11150 N HAYVENHURST AVE 91344

Certificate Information: 11150 N HAYVENHURST AVE 91344

Application / Permit
20014-30000-03603
Plan Check / Job No.
B20WL03649
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ADU 1,200 sq.ft per LAMC 12.22A.33(c) and (d)
Permit Issued
Issued on 6/29/2021
Issuing Office
Current Status
CofO Issued on 4/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 DAVID CASTILLO
Corrections Issued 9/25/2020 DAVID CASTILLO
Quality Review Completed 10/1/2020 TARIK SAOUD
Building Plans Picked Up 3/3/2021 APPLICANT
Applicant returned to address corrections 4/22/2021 DAVID CASTILLO
Plan Check Approved 5/27/2021 DAVID CASTILLO
Issued 6/29/2021 APPLICANT
CofO in Progress 4/4/2022 DAVID SCANTLIN
Permit Finaled 4/20/2022 JOHN JANSON
CofO Issued 4/20/2022 JOHN JANSON
Permit Finaled 4/20/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/2/2020 GUILLERMO PETRA
Grading Pre-Inspection Cleared 10/19/2020 PATRICK MISCHLICH
Low Impact Development Cleared 1/14/2021 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 1/20/2021 GUILLERMO PETRA
Hydrant and Access approval Cleared 2/16/2021 MATTHEW CRAIG
Roof/Waste drainage to street Cleared 2/16/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/17/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/20/2021 Not Ready for Inspection DAVID SCANTLIN
Underground Mechanical 7/23/2021 Corrections Issued DAVID SCANTLIN
Underground Mechanical 7/27/2021 Approved DAVID SCANTLIN
Footing/Foundation/Slab 8/9/2021 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 9/14/2021 Approved DAVID SCANTLIN
ELECTRICAL-Rough 9/23/2021 Corrections Issued DEANDRE HOFFMAN
HVAC-Rough 9/23/2021 Not Ready for Inspection DEANDRE HOFFMAN
PLUMBING-Rough 9/23/2021 Approved DEANDRE HOFFMAN
HVAC-Rough 9/28/2021 Approved DAVID SCANTLIN
Interior/Exterior Lathing 10/29/2021 Partial Approval DAVID SCANTLIN
Wood Frame 10/29/2021 Approved DAVID SCANTLIN
Insulation 11/5/2021 Approved MORRIS JACKSON
Drywall Nailing 11/15/2021 Approved DAVID SCANTLIN
Green Building Rough 11/15/2021 Approved DAVID SCANTLIN
Sewer 12/6/2021 Approved DAVID SCANTLIN
Underground Mechanical 12/6/2021 Approved DAVID SCANTLIN
ELECTRICAL-Final 2/2/2022 Approved SEAN WIRCH
Gas Test 2/2/2022 Approved SEAN WIRCH
HVAC-Final 2/2/2022 Approved SEAN WIRCH
PLUMBING-Final 2/2/2022 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 2/2/2022 SGSOV Approved SEAN WIRCH
BUILDING-Rough-Frame 3/21/2022 Approved DAVID SCANTLIN
Final 3/21/2022 Corrections Issued DAVID SCANTLIN
Green Building Final 3/21/2022 Approved DAVID SCANTLIN
MERV13>=Final 3/21/2022 Approved DAVID SCANTLIN
MERV13>=Rough 3/21/2022 Approved DAVID SCANTLIN
Service/Power Release 3/21/2022 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 3/21/2022 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 3/21/2022 Approved DAVID SCANTLIN
Final 4/1/2022 OK to Issue CofO DAVID SCANTLIN
Service/Power Release 4/1/2022 Approved DAVID SCANTLIN