
Footing/Foundation/Slab 10/19/2021 Partial Approval BRENDAN LOONEY
Wood Frame 10/19/2021 Not Ready for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 10/21/2021 Corrections Issued BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 10/21/2021 Corrections Issued BRENDAN LOONEY
HVAC-Rough 10/21/2021 Corrections Issued BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Partial Approval BRENDAN LOONEY
PLUMBING-Rough 10/22/2021 Corrections Issued BRENDAN LOONEY
Wood Frame 10/22/2021 Not Ready for Inspection BRENDAN LOONEY
Deputy Wood Construction 10/25/2021 Conditional Approval BRENDAN LOONEY
ELECTRICAL-Rough 10/27/2021 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Approved BRENDAN LOONEY
Footing/Foundation/Slab 10/27/2021 Partial Approval BRENDAN LOONEY
HVAC-Rough 10/27/2021 Approved BRENDAN LOONEY
PLUMBING-Rough 10/27/2021 Approved BRENDAN LOONEY
Wood Frame 10/27/2021 Corrections Issued BRENDAN LOONEY
Green Building Rough 11/2/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 11/2/2021 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 11/10/2021 Corrections Issued BRENDAN LOONEY
Insulation 11/10/2021 Partial Approval BRENDAN LOONEY
METHANE-Rough 11/10/2021 Approved BRENDAN LOONEY
Special/Order Compliance 11/10/2021 Corrections Issued BRENDAN LOONEY
Sewer 11/18/2021 Conditional Approval BRENDAN LOONEY
Shower Pan 11/18/2021 Approved BRENDAN LOONEY
Drywall Nailing 11/23/2021 Partial Approval RYAN SALAZAR
Drywall Nailing 12/2/2021 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 12/2/2021 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 12/6/2021 No Access for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 12/8/2021 Partial Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 1/27/2022 Corrections Issued BRENDAN LOONEY
Pre-Inspection 2/3/2022 Corrections Issued BRENDAN LOONEY
Special/Order Compliance 2/3/2022 Partial Inspection MICHAEL PELHAM
PLUMBING-Final 5/25/2022 Not Ready for Inspection BRENDAN LOONEY
Special/Order Compliance 5/25/2022 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 6/22/2022 Approved MICHAEL PELHAM
ELECTRICAL-Final 6/22/2022 Not Ready for Inspection MICHAEL PELHAM
Footing/Foundation/Slab 6/22/2022 Approved MICHAEL PELHAM
Gas Test 6/22/2022 Approved MICHAEL PELHAM
PLUMBING-Final 6/22/2022 Approved MICHAEL PELHAM
Special/Order Compliance 6/22/2022 Partial Inspection HERBERT GIRON
ELECTRICAL-Final 8/2/2022 Corrections Issued PATRICK QUALEY
Final 8/2/2022 Not Ready for Inspection PATRICK QUALEY
Green Building Final 8/2/2022 Not Ready for Inspection PATRICK QUALEY
HVAC-Final 8/2/2022 Corrections Issued PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 8/2/2022 SGSOV Approved PATRICK QUALEY
Smoke Detectors 8/2/2022 Approved PATRICK QUALEY
ELECTRICAL-Final 8/18/2022 Not Ready for Inspection ANDREW NAVE
Final 8/18/2022 Corrections Issued ANDREW NAVE
Green Building Final 8/18/2022 Corrections Issued ANDREW NAVE
HVAC-Final 8/18/2022 Corrections Issued ANDREW NAVE
ELECTRICAL-Final 9/1/2022 Approved STEPHANIE SWANSON
Final 9/1/2022 Partial Approval STEPHANIE SWANSON
Green Building Final 9/1/2022 Approved STEPHANIE SWANSON
HVAC-Final 9/1/2022 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 9/1/2022 SGSOV Approved STEPHANIE SWANSON
Service/Power Release 9/1/2022 Approved STEPHANIE SWANSON
Special/Order Compliance 9/1/2022 Partial Inspection MICHAEL PELHAM
Final 9/26/2023 Conditional Approval STEPHANIE SWANSON