2222 N MANDEVILLE CANYON ROAD 90049
Certificate Information: 2222 N MANDEVILLE CANYON ROAD 90049
- Application / Permit
- 20014-30000-03608
- Plan Check / Job No.
- B20WL03652
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion & addition to 1 story (E) detached garage & storage room to 2 story ADU with attached ground floor garage & rec room.
- Permit Issued
- Issued on 3/15/2021
- Issuing Office
- Current Status
- Issued on 3/15/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2020 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 9/25/2020 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 9/29/2020 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 12/16/2020 | APPLICANT |
| Plan Check Approved | 3/10/2021 | VLADIMIR ARUTYUNYAN |
| Issued | 3/15/2021 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/2/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/2/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/2/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/2/2020 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 12/2/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2020 | DINAH GARIN |
| Sewer availability | Cleared | 12/14/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 1/12/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/15/2021 | MAHELET GEBEYHU |
| Watercourse | Cleared | 1/15/2021 | MAHELET GEBEYHU |
| Hydrant and Access approval | Cleared | 1/25/2021 | JOHN CONNEALLY |
| GPI Written Notices | Cleared | 2/10/2021 | VLADIMIR ARUTYUNYAN |
| Grading Pre-Inspection | Cleared | 2/10/2021 | VLADIMIR ARUTYUNYAN |
| Address approval | Cleared | 3/2/2021 | OSCAR GUTIERREZ |
Contact Information
| Architect | Bambrough,, Patrick; Lic. No.: C34299 | 4132 ALLA ROAD LOS ANGELES, CA 90066 |
| Architect | Cichowski,, Joel Brennan; Lic. No.: C30916 | 1618 OCEAN PARK BOULEVARD SANTA MONICA, CA 90405 |
| Contractor | Paragon Construction Inc; Lic. No.: 1044734-B | 553 N PACIFIC COAST HWY #126 REDONDO BEACH, CA 90277 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/19/2021 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/19/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Underground Mechanical | 3/19/2021 | Partial Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 3/22/2021 | Partial Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/1/2021 | Approved | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2021 | Partial Inspection | JUAN VALENZUELA |
| Underground Mechanical | 6/1/2021 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 7/29/2021 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 7/29/2021 | Partial Inspection | JUAN VALENZUELA |
| Underground Mechanical | 8/11/2021 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 9/17/2021 | Partial Inspection | JUAN VALENZUELA |
| Underground Mechanical | 9/17/2021 | Partial Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 9/30/2021 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 10/12/2021 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 10/12/2021 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 10/21/2021 | Approved | JUAN VALENZUELA |
| FLOOD-Proofing Certificate | 10/21/2021 | Approved | JUAN VALENZUELA |
| Green Building Rough | 10/21/2021 | Approved | JUAN VALENZUELA |
| Insulation | 10/21/2021 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 10/21/2021 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 10/21/2021 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 10/29/2021 | Partial Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 12/3/2021 | Partial Approval | JUAN VALENZUELA |
| Shower Pan | 12/3/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 1/27/2022 | Approved | MICHAEL PELHAM |
| Sewer | 5/20/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Final | 2/13/2023 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Final | 2/21/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 4/13/2023 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 5/9/2023 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 5/11/2023 | Approved | KEVIN SARGSYAN |