712 N CITRUS AVE 90038

Certificate Information: 712 N CITRUS AVE 90038

Application / Permit
20014-30000-03808
Plan Check / Job No.
B20WL03808
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
major addition to existing DFD keeping only a small porion of wall and foundation.
Permit Issued
Issued on 2/26/2021
Issuing Office
Current Status
CofO Issued on 12/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2020 APPLICANT
Assigned to Plan Check Engineer 9/9/2020 FELIPE HERNANDEZ
Corrections Issued 9/18/2020 FELIPE HERNANDEZ
Quality Review Completed 9/28/2020 TARIK SAOUD
Applicant returned to address corrections 10/21/2020 FELIPE HERNANDEZ
Applicant returned to address corrections 11/10/2020 FELIPE HERNANDEZ
Applicant returned to address corrections 12/28/2020 FELIPE HERNANDEZ
Applicant returned to address corrections 1/6/2021 FELIPE HERNANDEZ
Plan Check Approved 1/26/2021 FELIPE HERNANDEZ
Issued 2/26/2021 APPLICANT
Building Plans Picked Up 3/2/2021 APPLICANT
CofO in Progress 12/6/2021 BRIAN SULLIVAN
Permit Finaled 12/13/2021 DEROLD HAUFF
CofO Issued 12/13/2021 DEROLD HAUFF
Permit Finaled 12/13/2021 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 10/20/2020 JUAN ASHTON
Hydrant and Access approval Cleared 11/23/2020 MATTHEW CRAIG
Low Impact Development Cleared 12/3/2020 ORVAL HERNANDEZ-MARCI
Eng Process Fee Ord 176,300 Cleared 12/10/2020 JUAN ASHTON
Roof/Waste drainage to street Cleared 12/10/2020 JUAN ASHTON

Contact Information

Architect Mohazab,, Ahmad; Lic. No.: C17636 2747 19TH STREET      SAN FRANCISCO, CA 94110
Contractor Owner-Builder       ,
Engineer Moeini,, Soheil; Lic. No.: C84000 11022 SANTA MONICA BLVD STE 440      LOS ANGELES, CA 90025

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Methane Barrier 3/2/2021 No Access for Inspection ELMER BLAND
Excavation/Setback/Form/Re-Bar 3/16/2021 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 3/16/2021 Not Ready for Inspection BRIAN SULLIVAN
METHANE-Barrier 3/16/2021 Approved BRIAN SULLIVAN
METHANE-Subgrade 3/16/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 3/16/2021 Order to Comply Issued BRIAN SULLIVAN
Footing/Foundation/Slab 3/17/2021 Partial Approval BRIAN SULLIVAN
METHANE-Rough 3/22/2021 Approved RAUL BARAJAS
Underground Mechanical 3/22/2021 Approved RAUL BARAJAS
Deputy Methane Barrier 3/23/2021 Approved RAUL BARAJAS
Deputy Methane Barrier 3/24/2021 Conditional Approval BRIAN SULLIVAN
Gas Test 3/30/2021 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 3/30/2021 SGSOV Not Ready RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 5/13/2021 Partial Approval BRIAN SULLIVAN
Masonry Wall/Backfill 5/13/2021 Corrections Issued BRIAN SULLIVAN
Deputy Wood Construction 5/14/2021 Conditional Approval ROBERT CORNELL
Masonry Wall/Backfill 5/18/2021 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 6/11/2021 Corrections Issued BRIAN SULLIVAN
Masonry Wall/Backfill 6/14/2021 No Access for Inspection JOSEPH MCGARRY
PLUMBING-Rough 6/24/2021 Approved BRIAN SULLIVAN
HVAC-Rough 7/2/2021 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 7/6/2021 Corrections Issued BRIAN SULLIVAN
Gas Test 7/6/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 7/13/2021 Partial Inspection RAUL BARAJAS
ELECTRICAL-Rough 7/13/2021 Approved RAUL BARAJAS
Green Building Rough 7/13/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 7/13/2021 Not Ready for Inspection RAUL BARAJAS
Shower Pan 7/13/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 7/20/2021 Partial Approval BRIAN SULLIVAN
Drywall Nailing 7/29/2021 Approved RAUL BARAJAS
Interior/Exterior Lathing 7/29/2021 Not Ready for Inspection RAUL BARAJAS
Interior/Exterior Lathing 8/20/2021 Partial Approval BRIAN SULLIVAN
Gas Test 10/13/2021 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 10/13/2021 SGSOV Not Ready ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 10/18/2021 SGSOV Not Ready ARTHUR SARGSYAN
Service/Power Release 10/18/2021 Corrections Issued ARTHUR SARGSYAN
ELECTRICAL-Final 11/17/2021 Not Ready for Inspection BRIAN SULLIVAN
HVAC-Final 11/17/2021 Not Ready for Inspection BRIAN SULLIVAN
Service/Power Release 11/17/2021 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Final 11/23/2021 Approved BRIAN SULLIVAN
HVAC-Final 11/23/2021 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 11/23/2021 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 11/23/2021 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 11/24/2021 Approved BRIAN SULLIVAN
Final 11/24/2021 Corrections Issued BRIAN SULLIVAN
Footing/Foundation/Slab 11/24/2021 Approved BRIAN SULLIVAN
Green Building Final 11/24/2021 Approved BRIAN SULLIVAN
Service/Power Release 11/24/2021 Approved BRIAN SULLIVAN
Smoke Detectors 11/24/2021 Approved BRIAN SULLIVAN
Final 12/3/2021 Partial Inspection RAUL BARAJAS
PLUMBING-Final 12/3/2021 Approved RAUL BARAJAS
Service/Power Release 12/3/2021 Partial Inspection RAUL BARAJAS
Final 12/6/2021 OK to Issue CofO BRIAN SULLIVAN