2007 S HILLSBORO AVE 90034

Certificate Information: 2007 S HILLSBORO AVE 90034

Application / Permit
20014-30000-03692
Plan Check / Job No.
B20WL03710
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST AND 2ND STORY ADDITION AND MAJOR REMODEL TO EXISTING 1-STORY TYPE VB SINGLE FAMILY DWELLING, EQUIPPED THROUGHOUT WITH NFPA-13D COMPLIANT FIRE SPRINKLERS.
Permit Issued
Issued on 6/8/2021
Issuing Office
Current Status
CofO Issued on 8/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2020 APPLICANT
Assigned to Plan Check Engineer 9/23/2020 SERGIO SILVA
Corrections Issued 10/5/2020 SERGIO SILVA
Quality Review Completed 10/15/2020 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 10/16/2020 APPLICANT
Applicant returned to address corrections 4/28/2021 SERGIO SILVA
Plan Check Approved 5/19/2021 SERGIO SILVA
Issued 6/8/2021 APPLICANT
CofO in Progress 8/15/2022 OGANES TARAKHCHYAN
Permit Finaled 8/18/2022 DANIEL ORRANTE
CofO Issued 8/18/2022 DANIEL ORRANTE
Permit Finaled 8/18/2022 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 10/28/2020 DENZEL HENDERSON
Permit Cleared 11/30/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 12/2/2020 DINAH GARIN
Sewer availability Cleared 12/2/2020 DINAH GARIN
Hydrant and Access approval Cleared 1/25/2021 KURT CORRAL
Trees in Parkway Cleared 2/4/2021 JOHN KIM
Low Impact Development Cleared 4/7/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 4/16/2021 DENNIS BRAGIN
GPI Written Notices Cleared 6/2/2021 SERGIO SILVA
Grading Pre-Inspection Cleared 6/2/2021 SERGIO SILVA
Green Code Cleared 6/2/2021 SERGIO SILVA
Miscellaneous Cleared 6/2/2021 SERGIO SILVA

Contact Information

Architect Lynch,, Todd Michael; Lic. No.: C35996 1068 YALE STREET      SANTA MONICA, CA 90403
Contractor El Reef Construction Inc; Lic. No.: 978074-B 19528 VENTURA BLVD #629      TARZANA, CA 91356
Engineer Ekmekji,, Steve Eli; Lic. No.: C66727 19281 BERCLAIR LANE      TARZANA, CA 91356
Engineer Scott,, Raymond J; Lic. No.: C14356 44263 CHARLOTTE DR      HEMET, CA 92544

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/24/2021 Approved JOHNNY MIRANDA
Pre-Inspection 6/28/2021 Partial Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 7/8/2021 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Barrier 7/8/2021 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 7/8/2021 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 8/3/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 8/4/2021 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Barrier 8/4/2021 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 8/4/2021 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 8/5/2021 Partial Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 8/6/2021 No Result Entered RONALD WEBER
Deputy Drilled-In Anchors 8/11/2021 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 8/13/2021 Partial Approval JUAN VALENZUELA
METHANE-Barrier 8/13/2021 Approved JUAN VALENZUELA
METHANE-Subgrade 8/13/2021 Approved JUAN VALENZUELA
Deputy Reinf. Concrete 8/16/2021 No Result Entered RONALD WEBER
Footing/Foundation/Slab 8/18/2021 Approved KEVIN SARGSYAN
Deputy Steel/Welding 9/1/2021 Conditional Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 9/2/2021 Not Ready for Inspection KEVIN SARGSYAN
Green Building Rough 9/2/2021 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Rough 9/2/2021 Approved KEVIN SARGSYAN
PLUMBING-Rough 9/2/2021 Corrections Issued KEVIN SARGSYAN
Structural Steel Frame 9/3/2021 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/7/2021 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 9/7/2021 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/9/2021 Conditional Approval KEVIN SARGSYAN
Deputy Wood Construction 9/10/2021 Conditional Approval KEVIN SARGSYAN
Deputy Wood Construction 9/27/2021 Conditional Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 9/28/2021 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/18/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 11/17/2021 Partial Inspection KEVIN SARGSYAN
PLUMBING-Rough 11/17/2021 Partial Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 11/23/2021 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 11/23/2021 Approved KEVIN SARGSYAN
Sewer 11/23/2021 Approved KEVIN SARGSYAN
Underground Mechanical 11/23/2021 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/24/2021 Approved KEVIN SARGSYAN
Green Building Rough 11/24/2021 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 11/24/2021 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 12/1/2021 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 12/1/2021 Partial Approval KEVIN SARGSYAN
Shower Pan 12/1/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 12/7/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 12/7/2021 Not Ready for Inspection OGANES TARAKHCHYAN
HVAC-Rough 12/7/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 12/14/2021 Approved KEVIN SARGSYAN
Green Building Rough 12/14/2021 Approved KEVIN SARGSYAN
Insulation 12/20/2021 Approved KEVIN SARGSYAN
Drywall Nailing 12/28/2021 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 12/28/2021 Approved KEVIN SARGSYAN
Drywall Nailing 12/30/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Final 12/30/2021 Corrections Issued KEVIN SARGSYAN
Deputy Drilled-In Anchors 3/4/2022 Conditional Approval KEVIN SARGSYAN
Masonry Wall/Backfill 3/9/2022 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 4/11/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Final 4/13/2022 Corrections Issued KEVIN SARGSYAN
HVAC-Final 4/13/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Final 4/18/2022 Approved KEVIN SARGSYAN
Gas Test 4/19/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Final 4/19/2022 Corrections Issued KEVIN SARGSYAN
Gas Test 4/22/2022 Approved KEVIN SARGSYAN
PLUMBING-Final 4/22/2022 Approved KEVIN SARGSYAN
Final 7/6/2022 Corrections Issued KEVIN SARGSYAN
Green Building Final 7/6/2022 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 7/6/2022 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 7/6/2022 Approved KEVIN SARGSYAN
Final 7/26/2022 Corrections Issued STEPHANIE SWANSON
Service/Power Release 7/26/2022 Approved STEPHANIE SWANSON
Final 8/12/2022 OK to Issue CofO OGANES TARAKHCHYAN