3361 N ANDRITA ST 90065

Certificate Information: 3361 N ANDRITA ST 90065

Application / Permit
20014-30000-03401
Plan Check / Job No.
B20WL03406
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSE ADDITION OF 407 SQ FT AT THE REAR OF THE (E) 1-STORY SFD .
Permit Issued
Issued on 11/4/2021
Issuing Office
Current Status
CofO Issued on 2/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2020 APPLICANT
Assigned to Plan Check Engineer 8/14/2020 ALFREDO JARA
Corrections Issued 8/14/2020 ALFREDO JARA
Plan Check Approved 2/26/2021 ALFREDO JARA
Issued 11/4/2021 APPLICANT
Building Plans Picked Up 11/18/2021 APPLICANT
CofO in Progress 12/29/2022 HAMIK HARTOUNIAN
No Progress 2/11/2023 MICHAEL PELHAM
CofO in Progress 2/15/2023 MICHAEL PELHAM
Permit Finaled 2/19/2023 DEROLD HAUFF
CofO Issued 2/19/2023 DEROLD HAUFF
Permit Finaled 2/19/2023 DEROLD HAUFF

Permit Application Clearance Information

Tenant Habitability Plan Cleared 11/5/2020 ISMAEL HERNANDEZ
Roof/Waste drainage to street Cleared 11/13/2020 JEANIE LAM
Sewer availability Cleared 11/13/2020 JEANIE LAM
Miscellaneous Cleared 11/19/2020 SARAHI ORTEGA
Supp. Use District POD/CDO/TDO Cleared 11/19/2020 SARAHI ORTEGA
Eng Process Fee Ord 176,300 Cleared 2/1/2021 JEANIE LAM
Grading Pre-Inspection Cleared 2/26/2021 ALFREDO JARA

Contact Information

Contractor Advanced Building And Remodeling Inc; Lic. No.: 1064387-B 4470 W SUNSET BLVD #366      LOS ANGELES, CA 90027
Engineer Dominguez,, Refugio; Lic. No.: C50820 254 COTTONWOOD ST      ONTARIO, CA 91761

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/8/2021 Corrections Issued HAMIK HARTOUNIAN
Pre-Inspection 12/3/2021 No Access for Inspection HAMIK HARTOUNIAN
Pre-Inspection 12/9/2021 Partial Approval CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 1/26/2022 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 1/27/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/27/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 1/27/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 2/22/2022 Partial Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 2/22/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 2/22/2022 Partial Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 6/16/2022 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 6/22/2022 Approved HAMIK HARTOUNIAN
Insulation 6/22/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 7/19/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/10/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/12/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 8/22/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/31/2022 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 8/31/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 9/6/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 9/6/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/19/2022 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/6/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 10/6/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/6/2022 Approved HAMIK HARTOUNIAN
Insulation 10/12/2022 No Access for Inspection CHARLES BOGHOSKHAN
Interior/Exterior Lathing 10/12/2022 No Access for Inspection CHARLES BOGHOSKHAN
Shower Pan 10/12/2022 No Access for Inspection CHARLES BOGHOSKHAN
Insulation 10/17/2022 Partial Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/17/2022 Approved HAMIK HARTOUNIAN
Shower Pan 10/17/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Drywall Nailing 10/24/2022 Approved CHARLES BOGHOSKHAN
Shower Pan 10/24/2022 Approved CHARLES BOGHOSKHAN
Floor/Roof Diaphrgm/Shear Wall 12/8/2022 Partial Inspection HAMIK HARTOUNIAN
Pre-Inspection 12/8/2022 Partial Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 12/8/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Sewer 12/8/2022 Corrections Issued HAMIK HARTOUNIAN
Sewer 12/14/2022 Approved HAMIK HARTOUNIAN
Final 12/19/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Gas Test 12/19/2022 Approved HAMIK HARTOUNIAN
Green Building Final 12/19/2022 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 12/19/2022 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 12/19/2022 Approved HAMIK HARTOUNIAN
Final 12/28/2022 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 12/28/2022 Approved HAMIK HARTOUNIAN