2115 S GLYNDON AVE 90291

Certificate Information: 2115 S GLYNDON AVE 90291

Application / Permit
20014-30000-03811
Plan Check / Job No.
B20WL03810
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL & ADDITION TO (E) SFD
Permit Issued
Issued on 12/22/2020
Issuing Office
Current Status
CofO Issued on 3/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2020 APPLICANT
Assigned to Plan Check Engineer 9/23/2020 VLADIMIR ARUTYUNYAN
Corrections Issued 9/30/2020 VLADIMIR ARUTYUNYAN
Quality Review Completed 10/9/2020 KAMRAN GHOTBI RAVANDI
Plan Check Approved 12/15/2020 VLADIMIR ARUTYUNYAN
Building Plans Picked Up 12/15/2020 APPLICANT
Issued 12/22/2020 APPLICANT
CofO in Progress 2/17/2022 DAVID FEILER
Permit Finaled 3/8/2022 DANIEL ORRANTE
CofO Issued 3/8/2022 DANIEL ORRANTE
Permit Finaled 3/8/2022 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 11/5/2020 ROBIN YAMADA
Eng Process Fee Ord 176,300 Cleared 11/19/2020 HISASHI KOBAYAKAWA
Sewer availability Cleared 11/19/2020 HISASHI KOBAYAKAWA
Specific Plan Cleared 11/30/2020 PEDRO AYALA
Roof/Waste drainage to street Cleared 12/21/2020 HISASHI KOBAYAKAWA

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Zepeda General Building; Lic. No.: 1028796-B 9525 HUNT AVE      SOUTH GATE, CA 90280
Engineer Namdar,, Mansour Tom; Lic. No.: S2976 16867 SEVERO PLACE      ENCINO, CA 91436

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/12/2021 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 1/13/2021 Partial Approval DAVID HEINE
Excavation/Setback/Form/Re-Bar 1/26/2021 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 1/26/2021 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 2/8/2021 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/15/2021 Partial Approval JOHNNY MIRANDA
HVAC-Rough 4/19/2021 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 4/30/2021 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 4/30/2021 Approved JOHNNY MIRANDA
PLUMBING-Rough 4/30/2021 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 5/5/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 5/10/2021 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 5/11/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/18/2021 Partial Approval JOHNNY MIRANDA
Insulation 5/21/2021 Approved JOHNNY MIRANDA
Drywall Nailing 6/2/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 6/9/2021 Partial Approval ADAM ESCOTO
ELECTRICAL-Final 1/24/2022 Corrections Issued DAVID FEILER
HVAC-Final 1/24/2022 Corrections Issued DAVID FEILER
PLUMBING-Final 1/24/2022 Corrections Issued DAVID FEILER
ELECTRICAL-Final 2/7/2022 Approved RYAN SALAZAR
Gas Test 2/7/2022 Approved RYAN SALAZAR
HVAC-Final 2/7/2022 Partial Approval RYAN SALAZAR
PLUMBING-Final 2/7/2022 Approved RYAN SALAZAR
BUILDING-Rough-Frame 2/10/2022 Approved DAVID FEILER
Final 2/10/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 2/10/2022 Approved DAVID FEILER
Green Building Final 2/10/2022 Approved DAVID FEILER
Green Building Rough 2/10/2022 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 2/10/2022 SGSOV Approved DAVID FEILER
Smoke Detectors 2/10/2022 Approved DAVID FEILER
Final 2/14/2022 Partial Inspection DAVID FEILER
Final 2/16/2022 OK to Issue CofO DAVID FEILER
Service/Power Release 2/23/2022 Approved RICHARD STEINBACH