2007 S HILLSBORO AVE 90034
Certificate Information: 2007 S HILLSBORO AVE 90034
- Application / Permit
- 20014-30000-03692
- Plan Check / Job No.
- B20WL03710
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST AND 2ND STORY ADDITION AND MAJOR REMODEL TO EXISTING 1-STORY TYPE VB SINGLE FAMILY DWELLING, EQUIPPED THROUGHOUT WITH NFPA-13D COMPLIANT FIRE SPRINKLERS.
- Permit Issued
- Issued on 6/8/2021
- Issuing Office
- Current Status
- CofO Issued on 8/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2020 | SERGIO SILVA |
| Corrections Issued | 10/5/2020 | SERGIO SILVA |
| Quality Review Completed | 10/15/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 10/16/2020 | APPLICANT |
| Applicant returned to address corrections | 4/28/2021 | SERGIO SILVA |
| Plan Check Approved | 5/19/2021 | SERGIO SILVA |
| Issued | 6/8/2021 | APPLICANT |
| CofO in Progress | 8/15/2022 | OGANES TARAKHCHYAN |
| Permit Finaled | 8/18/2022 | DANIEL ORRANTE |
| CofO Issued | 8/18/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/18/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Miscellaneous | Cleared | 10/28/2020 | DENZEL HENDERSON |
| Permit | Cleared | 11/30/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2020 | DINAH GARIN |
| Sewer availability | Cleared | 12/2/2020 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 1/25/2021 | KURT CORRAL |
| Trees in Parkway | Cleared | 2/4/2021 | JOHN KIM |
| Low Impact Development | Cleared | 4/7/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 4/16/2021 | DENNIS BRAGIN |
| GPI Written Notices | Cleared | 6/2/2021 | SERGIO SILVA |
| Grading Pre-Inspection | Cleared | 6/2/2021 | SERGIO SILVA |
| Green Code | Cleared | 6/2/2021 | SERGIO SILVA |
| Miscellaneous | Cleared | 6/2/2021 | SERGIO SILVA |
Contact Information
| Architect | Lynch,, Todd Michael; Lic. No.: C35996 | 1068 YALE STREET SANTA MONICA, CA 90403 |
| Contractor | El Reef Construction Inc; Lic. No.: 978074-B | 19528 VENTURA BLVD #629 TARZANA, CA 91356 |
| Engineer | Ekmekji,, Steve Eli; Lic. No.: C66727 | 19281 BERCLAIR LANE TARZANA, CA 91356 |
| Engineer | Scott,, Raymond J; Lic. No.: C14356 | 44263 CHARLOTTE DR HEMET, CA 92544 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/24/2021 | Approved | JOHNNY MIRANDA |
| Pre-Inspection | 6/28/2021 | Partial Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/8/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Barrier | 7/8/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 7/8/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 8/3/2021 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 8/4/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Barrier | 8/4/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Subgrade | 8/4/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 8/5/2021 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 8/6/2021 | No Result Entered | RONALD WEBER |
| Deputy Drilled-In Anchors | 8/11/2021 | No Access for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 8/13/2021 | Partial Approval | JUAN VALENZUELA |
| METHANE-Barrier | 8/13/2021 | Approved | JUAN VALENZUELA |
| METHANE-Subgrade | 8/13/2021 | Approved | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 8/16/2021 | No Result Entered | RONALD WEBER |
| Footing/Foundation/Slab | 8/18/2021 | Approved | KEVIN SARGSYAN |
| Deputy Steel/Welding | 9/1/2021 | Conditional Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/2/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 9/2/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Rough | 9/2/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/2/2021 | Corrections Issued | KEVIN SARGSYAN |
| Structural Steel Frame | 9/3/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2021 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/7/2021 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2021 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 9/10/2021 | Conditional Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 9/27/2021 | Conditional Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2021 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2021 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/17/2021 | Partial Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/17/2021 | Partial Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/23/2021 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 11/23/2021 | Approved | KEVIN SARGSYAN |
| Sewer | 11/23/2021 | Approved | KEVIN SARGSYAN |
| Underground Mechanical | 11/23/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2021 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 11/24/2021 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 11/24/2021 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 12/1/2021 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/1/2021 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 12/1/2021 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 12/7/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 12/7/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 12/7/2021 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 12/14/2021 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 12/14/2021 | Approved | KEVIN SARGSYAN |
| Insulation | 12/20/2021 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 12/28/2021 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/28/2021 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 12/30/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 12/30/2021 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 3/4/2022 | Conditional Approval | KEVIN SARGSYAN |
| Masonry Wall/Backfill | 3/9/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 4/11/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 4/13/2022 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Final | 4/13/2022 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 4/18/2022 | Approved | KEVIN SARGSYAN |
| Gas Test | 4/19/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 4/19/2022 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 4/22/2022 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 4/22/2022 | Approved | KEVIN SARGSYAN |
| Final | 7/6/2022 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 7/6/2022 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 7/6/2022 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 7/6/2022 | Approved | KEVIN SARGSYAN |
| Final | 7/26/2022 | Corrections Issued | STEPHANIE SWANSON |
| Service/Power Release | 7/26/2022 | Approved | STEPHANIE SWANSON |
| Final | 8/12/2022 | OK to Issue CofO | OGANES TARAKHCHYAN |