10320 W CHEVIOT DR 90064
Certificate Information: 10320 W CHEVIOT DR 90064
- Application / Permit
- 20014-30000-03492
- Plan Check / Job No.
- B20WL03515
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-Story addiation to an (E) 2-Story house
- Permit Issued
- Issued on 12/24/2020
- Issuing Office
- Current Status
- CofO Issued on 10/26/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2020 | MARJAN SHENASI |
| Corrections Issued | 8/24/2020 | MARJAN SHENASI |
| Applicant returned to address corrections | 9/14/2020 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 9/15/2020 | JAHANSHAH POURHASSAN |
| Issued | 12/24/2020 | APPLICANT |
| Building Plans Picked Up | 12/29/2020 | APPLICANT |
| CofO in Progress | 10/21/2021 | KEVIN SARGSYAN |
| Permit Finaled | 10/26/2021 | KENNETH NAGLE |
| CofO Issued | 10/26/2021 | KENNETH NAGLE |
| Permit Finaled | 10/26/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/25/2020 | DYLAN SITTIG |
| Roof/Waste drainage to street | Cleared | 8/26/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2020 | DINAH GARIN |
| Specific Plan | Cleared | 9/3/2020 | FREDDY GARCIA |
| Grading Pre-Inspection | Cleared | 9/15/2020 | MARJAN SHENASI |
Contact Information
| Contractor | Forsyth Construction Inc; Lic. No.: 560243-B | 578 WASHINGTON BLVD #377 MARINA DEL REY, CA 90292 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/8/2021 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/14/2021 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/29/2021 | Approved | KEVIN SARGSYAN |
| Wood Frame | 5/6/2021 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 5/13/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2021 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 6/11/2021 | Conditional Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 7/8/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2021 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 7/8/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 7/8/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/8/2021 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 7/14/2021 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 7/14/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 7/14/2021 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 7/20/2021 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 7/28/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 7/28/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Shower Pan | 7/28/2021 | Approved | KEVIN SARGSYAN |
| Final | 10/14/2021 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 10/14/2021 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 10/14/2021 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 10/14/2021 | Approved | KEVIN SARGSYAN |
| Final | 10/21/2021 | OK to Issue CofO | KEVIN SARGSYAN |