10320 W CHEVIOT DR 90064

Certificate Information: 10320 W CHEVIOT DR 90064

Application / Permit
20014-30000-03492
Plan Check / Job No.
B20WL03515
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-Story addiation to an (E) 2-Story house
Permit Issued
Issued on 12/24/2020
Issuing Office
Current Status
CofO Issued on 10/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/18/2020 APPLICANT
Assigned to Plan Check Engineer 8/20/2020 MARJAN SHENASI
Corrections Issued 8/24/2020 MARJAN SHENASI
Applicant returned to address corrections 9/14/2020 JAHANSHAH POURHASSAN
Plan Check Approved 9/15/2020 JAHANSHAH POURHASSAN
Issued 12/24/2020 APPLICANT
Building Plans Picked Up 12/29/2020 APPLICANT
CofO in Progress 10/21/2021 KEVIN SARGSYAN
Permit Finaled 10/26/2021 KENNETH NAGLE
CofO Issued 10/26/2021 KENNETH NAGLE
Permit Finaled 10/26/2021 KENNETH NAGLE

Permit Application Clearance Information

Specific Plan Cleared 8/25/2020 DYLAN SITTIG
Roof/Waste drainage to street Cleared 8/26/2020 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/28/2020 DINAH GARIN
Specific Plan Cleared 9/3/2020 FREDDY GARCIA
Grading Pre-Inspection Cleared 9/15/2020 MARJAN SHENASI

Contact Information

Contractor Forsyth Construction Inc; Lic. No.: 560243-B 578 WASHINGTON BLVD #377      MARINA DEL REY, CA 90292

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/8/2021 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 4/14/2021 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 4/29/2021 Approved KEVIN SARGSYAN
Wood Frame 5/6/2021 Partial Approval KEVIN SARGSYAN
Insulation 5/13/2021 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/19/2021 Partial Approval KEVIN SARGSYAN
Deputy Wood Construction 6/11/2021 Conditional Approval KEVIN SARGSYAN
ELECTRICAL-Rough 7/8/2021 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Approved KEVIN SARGSYAN
Green Building Rough 7/8/2021 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 7/8/2021 Approved KEVIN SARGSYAN
PLUMBING-Rough 7/8/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 7/14/2021 Approved KEVIN SARGSYAN
Green Building Rough 7/14/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 7/14/2021 Partial Approval KEVIN SARGSYAN
Insulation 7/20/2021 Approved KEVIN SARGSYAN
Drywall Nailing 7/28/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 7/28/2021 Not Ready for Inspection KEVIN SARGSYAN
Shower Pan 7/28/2021 Approved KEVIN SARGSYAN
Final 10/14/2021 Corrections Issued KEVIN SARGSYAN
Green Building Final 10/14/2021 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 10/14/2021 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 10/14/2021 Approved KEVIN SARGSYAN
Final 10/21/2021 OK to Issue CofO KEVIN SARGSYAN