3201 S CORINTH AVE 90066
Certificate Information: 3201 S CORINTH AVE 90066
- Application / Permit
- 20014-30000-03462
- Plan Check / Job No.
- B20WL03495
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 281 sf addition and interior remodeling to (e) one story SFD. Per engineering design.
- Permit Issued
- Issued on 11/25/2020
- Issuing Office
- Current Status
- CofO Issued on 7/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/31/2020 | ALFREDO JARA |
| Corrections Issued | 9/1/2020 | ALFREDO JARA |
| Applicant returned to address corrections | 10/5/2020 | JASON JANGADA |
| Applicant returned to address corrections | 11/13/2020 | JASON JANGADA |
| Plan Check Approved | 11/18/2020 | JASON JANGADA |
| Issued | 11/25/2020 | APPLICANT |
| Building Plans Picked Up | 11/30/2020 | APPLICANT |
| CofO in Progress | 6/27/2022 | JOHNNY MIRANDA |
| Permit Finaled | 7/6/2022 | DANIEL ORRANTE |
| CofO Issued | 7/6/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/6/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/25/2020 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2020 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 9/12/2020 | DENNIS BRAGIN |
| Sewer availability | Cleared | 9/12/2020 | DENNIS BRAGIN |
| ZA Case | Cleared | 10/8/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 10/8/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 10/8/2020 | DENZEL HENDERSON |
| Specific Plan | Cleared | 11/5/2020 | VALERIA CEJA |
Contact Information
| Contractor | Lightning Construction & Design Inc; Lic. No.: 951122-B | 6047 TAMPA AVE #303 TARZANA, CA 91356 |
| Engineer | Ilasin,, John Lacebal; Lic. No.: C67469 | 1011 OARFISH LN OXNARD, CA 93035 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/16/2020 | No Access for Inspection | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 12/21/2020 | Corrections Issued | RICHARD ROBLES |
| Footing/Foundation/Slab | 12/28/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 12/30/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 1/5/2021 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2021 | Approved | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 1/27/2021 | Approved | RICHARD ROBLES |
| Green Building Rough | 1/27/2021 | Not Ready for Inspection | RICHARD ROBLES |
| MERV13>=Rough | 1/27/2021 | Not Ready for Inspection | RICHARD ROBLES |
| Excavation/Setback/Form/Re-Bar | 2/5/2021 | Approved | RICHARD ROBLES |
| Rough-Elec/Plmb/HVAC | 2/22/2021 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/24/2021 | Approved | RICHARD ROBLES |
| Green Building Rough | 2/24/2021 | Approved | RICHARD ROBLES |
| MERV13>=Rough | 2/24/2021 | Approved | RICHARD ROBLES |
| Shower Pan | 2/24/2021 | Approved | RICHARD ROBLES |
| Insulation | 3/4/2021 | Approved | RICHARD ROBLES |
| Interior/Exterior Lathing | 3/4/2021 | Partial Approval | RICHARD ROBLES |
| Drywall Nailing | 3/16/2021 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 4/14/2021 | Approved | EVAN COOPER |
| Final | 8/20/2021 | Corrections Issued | KENNETH NAGLE |
| Green Building Final | 8/20/2021 | Not Ready for Inspection | KENNETH NAGLE |
| MERV13>=Final | 8/20/2021 | Not Ready for Inspection | KENNETH NAGLE |
| SGSOV-Seismic Gas S/O Valve | 8/20/2021 | SGSOV Approved | KENNETH NAGLE |
| Smoke Detectors | 8/20/2021 | Approved | KENNETH NAGLE |
| Final | 8/26/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 8/26/2021 | Approved | OGANES TARAKHCHYAN |
| MERV13>=Final | 8/26/2021 | Approved | OGANES TARAKHCHYAN |
| Final | 1/20/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Final | 6/9/2022 | OK to Issue CofO | JOHNNY MIRANDA |